2      Management Organization of the Main Construction Companies                 

2.1    Advanced Works Contract                                                                                    

2.2    Deep Cement Mixing (DCM) Works Contracts                                                        

2.3    Main Reclamation Works Contract                                                                         

2.4    Airfield Works Contract                                                                                         

2.5    Terminal 2 Expansion Works Contracts                                                                 

2.6    Automated People Mover Works Contract                                                              

2.7    Baggage Handling System Works Contract                                                            

2.8    Airport Support Infrastructure and Logistic Works Contract                                     

3      Management Organization of the Environmental Team                                  

4      Management Organisation of the Independent Environmental Checker and His Team         

Attachment                                                                                                                      

I.               Organization Chart of the Works Contracts                                               

II.              Organization Chart of the ET and IEC                                                     

 

 

Tables

Table 1: Contact Information of Key Personnel 3

Table 2: Contact Information of ET  5

Table 3: Contact Information of IEC  6

 

 

 


1        Introduction

The Environmental Impact Assessment (EIA) Report (Register No.: AEIAR-185/2014) prepared for the “Expansion of Hong Kong International Airport into a Three-Runway System” (the project) has been approved by the Director of Environmental Protection, and an Environmental Permit (EP) (Permit No.: EP-489/2014) has been issued for the project under the Environmental Impact Assessment Ordinance.

The first, second, third and fourth submission of Management Organizations has been prepared and submitted in November 2015, October 2016, February and August 2017 respectively in accordance with Condition 2.4 of the EP. The purpose of this updated Management Organizations is to provide the latest information based on the recent contracts awarded under this project. This updated Management Organizations includes the following information:

a)    the management organization of the main construction companies and/or any form of joint ventures associated with the construction of the Project (in Section 2);

b)    the management organization of the Environmental Team (ET) (in Section 3);

c)     the management organization of the Independent Environmental Checker (IEC) and his team (in Section 4); and

d)    organization charts, names of responsible persons and their contact details.

 

 

2        Management Organization of the Main Construction Companies

2.1      Advanced Works Contract

Langfang Huayuan Mechanical and Electrical Engineering Co., Ltd. (Contract P560(R)) is the contractor appointed to undertake the diversion of the existing submarine aviation fuel pipelines. Names of the responsible persons and their contact details are set out in Table 1 below.

2.2      Deep Cement Mixing (DCM) Works Contracts

Penta-Ocean-China State-Dong-Ah Joint Venture (Contract 3201), Samsung-Build King Joint Venture (Contract 3202), Sambo E&C Co., Ltd. (Contract 3203), China Road and Bridge-Sambo Joint Venture (Contract 3204) and Bachy Soletanche-Sambo Joint Venture (Contract 3205) are the contractors appointed to undertake the DCM ground improvement works. Names of the responsible persons and their contact details are set out in Table 1 below.

2.3      Main Reclamation Works Contract

Zhen Hua Engineering Company Ltd.-China Communications Construction Company Ltd.-CCCC Dredging (Group) Company Ltd. (ZHEC-CCCC-CDC) Joint Venture (Contract 3206) is the contractor appointed to undertake the main reclamation works. Names of the responsible persons and their contact details are set out in Table 1 below.

2.4      Airfield Works Contract

Fujita Corporation-China Harbour Engineering Company Ltd.-Zhen Hua Engineering Company Ltd. (FJT-CHEC-ZHEC) Joint Venture (Contract 3301) is the contractor appointed to undertake the construction works for the north runway crossover taxiway. Names of the responsible persons and their contact details are set out in Table 1 below.

2.5      Terminal 2 Expansion Works Contracts

Build King Construction Ltd. (Contract 3501) is the contractor appointed to undertake the construction works for antenna farm and sewage pumping station. Build King Construction Ltd. (Contract 3502) is the contractor appointed to undertake Terminal 2 (T2) automated people mover (APM) depot modification works. Leighton–Chun Wo Joint Venture (Contract 3503) is the contractor appointed to undertake T2 foundation and substructure works. Names of the responsible persons and their contact details are set out in Table 1 below.

2.6      Automated People Mover Works Contract

Niigata Transys Company Ltd. (Contract 3602) is the contractor appointed to undertake the existing APM system modification works. Names of the responsible persons and their contact details are set out in Table 1 below.

2.7      Baggage Handling System Works Contract

Vanderlande Industries Hong Kong Limited and Shun Hing Systems Integration Company Limited (Contract 3603) is the contractor appointed to undertake the construction works of baggage handling system (BHS). Names of the responsible persons and their contact details are set out in Table 1 below.

2.8      Airport Support Infrastructure and Logistic Works Contract

China State Construction Engineering (Hong Kong) Ltd. (Contract 3801) is the contractor appointed to undertake the construction works of APM and BHS tunnels on existing airport island. Names of the responsible persons and their contact details are set out in Table 1 below.

Table 1: Contact Information of Key Personnel

Party

Position

Name

Telephone

Email

Contract P560(R) Aviation Fuel Pipeline Diversion Works

(Langfang Huayuan Mechanical and Electrical Engineering Co., Ltd.)

