Expansion of Hong Kong International Airport into a Three-Runway System

Contamination Assessment Report for
Terminal 2 Emergency Power Supply System No.1 (Volume 1)

January 2020

 

 

 

 

 

 

 

 

 

Contents

1       Introduction

1.1     Background

1.2     Scope of this CAR

1.3     Objective

2       Summary of Sampling and Testing Strategy

2.1     Proposed Sampling Method in the SCAP

2.1.1       Proposed Sampling Method of BH1 and BH2

2.2     Alternative Sampling Method Formulated after Pre-demolition Survey

2.2.1       Alternative Sampling Method of BH1

2.3     Assessment Criteria

3       Site Investigation

3.1     Sand/Soil Sampling

3.1.1       Underground Fuel Tank BH1

3.1.2       Underground Fuel Pipeline BH2

3.2     Decontamination Procedures

3.3     Quality Assurance / Quality Control Procedure

4       Interpretation of Laboratory Testing Results

4.1     Sand/Soil Contamination

4.1.1       Underground Fuel Tank BH1

4.1.2       Underground Fuel Pipeline BH2

5       Final Inspection and Record Checking Findings

5.1     General

5.1.1       Final Inspection Findings

5.1.2       Record Checking Findings

6       Conclusion

 

 

 

 

Appendices

 

A.

Updated Implementation Schedule of Land Contamination – Construction Phase

 

B.

Location of Emergency Power Supply System No.1 of T2 Building Proposed SI Locations for Expansion of T2 Building

 

 

B.1   Location of Emergency Power Supply System No.1 of T2 Building (Overview)

 

 

B.2   Location of Emergency Power Supply System No.1 of T2 Building (Zoom-in View of Northern Section of T2 Building)                                

 

C.

Identified Potential Land Contaminated Source of Emergency Power Supply System No.1 (EPSS1) in SCAP

 

D.

Indicative Sampling Point Selection of BH1 and BH2 - BH2-S1, BH2-S2, BH2-S3, BH2-S6 in SCAP

 

E.

Structure and Actual Sampling Depth of 2,500 L Underground Fuel Tank of EPPS1 (i.e. BH1)

 

F.

Sampling Point of Underground Pipeline Trench of EPSS1 (i.e. BH2 - BH2-S1, BH2-S2, BH2-S3, BH2-S6)

 

G.

Chain-of-Custody Record

 

H.

Laboratory Testing Results of BH1 and BH2

 

 

H.1 Laboratory Testing Results of BH1

 

 

H.2 Laboratory Testing Results of BH2

 

I.

Photo Record of Final Inspection for BH3 and BH4

 

 


1          Introduction

1.1          Background

The Environmental Impact Assessment (EIA) Report (Register No.: AEIAR-185/2014) prepared for the “Expansion of Hong Kong International Airport into a Three-Runway System” (the project) has been approved by the Director of Environmental Protection, and an Environmental Permit (EP) (Permit No.: EP-489/2014) has been issued for the project under the Environmental Impact Assessment Ordinance. As part of the EIA study, a Contamination Assessment Plan (CAP) (hereafter referred to as the Approved CAP) was prepared and presented as Appendix 11.1 of the approved EIA Report. In accordance to Section 8.1.1.1 of the Updated Environmental Monitoring and Audit (EM&A) Manual, which was submitted under Condition 3.1 of the EP, and Section 11.10.1.2 of the EIA Report, six areas (i.e. fuel tank room within Terminal 2 (T2) building, fuel tank room to the west of Civil Aviation Department (CAD) antenna farm, seawater pump house, switching station, pumping station and fire training facility), were inaccessible for site reconnaissance at the time of preparing the EIA Report.

According to Sections 11.5.4.14 and 11.5.4.37 of the EIA Report, it is anticipated that any potential land contamination concern related to possible leakage/ spillage of fuel in the fuel tank room within T2 building and fuel tank room to the west of CAD antenna farm will not cause any insurmountable impact. Furthermore, as mentioned in Sections 11.5.4.38, 11.5.4.47 and 11.5.4.50 of the EIA Report, the seawater pump house, switching station, pumping station and fire training facility are not identified as potential contaminative land use types as given in Table 2.3 of the Practice Guide for Investigation and Remediation of Contaminated Land, hence no potential land contamination along these areas are anticipated.

