Expansion of Hong Kong International Airport into a Three-Runway System

Submission of Management Organizations

April 2019

 

 

 

 

Contents

1      Introduction

2      Management Organization of the Main Construction Companies

2.1    Advanced Works Contract

2.2    Deep Cement Mixing (DCM) Works Contracts

2.3    Main Reclamation Works Contract

2.4    Airfield Works Contract

2.5    Third Runway Concourse and Integrated Airport Centers Works Contract

2.6    Terminal 2 Expansion Works Contracts

2.7    Automated People Mover Works Contract

2.8    Baggage Handling System Works Contract

2.9    Airport Support Infrastructure and Logistic Works Contract

3      Management Organization of the Environmental Team

4      Management Organisation of the Independent Environmental Checker and His Team

Attachment

I.               Organization Chart of the Works Contracts

II.              Organization Chart of the ET and IEC

 

 

Tables

Table 1: Contact Information of Key Personnel 3

Table 2: Contact Information of ET  5

Table 3: Contact Information of IEC  6

 

 

 


 

1        Introduction

The Environmental Impact Assessment (EIA) Report (Register No.: AEIAR-185/2014) prepared for the “Expansion of Hong Kong International Airport into a Three-Runway System” (the project) has been approved by the Director of Environmental Protection, and an Environmental Permit (EP) (Permit No.: EP-489/2014) has been issued for the project under the Environmental Impact Assessment Ordinance.

The purpose of this updated Management Organizations is to provide the latest information based on the recent contracts awarded under this project. This updated Management Organizations includes the following information:

a)    the management organization of the main construction companies and/or any form of joint ventures associated with the construction of the Project (in Section 2);

b)    the management organization of the Environmental Team (ET) (in Section 3);

c)     the management organization of the Independent Environmental Checker (IEC) and his team (in Section 4); and

d)    organization charts, names of responsible persons and their contact details.

 

 

2        Management Organization of the Main Construction Companies

2.1      Advanced Works Contract

Langfang Huayuan Mechanical and Electrical Engineering Co., Ltd. (Contract P560(R)) is the contractor appointed to undertake the diversion of the existing submarine aviation fuel pipelines. Names of the responsible persons and their contact details are set out in Table 1 below.

2.2      Deep Cement Mixing (DCM) Works Contracts

Penta-Ocean-China State-Dong-Ah Joint Venture (Contract 3201), Samsung-Build King Joint Venture (Contract 3202), Sambo E&C Co., Ltd. (Contract 3203), China Road and Bridge-Sambo Joint Venture (Contract 3204) and Bachy Soletanche-Sambo Joint Venture (Contract 3205) are the contractors appointed to undertake the DCM ground improvement works. Names of the responsible persons and their contact details are set out in Table 1 below.

2.3      Main Reclamation Works Contract

Zhen Hua Engineering Company Ltd.-China Communications Construction Company Ltd.-CCCC Dredging (Group) Company Ltd. (ZHEC-CCCC-CDC) Joint Venture (Contract 3206) is the contractor appointed to undertake the main reclamation works. Names of the responsible persons and their contact details are set out in Table 1 below.

2.4      Airfield Works Contract

Fujita Corporation-China Harbour Engineering Company Ltd.-Zhen Hua Engineering Company Ltd. (FJT-CHEC-ZHEC) Joint Venture (Contract 3301) is the contractor appointed to undertake the construction works for the north runway crossover taxiway. China Road and Bridge Corporation (Contract 3302) is the contractor appointed to undertake advance works for the eastern vehicular tunnel. Names of the responsible persons and their contact details are set out in Table 1 below.

2.5      Third Runway Concourse and Integrated Airport Centers Works Contract

Wing Hing Construction Co., Ltd. (Contract 3402) is the contractor appointed to undertake enabling works for the new Integrated Airport Centres. Names of the responsible persons and their contact details are set out in Table 1 below.