Project Manager

Wei Shih

2117 0566

wei.shih@hycrossing.com

Environmental Officer

Lyn Lau

5172 6543

xiaolin.liu@hycrossing.com

Contract 3201 DCM (Package 1)

(Penta-Ocean-China State-Dong-Ah Joint Venture)

Project Director

Tsugunari Suzuki

9178 9689

tsugunari.suzuki@mail.penta-ocean.co.jp

Environmental Officer

Alan Tam

6119 3107

alan.tam@pentaocean.com.hk

Contract 3202 DCM (Package 2)

(Samsung-Build King Joint Venture)

Project Manager

Ilkwon Nam

9643 3117

ilkwon.nam@samsung.com

Environmental Officer

Dickson Mak

9525 8408

dickson.mak@buildking.hk

Contract 3203 DCM (Package 3)

(Sambo E&C Co., Ltd.)

Project Manager

Eric Kan

9014 6758

eric.kan_oasis@samboenc.com.hk

Environmental Officer

David Hung

9765 6151

davidhung@samboenc.com.hk

Contract 3204 DCM (Package 4)

(CRBC-Sambo Joint Venture)

Project Manager

Kyung Sik Yoo

9683 8697

ksyoo@samboenc.co.kr

Environmental Officer

Kanny Cho

6799 8226

sh.cho@crbc.com.hk

Contract 3205 DCM (Package 5)

(Bachy Soletanche- Sambo Joint Venture)

Deputy Project Director

Min Park

9683 0765

mpark@bsglsambo.com

Environmental Officer

Margaret Chung

9130 3696

margaret.chung@bsglsambo.com

Contractor 3206 Main Reclamation Works (ZHEC-CCCC-CDC Joint Venture)

Project Manager

Kim Chuan Lim

3693 2288

kim.lim@3206.zccjv3rs.com

Environmental Officer

Kwai Fung Wong

3693 2252

kf.wong@3206.zccjv3rs.com

Contract 3301 North Runway Crossover Taxiway

(FJT-CHEC-ZHEC Joint Venture)

Project Manager

Kin Hang Chung

9412 1386

samuel.chung@chechk.com

Contract 3501 Antenna Farm and Sewage Pumping Station

(Build King Construction Ltd.)

Project Manager

 

Raymond Au

 

6985 8860

 

raymondau@buildking.hk

Environmental Officer

Edward Tam

9287 8270

edward.tam@buildking.hk

Contract 3502 T2 APM Depot Modification Works

(Build King Construction Ltd.)

Project Manager

Kivin Cheng

9380 3635

kivin.cheng@buildking.hk

Environmental Officer

Chun Pong Chan

9187 7118

chunpong.chan@buildking.hk

Contract 3503

T2 Foundation and Substructure Works

(Leighton–Chun Wo Joint Venture)

Construction Manager

Stephen O’Donoghue

9732 6787

stephen.odonoghue@lcwjv.com

Environmental Officer

Stephen Tsang

5508 6361

stephen.tsang@lcwjv.com

Contract 3602 Existing APM System Modification Works (Niigata Transys Co., Ltd.)

Project Manager

Kunihiro Tatecho

9755 0351

Kunihiro_tatecho@niigata-transys.com

Environmental Officer

Arthur Wong

9170 3394

arthur.wong@whytecliff.com

Contract 3603

Baggage Handling System

(Vanderlande Industries Hong Kong Ltd. and Shun Hing Systems Integration Co., Ltd.)

Project Manager

Kee Cheung Ho

9272 9626

ho.kee.cheung@shunhinggroup.com

Environmental Officer

Eric Ha

9215 3432

eric.ha@shunhinggroup.com

Contract 3801

APM and BHS Tunnels on Existing Airport Island

(China State Construction Engineering (Hong Kong) Ltd.)

Project Manager

Tony Wong

9642 8672

tony_wong@cohl.com

Environmental Officer

Fredrick Wong

9842 2703

cheukwai_wong@cohl.com

 

Attachment I presents the organization charts of all the above-mentioned contractors required under EP Condition 2.4.

 

 

3        Management Organization of the Environmental Team

The management organization of the Environmental Team (ET), including names of the ET Leader and Deputy ET Leaders and their contact details are set out in Table 2 below:

Table 2: Contact Information of ET

Name

Position

Telephone

Email

Terence Kong

ET Leader

2828 5919

Terence.Kong@mottmac.com

Heidi Yu

Deputy ET Leader

2828 5704

Heidi.Yu@mottmac.com

Keith Chau

Deputy ET Leader

2972 1721

Keith.Chau@atkinsglobal.com

 

Attachment II presents an organization chart of the ET (together with that for the IEC, as described in Section 4 below) required under EP Condition 2.4.

4        Management Organisation of the Independent Environmental Checker and His Team

The management organization of the Independent Environmental Checker (IEC), including names of the IEC and Deputy IEC are set out in Table 3 below:

Table 3: Contact Information of IEC

Name

Position

Telephone

Email

Jackel Law

IEC

3922 9376

jackel.law@aecom.com

Roy Man

Deputy IEC

3922 9376

roy.man@aecom.com

 

Attachment II presents an organization chart of the IEC required under EP Condition 2.4.

 

Attachment

I.        Organization Chart of the Works Contracts                                                                   

II.       Organization Chart of the ET and IEC                                                                        

 

  I.       Organization Chart of the Works Contracts



 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

II.       Organization Chart of the ET and IEC