As part of the ongoing detailed design of the project, relocation of the switching station is no longer required for the modification of existing North Runway. Hence site appraisal process for land contamination potential at the switching station is considered not necessary. Further site reconnaissance was conducted at the remaining five assessment areas (i.e. the fuel tank room within T2 building, fuel tank room to the west of CAD antenna farm, seawater pump house, pumping station and fire training facility) in third quarter of 2016 and May 2017.

In addition, further review of the as-built drawings when taking into account the latest design details of T2 Expansion project and planned site investigation (SI), as well as follow-up site reconnaissance at T2 building have been undertaken in January 2018 and February 2018 (i.e. fuel tanks and generators within the building). Findings and consideration of assessment results after EIA stage have been summarized in the Supplementary Contamination Assessment Plan (SCAP) being approved in August 2018.

To match with the construction programme, decommissioning/ demolition of the Emergency Power Supply System No.1 (hereafter referred as EPSS1) at T2 northern section have been scheduled in 2019. Mott MacDonald Hong Kong Limited (MMHK), as the project’s Environmental Team, was appointed by Airport Authority Hong Kong (AAHK) to prepare the Contamination Assessment Report (CAR) for Terminal 2 Emergency Power Supply System No.1 (Volume 1)  to partially fulfil the SCAP’s recommendation. CAR(s) for the other areas of the Project Site will be submitted to EPD for endorsement in accordance with the SCAP and the updated Implementation Schedule of Land Contamination – Construction Phase is given in Appendix A.

1.2          Scope of this CAR

T2 building of the Hong Kong International Airport comprises northern and southern sections, where each section consists of number of Emergency Generator Rooms and Fuel Tank Rooms.

The Emergency Power Supply System No.1 was located at northern section of T2 Building as shown in Appendix B. This set of emergency power supply system comprises underground and above-ground section, with the following identified potential land contamination sources listed in Table 1.1 below,

Table 1.1: Identified Potential Land Contamination Source of Emergency Power Supply System No.1

Potential Land Contamination Source Reference ID

Descriptions

Location

Underground Section

 

Please refer to  Appendix C

BH1

A 2,500 L underground fuel tank

BH2

53 m-in-length underground fuel pipelines connecting the 2,500 L underground fuel tank (i.e. BH1) and the 450 L above-ground fuel tank (i.e. BH3)

Above-ground Section

 

BH4

An emergency generator at Emergency Generator Room, connected to 450 L above-ground fuel tank (i.e. BH3)

BH3

A 450 L above-ground fuel tank at Emergency Generator Room

To match with the construction programme, scope of the CAR for Terminal 2 Emergency Power Supply System No.1 (Volume 1) is as follows,

     BH1

     Partial portion of BH2, which includes:

     Segment running from BH1 to sampling point BH2-S3, i.e. BH2-S1, BH2 S2, BH2-S3; and

     BH2-S6;

     BH3

     BH4

 

Soil sampling for BH1, BH2-S1, BH2-S2, BH2-S3 and BH2-S6 were planned in accordance with the approved SCAP, therefore, the laboratory testing results of BH2-S6 as well as the duplicate, equipment blank and field blank conducted in the event of BH2-S6 sampling are presented in this CAR as QA/QC. Construction works will only be conducted at (i) areas around BH1 and BH2-S3 and (ii) above-ground structures at BH3 and BH4 (see delineated areas by orange dotted-line for BH1, BH3 and BH4 in Appendix F).  No works will be conducted in other areas within the Emergency Power Supply System No. 1 prior to the agreement of Vol. 2 of the CAR for T2 EPPS1, or Remediation Report for T2 EPPS1 (if remediation is required). No works will be conducted for BH2-S6 at current stage and the works for BH2-S6 will be conducted together with the system portion to be included in Vol. 2 of the CAR for T2 EPPS1.

 

Graphical illustration of the scope of this CAR is presented in Appendix C.

1.3          Objective

According to the approved SCAP, the Emergency Power Supply System No. 1 located in northern section of the T2 building have been identified as the potential land contamination source, which being proposed in EIA Report as sampling locations. As per the approved SCAP, for the above-ground section (i.e. BH3 and BH4), final inspection and record checking shall be conducted right before decommissioning/ demolition. While for the underground section (i.e. BH1 and BH2), enhanced SI programme shall be conducted along with decommissioning/demolition to confirm no potential land contamination taken place.