2.6      Terminal 2 Expansion Works Contracts

Build King Construction Ltd. (Contract 3501) is the contractor appointed to undertake the construction works for antenna farm and sewage pumping station. Build King Construction Ltd. (Contract 3502) is the contractor appointed to undertake Terminal 2 (T2) automated people mover (APM) depot modification works. Leighton–Chun Wo Joint Venture (Contract 3503) is the contractor appointed to undertake T2 foundation and substructure works. Names of the responsible persons and their contact details are set out in Table 1 below.

2.7      Automated People Mover Works Contract

Niigata Transys Company Ltd. (Contract 3602) is the contractor appointed to undertake the existing APM system modification works. Names of the responsible persons and their contact details are set out in Table 1 below.

2.8      Baggage Handling System Works Contract

Vanderlande Industries Hong Kong Limited and Shun Hing Systems Integration Company Limited (Contract 3603) is the contractor appointed to undertake the construction works of baggage handling system (BHS). Names of the responsible persons and their contact details are set out in Table 1 below.

2.9      Airport Support Infrastructure and Logistic Works Contract

China State Construction Engineering (Hong Kong) Ltd. (Contract 3801) is the contractor appointed to undertake the construction works of APM and BHS tunnels on existing airport island. Names of the responsible persons and their contact details are set out in Table 1 below.

Table 1: Contact Information of Key Personnel

Party

Position

Name

Telephone

Email

Contract P560(R) Aviation Fuel Pipeline Diversion Works

(Langfang Huayuan Mechanical and Electrical Engineering Co., Ltd.)

Project Manager

Wei Shih

2117 0566

wei.shih@hycrossing.com

Environmental Officer

Lyn Liu

5172 6543

xiaolin.liu@hycrossing.com

Contract 3201 DCM (Package 1)

(Penta-Ocean-China State-Dong-Ah Joint Venture)

Project Director

Tsugunari Suzuki

9178 9689

tsugunari.suzuki@mail.penta-ocean.co.jp

Environmental Officer

Hiu Yeung Tang

6329 3513

hy.tang@pentaocean.com.hk

Contract 3202 DCM (Package 2)

(Samsung-Build King Joint Venture)

Project Manager

Ilkwon Nam

9643 3117

ilkwon.nam@samsung.com

Environmental Officer

David Man

6421 3238

david.man@sbjv.hk

Contract 3203 DCM (Package 3)

(Sambo E&C Co., Ltd.)

Project Manager

Eric Kan

9014 6758

eric.kan_oasis@samboenc.com.hk

Environmental Officer

David Hung

9765 6151

davidhung@samboenc.com.hk

Contract 3204 DCM (Package 4)

(CRBC-Sambo Joint Venture)

Project Manager

Kyung Sik Yoo

9683 8697

ksyoo@samboenc.co.kr

Contract 3205 DCM (Package 5)

(Bachy Soletanche- Sambo Joint Venture)

Deputy Project Director

Min Park

9683 0765

mpark@bsglsambo.com

Environmental Officer

Michael Wan

6693 3596

michael.wan@bsglsambo.com

Contractor 3206 Main Reclamation Works (ZHEC-CCCC-CDC Joint Venture)

 

 

Project Manager

Kim Chuan Lim

3763 1509

kim.lim@3206.zccjv3rs.com

Environmental Officer

Kwai Fung Wong

3763 1452

kf.wong@3206.zccjv3rs.com

Contract 3301 North Runway Crossover Taxiway

(FJT-CHEC-ZHEC Joint Venture)

Deputy Project Director

Kin Hang Chung

9800 0048

samuel.chung@chechk.com

Environmental Officer

Nelson Tam

9721 3942

nelsontam@fujitaco.com.hk

Contract 3302 Eastern Vehicular Tunnel Advance Works

(China Road and Bridge Corporation)

Project Manager

Raymond Cheng

6026 5971

raymond.cheng@crbc.com.hk

Environmental Officer

Kanny Cho

6381 8171

sh.cho@crbc.com.hk

Contract 3402 New Integrated Airport Centers Enabling Works

(Wing Hing Construction Co., Ltd.)