For the above-ground section (i.e. BH3 and BH4), demolition works have been scheduled in early April 2019. Final site inspection and record checking have been conducted on 19 March 2019. Photo records and findings have been included in this CAR. For underground section, enhanced SI programmes for BH1, segment of BH2 running from BH1 to sampling point BH2-S3, and the segment at BH2-S6 were carried out on 4 October 2019, 4 and 14 November 2019 respectively.

This Contamination Assessment Report for Terminal 2 Emergency Power Supply System No.1 (Volume 1) has been prepared to present the findings of final inspection and record checking of the above-ground section (i.e. BH3 and BH4), as well as the procedures and laboratory testing of enhanced SI for the underground section (including BH1, segment of BH2 running from BH1 to sampling point BH2-S3, and the segment at BH2-S6) under the scope presented in Section 1.2. The testing results have been interpreted based on the Guidance Manual for Use of Risk Based Remediation Goals (RBRGs) for Contaminated Land Management (Guidance Manual).

 

2          Summary of Sampling and Testing Strategy

2.1          Proposed Sampling Method in the SCAP

2.1.1              Proposed Sampling Method of BH1 and BH2

Grab sampling was proposed for the concerned underground facilities of T2 Building, including BH1 and BH2. The proposed sampling and testing plan in the SCAP, including the parameters to be tested, sampling locations and sampling depths are extracted and presented in Table 2.1. Sand and soil samples shall be grabbed manually during decommissioning/demolition process of concerned fuel tanks (i.e. BH1) and underground pipeline trench (i.e. BH2). The whole sampling process shall be under the supervision of on-site contamination specialist.

Sampling Selection of Underground Fuel Tank (i.e. BH1)

Sand and soil samples should be collected as follows:

·        Sand samples should be collected at 0.5 m, 1.5 m and bottom level inside the concrete chamber of underground fuel tank;

·        Soil sample should be collected right underneath concrete chamber of underground fuel tank.

Sampling Selection of Underground Fuel Pipelines (i.e. BH2)

Sand and soil samples should be collected as follows:

·        Sand samples should be taken at every curvature of pipelines inside the concrete trench;

·        Additional sampling points inside the concrete trench are set depending on length of pipeline segment (from curvature/connection to curvature):

°        If pipeline segment is ≤10 m, additional sample is considered not required;

°        If pipeline segment is >10 m and ≤20 m, one sample shall be taken at segment mid-point;

°        If pipeline segment is >20 m and ≤30 m, samples shall be collected at 2 points which are evenly spaced with each other and segment ends.

·       Soil samples should be taken right underneath concrete trench at every curvature.

 

Sampling point annotation and indicative sampling point locations of BH1 and BH2 extracted from the SCAP are presented in Table 2.2 and Appendix D.


Table 2.1: Enhanced Sampling and Testing Plan for BH1 and BH2 of Emergency Power Supply System No.1 in T2 Building

Proposed Sampling Locations

Sample Matrix

Sampling Point Annotation

Parameters to be Tested1 & 2

Rationale of Sampling

Heavy Metals

PCRs3

VOCs3

SVOCs3

BH14

Sand5

0.5 m, 1.5 m bgs6and bottom level inside the concrete chamber

/

Lead only

ü

BTEX7 and MTBE8

PAHs9

Confirm no diesel leakage from underground fuel tank

 

Soil

Right underneath concrete chamber

/

Lead only

ü

BTEX7 and MTBE8

PAHs9

Confirm no leaked diesel (if any) penetrate the concrete chamber

BH24

Sand5

At the level of fuel pipelines

BH2S1 - BH2S7

Lead only

ü

BTEX7 and MTBE8

PAHs9

Confirm no diesel leakage from underground fuel pipelines

 

Soil

Right underneath concrete/brick trench

BH2S1, BH2S2,

BH2S3, BH2S6

Lead only

ü

BTEX7 and MTBE8

PAHs9

Confirm no leaked diesel (if any) penetrate the concrete /brick trench

Remarks:

1 ü = testing proposed.

2 Having reviewed the potentially polluting activities of the site (use of diesel fuel) and S2.4.3 of Practice Guide, it is recommended to analyse the key COCs (i.e. Lead, PCRs, BTEX, MTBE and PAHs) of “Petrol Filling Station” which is the most relevant land use type for the case of T2. The concerned diesel tanks and pipelines are used for storage and transfer of diesel fuel only and only diesel fuel is used for the generator. It is noted BTEX, MTBE and Lead present in gasoline but unlikely to be found in diesel fuel.

3 PCRs = Petroleum Carbon Ranges; VOCs = Volatile Organic Chemicals; SVOCs = Semi-volatile Organic Chemicals;

4 Exact sampling locations will be identified on site during the removal of sand/soil during fuel tank and pipelines decommissioning/ demolition.

5 All sand samples will be collected within the concrete chamber or concrete/brick trench.

6 bgs = Below Ground Surface.

7 BTEX = Benzene, Toluene, Ethylbenzene, and Xylenes.

8 MTBE = Methyl Tert-Butyl Ether.

9 Polyaromatic hydrocarbons (PAHs) in the RBRGs include, acenaphthene, acenaphthylene, anthracene, benzo(a)anthracene, benzo(a)pyrene, benzo(b)fluoranthene, benzo(g,h,i)perylene, benzo(k)fluoranthene, chrysene, dibenzo(a,h)anthracene, fluoranthene, fluorene, indeno(1,2,3-cd)pyrene, naphthalene, phenanthrene and pyrene.


Table 2.2: Sampling Point Annotation of Underground Fuel Pipeline BH2

Proposed Sampling Locations

Annotation of Sampling Point

Type of Sampling Point (Curvature / Additional)

Figure No.

BH2

BH2-S1

Curvature

Appendix D

BH2-S2

Curvature

BH2-S3

Curvature

BH2-S41

Additional

BH2-S51

Additional

BH2-S6

Curvature

BH2-S71

Additional

Remarks:

1 Not under the scope of this CAR. BH2-S4, BH2-S5 and BH2-S7 will be presented in Vol. 2 of the CAR for T2 EPPS1.

2.2          Alternative Sampling Method Formulated after Pre-demolition Survey

2.2.1              Alternative Sampling Method of BH1

Pre-demolition survey have been undertaken by the Contractor, AAHK and the land contamination specialist in early October 2019. Based on the site condition, it is observed that the concrete chamber structure was deviated from the as-built drawing, the revealed as illustrated in Appendix E. The fuel tank is still fully encased in a at least 300 mm thick concrete chamber, however, the top slab of the chamber located at around 2.4 m below ground level (bgl) rather than at the level right beneath the surface ground level. In such case, borehole sampling for BH1 is proposed by the Contractor, instead of grab sampling as proposed in SCAP. Agreement on the proposed alternative sampling method of BH1 has been sought between the Contractor, AAHK and the land contamination specialist.

Borehole has been undertaken by means of rotary drilling method, as agreed with the on-site contamination specialist. To inspect for any underground utilities at the proposed borehole location, an inspection pit has been excavated down to 2.0 m below ground surface (bgs).

Details of sampling depths please refer to Section 3.1.1.

2.3          Assessment Criteria

The chemicals of concern (COCs) listed in EPD’s Guidance Manual for Use of Risk-Based Remediation Goals (RBRGs) for Contaminated Land Management were referred to when proposing the analytical parameters listed in Table 2.1. According to Section 5.3 of the SCAP, categories of Industrial has been adopted for evaluating the contamination level of T2 building.

 


 

3          Site Investigation

3.1          Sand/Soil Sampling

3.1.1              Underground Fuel Tank BH1

Site investigation works of BH1 was carried out by DrilTech Ground Engineering Limited on 4 October 2019. As per on-site measurement, the revealed inner depth of the concrete chamber (i.e. depth from the bottom side of top concrete slab to upper side of the bottom concrete slab) is around 1.73 m.

Since there is a reduction of inner depth of concrete chamber (i.e. from ~3.9m as shown in the as-built drawing, to the on-site revealed depth 1.73m), as decided by the on-site contamination specialist, it is considered that 2 undisturbed sand samples collected at 0.7m and 1.6m below the top concrete slab of the concrete chamber is adequate and representative to confirm no land contamination issue at the underground fuel tank. Also, 1 undisturbed soil sample was collected at 0.5m right underneath the bottom of the concrete chamber. The entire SI programme was supervised by the on-site land contamination specialist. The actual sampling depths are summarized in Table 3.1 and illustrated in Appendix E. All soil/sand samples were analyzed in accordance with the testing schedules detailed in Table 2.1.