Construction Manager

Michael Kan

9206 0550

michaelkan@whconst.com.hk

Environmental Officer

Lisa He

5374 3418

lisahe@whconst.com.hk

Contract 3501 Antenna Farm and Sewage Pumping Station

(Build King Construction Ltd.)

Project Manager

 

Vincent Kwan

 

9833 1313

 

vincent.kwan@buildking.hk

Environmental Officer

Edward Tam

9287 8270

edward.tam@buildking.hk

Contract 3502 T2 APM Depot Modification Works

(Build King Construction Ltd.)

Project Manager

David Ng

9010 7871

david.ng@buildking.hk

Environmental Officer

Chun Pong Chan

9187 7118

chunpong.chan@buildking.hk

Contract 3503

T2 Foundation and Substructure Works

(Leighton–Chun Wo Joint Venture)

Project Manager

Eric Wu

3973 1718

eric.wu@lcwjv.com

Environmental Officer

Stephen Tsang

5508 6361

stephen.tsang@lcwjv.com

Contract 3602 Existing APM System Modification Works (Niigata Transys Co., Ltd.)

Project Manager

Kunihiro Tatecho

9755 0351

kunihiro_tatecho@niigata-transys.com

Environmental Officer

Arthur Wong

9170 3394

arthur.wong@whytecliff.com

Contract 3603

Baggage Handling System

(Vanderlande Industries Hong Kong Ltd. and Shun Hing Systems Integration Co., Ltd.)

Project Manager

Andy Ng

9102 2739

andy.ng@shunhinggroup.com

Environmental Officer

Eric Ha

9215 3432

eric.ha@shunhinggroup.com

Contract 3801

APM and BHS Tunnels on Existing Airport Island

(China State Construction Engineering (Hong Kong) Ltd.)

Project Manager

Tony Wong

9642 8672

tony_wong@cohl.com

Environmental Officer

Fredrick Wong

9842 2703

cheukwai_wong@cohl.com

Attachment I presents the organization charts of all the above-mentioned contractors required under EP Condition 2.4.

 

3        Management Organization of the Environmental Team

The management organization of the Environmental Team (ET), including names of the ET Leader and Deputy ET Leaders and their contact details are set out in Table 2 below:

Table 2: Contact Information of ET

Name

Position

Telephone

Email

Terence Kong

ET Leader

2828 5919

Terence.Kong@mottmac.com

Heidi Yu

Deputy ET Leader

2828 5704

Heidi.Yu@mottmac.com

Daniel Sum

Deputy ET Leader

2585 8495

Daniel.Sum@mottmac.com

 

Attachment II presents an organization chart of the ET (together with that for the IEC, as described in Section 4 below) required under EP Condition 2.4.

 

4        Management Organisation of the Independent Environmental Checker and His Team

The management organization of the Independent Environmental Checker (IEC), including names of the IEC and Deputy IEC are set out in Table 3 below:

Table 3: Contact Information of IEC

Name

Position

Telephone

Email

Jackel Law

IEC

3922 9376

jackel.law@aecom.com

Roy Man

Deputy IEC

3922 9348

roy.man@aecom.com

 

Attachment II presents an organization chart of the IEC required under EP Condition 2.4.

 

Attachment

I.        Organization Chart of the Works Contracts

II.       Organization Chart of the ET and IEC

 

 

 

 

  I.       Organization Chart of the Works Contracts




Organization Chart of Penta-Ocean-China State-Dong-Ah Joint Venture (Contract 3201) for Deep Cement Mixing Works (Package 1)

Project Director
Tsugunari Suzuki
,Deputy Project Director
Victor Wu
,Environmental Team,Safety Team,QA/QC Team,DCM Operation Team,Environmental Officer
Hiu Yeung Tang

,Environmental Supervisor

,QS Team,Planning, Engineering and Logistic Operation Team,Administration Team,Environmental Coordinator,Deputy Project Director
Dong Hae Kim
,Project Manager
Eiji Murauchi
,Monitoring Team,Project Manager
Byeung Gee Ahn

 

 


 



 



 



 



 



 



 


 


 



 


 


 


 



 




II.       Organization Chart of the ET and IEC