Table 3.1: Summary of Sampling Depth of BH1

Sampling Locations

Sampling Depth

Sampling Date

BH1

0.7m below the top concrete slab of the concrete chamber

4 October 2019

 

1.6m below the top concrete slab of the concrete chamber

4 October 2019

 

0.5m below the bottom slab of the concrete chamber

4 October 2019

3.1.2              Underground Fuel Pipeline BH2

Soil sampling of BH2 segment between BH1 and sampling point BH2-S3 was carried out by Mott MacDonald HK Limited on 4 November 2019. Soil sampling at sampling point BH2-S6 was carried out by Mott MacDonald HK Limited on 14 November 2019.

BH2 segment between BH1 and sampling point BH2-S3

Soil sample was collected at sampling points BH2-S1, BH2-S2 and BH2-S3. According to site observation, the segment of underground pipeline located between BH1 and BH2-S1 are not laid inside the concrete trench, while the underground pipeline running from BH2-S1 to BH2-S3 is laid inside the concrete trench.

To confirm no diesel leakage from underground fuel pipelines from the no-concrete-trench segment, 1 soil sample have been taken right underneath the particular segment (i.e. NCTS1). Based on the sampling point selection strategy in the SCAP (i.e. If pipeline segment is 10 m, additional sample is considered not required;), together with the site observations where no oil stains being identified in the vicinity of NCTS1, and with reference to the laboratory testing result of soil sample taken at 0.5m below the bottom slab of the concrete chamber at BH1 (refer to Section 4.1.1) which is near to the location of NCTS1, therefore, it is considered that 1 sample collected at the depth right underneath the pipeline is deemed to be sufficient to represent and confirm if any diesel leakage from the <2m (as revealed on-site) no-concrete-trench segment.

While opening up the concrete trench from BH2-S1 to BH2-S3, it is observed that the concrete trench is filled with concrete rather than sand, which previously shown in the as-built drawings. Based on site situation, no sand samples could be taken at the level of fuel pipelines within the concrete trench.

No ground water was observed during soil sampling of NCTS1, BH2-S1, BH2-S2 and BH2-S3.

Sampling Point BH2-S6

Soil sample was collected at sampling point BH2-S6. With reference to on-site observation, it is observed that the concrete trench is filled with concrete rather than sand, which previously shown in the as-built drawings. Based on site situation, no sand samples could be taken at the level of fuel pipelines within the concrete trench.

No ground water was observed during soil sampling of BH2-S6.

The actual sampling points and on-site length measurement of the particular segment of underground pipeline BH2 are summarized in Table 3.2 and illustrated in Appendix F. All soil samples were analyzed in accordance with the analysis schedules detailed in Table 2.1.

 

Table 3.2: Summary of Sampling Point of BH2

Sampling Locations

Sampling Point

Type of Sampling Point

(Curvature/ Additional/ No-concrete-trench Segment)

Sampling Date

BH2

 

NCTS1

No-concrete-trench Segment

4 November 2019

BH2-S1

Curvature

4 November 2019

BH2-S2

Curvature

4 November 2019

BH2-S3

Curvature

4 November 2019

BH2-S6

Curvature

14 November 2019

3.2          Decontamination Procedures

Before drilling/ excavation/ sampling, all equipment in contact with the ground were thoroughly decontaminated between each excavation, drilling and sampling event to minimise the potential for cross contamination. The equipment should be decontaminated by steam cleaning or high-pressure hot water jet, then washed by phosphate-free detergent and finally rinsed by distilled water. During decontamination procedures and sampling, disposable latex gloves were worn to prevent the transfer of contaminants from other sources.

3.3          Quality Assurance (QA) / Quality Control (QC) Procedure

3.3.1              QA/QC Procedure

The soil samples taken were placed in sample containers provided by the HOKLAS laboratory. Sufficient sample size was collected for the laboratory analysis. Samples were marked with sampling date, sampling identification number and sampling depth with appropriate chain-of-custody form. Following sampling, samples were stored in a cool box at a temperature between 0oC and 4oC and transported to the laboratory immediately after completion of the sampling.

The chain-of-custody records are given in Appendix G.

3.3.2              QA/QC Analysis

In this enhanced SI programme, QA/QC samples were collected in accordance to the frequency proposed in the SCAP as follows, with a Chain of Custody protocol adopted: 

     One equipment blank per 20 samples for full suite analysis*;

     One field blank per 20 samples for full suite analysis*;

     One duplicate sample per 20 samples for full suite analysis*; and

     One trip blank per trip for the analysis of volatile parameters#.

Note: 

*              For the purposes of this enhanced SI programme, the following parameters were tested in a ‘full suite analysis’ –

1)    Heavy Metals: Lead only.

2)    PCRs: C6-C8; C9-C16; C17-C35. 

3)    VOCs: Benzene, Toluene, Ethylbenzene, Xylenes and Methyl Tert-Butyl Ether. 

4)    SVOCs: acenaphthene, acenaphthylene, anthracene, benzo(a)anthracene, benzo(a)pyrene, benzo(b)fluoranthene, benzo(g,h,i)perylene, benzo(k)fluoranthene, chrysene, dibenzo(a,h)anthracene, fluoranthene, fluorene, indeno(1,2,3-cd)pyrene, naphthalene, phenanthrene and pyrene. 

#              For the purposes of this Project, the following parameters would be tested in the analysis of ‘volatile parameters’ – Benzene, Toluene, Ethylbenzene, Xylenes, Methyl Tert-Butyl Ether and C6-C8.

 

The duplicate, equipment blank and field blank samples have been collected on 14 Nov 2019 during the sampling for BH2-S6.

The laboratory results for QA/QC samples are presented in Appendix H.

All testing parameters were not detected (below the limit of reporting) in all blank samples obtained. QA/QC procedures for sample collection and preparation are considered acceptable.

 

 

4          Interpretation of Laboratory Testing Results

4.1          Sand/Soil Contamination

4.1.1              Underground Fuel Tank BH1

A total of 2 sand and 1 soil samples were collected at BH1 for laboratory testing. The testing results are summarised in Table 4.1 and the testing reports are presented in Appendix H. The testing results of all parameters indicated that all sand/ soil samples from BH1 were below the value of Risk-Based Remediation Goals (RBRGs) for Industrial. 

Table 4.1: Laboratory Testing Results of Sand/ Soil Samples at BH1

Chemical

Concentration (mg/kg)

BH1

(0.7 m below the top concrete slab of the concrete chamber)

BH1

(1.6 m below the top concrete slab of the concrete chamber)

BH1

(0.5m below the bottom concrete slab of the concrete chamber)

RBRGs for Industrial

Heavy Metals

 

 

 

 

Lead

9

8

38

2290

PCRs

 

 

 

 

C6 - C8

<5

<5

<5

C6 - C8: 10,000

C9 - C16: 10,000

C17 - C35: 10,000

C9 - C16

<200

<200

<200

C17 - C35

<500

<500

<500

VOCs

 

 

 

 

Benzene

<0.2

<0.2

<0.2

9.21

Toluene

<0.5

<0.5

<0.5

10,000

Ethylbenzene

<0.5

<0.5

<0.5

8,240

Xylenes (Total)

<2.0

<2.0

<2.0

1,230

Methyl tert-Butyl Ether

<0.2

<0.2

<0.2

70.1

SVOCs

 

 

 

 

Naphthalene

<0.500

<0.500

<0.500

453

Acenaphthylene

<0.500

<0.500

<0.500

10,000

Acenaphthene

<0.500

<0.500

<0.500

10,000

Fluorene

<0.500

<0.500

<0.500

10,000

Phenanthrene

<0.500

<0.500

<0.500

10,000

Anthracene

<0.500

<0.500

<0.500

10,000

Fluoranthene

<0.500

<0.500

<0.500

10,000

Pyrene

<0.500

<0.500

<0.500

10,000

Benz(a)anthracene

<0.500

<0.500

<0.500

91.8

Chrysene

<0.500

<0.500

<0.500

1140

Benzo(b)fluoranthene

<0.500

<0.500

<0.500

17.8

Benzo(k)fluoranthene

<0.500

<0.500

<0.500

918

Benzo(a)pyrene

<0.500

<0.500

<0.500

9.18

Indeno(1.2.3.cd)pyrene

<0.500

<0.500

<0.500

91.8

Dibenz(a.h)anthracene

<0.500

<0.500

<0.500

9.18

Benzo(g.h.i)perylene

<0.500

<0.500

<0.500

10,000

 

4.1.2              Underground Fuel Pipeline BH2

A total of 5 soil samples were collected within the scope of this CAR at BH2 for laboratory testing. The testing results are summarised in Table 4.2 and the testing reports are presented in Appendix H. The testing results of all parameters indicated that all soil samples from BH2 were below the value of Risk-Based Remediation Goals (RBRGs) for Industrial. 


Table 4.2: Laboratory Testing Results of Soil Samples at BH2

Compound

 

Concentration (mg/kg)

 

NCTS1

BH2-S1

BH2-S2

BH2-S3

BH2-S6

RBRGs for Industrial

Heavy Metals

 

 

 

 

 

 

Lead

9

52

80

48

41

2290

PCRs

 

 

 

 

 

 

C6 - C8

<5

<5

<5

<5

<5

C6 - C8: 10,000

C9 - C16: 10,000

C17 - C35: 10,000

C9 - C16

<200

<200

<200

<200

<200

C17 - C35

<500

<500

<500

<500

<500

VOCs

 

 

 

 

 

 

Benzene

<0.2

<0.2

<0.2

<0.2

<0.2

9.21

Toluene

<0.5

<0.5

<0.5

<0.5

<0.5

10,000

Ethylbenzene

<0.5

<0.5

<0.5

<0.5

<0.5

8,240

Xylenes (Total)

<2.0

<2.0

<2.0

<2.0

<2.0

1,230

Methyl tert-Butyl Ether

<0.2

<0.2

<0.2

<0.2

<0.2

70.1

SVOCs

 

 

 

 

 

 

Naphthalene

<0.500

<0.500

<0.500

<0.500

<0.500

453

Acenaphthylene

<0.500

<0.500

<0.500

<0.500

<0.500

10,000

Acenaphthene

<0.500

<0.500

<0.500

<0.500

<0.500

10,000

Fluorene

<0.500

<0.500

<0.500

<0.500

<0.500

10,000

Phenanthrene

<0.500

<0.500

<0.500

<0.500

<0.500

10,000

Anthracene

<0.500

<0.500

<0.500

<0.500

<0.500

10,000

Fluoranthene

<0.500

<0.500

<0.500

<0.500

<0.500

10,000

Pyrene

<0.500

<0.500

<0.500

<0.500

<0.500

10,000

Benz(a)anthracene

<0.500

<0.500

<0.500

<0.500

<0.500

91.8

Chrysene

<0.500

<0.500

<0.500

<0.500

<0.500

1140

Benzo(b)fluoranthene

<0.500

<0.500

<0.500

<0.500

<0.500

17.8

Benzo(k)fluoranthene

<0.500

<0.500

<0.500

<0.500

<0.500

918

Benzo(a)pyrene

<0.500

<0.500

<0.500

<0.500

<0.500

9.18

Indeno(1.2.3.cd)pyrene

<0.500

<0.500

<0.500

<0.500

<0.500

91.8

Dibenz(a.h)anthracene

<0.500

<0.500

<0.500

<0.500

<0.500

9.18

Benzo(g.h.i)perylene

<0.500

<0.500

<0.500

<0.500

<0.500

10,000

 


5          Final Inspection and Record Checking Findings

5.1          General

According to Section 3.2.5 of the SCAP, it is recommended that final inspection and record checking should be conducted right before decommissioning/ demolition of the 450 L above-ground fuel tank equipped with drip tray (i.e. BH 3) and the above-ground emergency generator (i.e. BH 4) to ensure no contaminative activities during the period from the time of preparation of SCAP till the decommissioning.

BH3 and BH4 have been decommissioned/ demolished in early April 2019. Summary of final inspection and record checking are given in ensuing paragraphs.

5.1.1              Final Inspection Findings

Final inspection of the BH3 and BH4 was conducted on 19 March 2019. The demolition of Emergency Generator Room building structure was commenced in early April 2019 which leading to unsafe condition for further inspection of the facilities.

During our final inspection, BH 3 and BH 4 are at the same locations as for the time of preparation of SCAP in 2018. Both facilities are mounted on intact concrete floor with no oil stain. The above-ground fuel tank was surrounded by concrete curb and no oil stain was observed on its drip tray.

The fuel pipelines running through BH3 and BH4 are buried by sand inside a concrete and brick trench at floor level. 2 sections of the pipelines were checked by removing the chequer plate cover and no sign of leakage was observed.

Photo record of final inspection is presented in Appendix I.

5.1.2              Record Checking Findings

Available monthly maintenance records of BH3 and BH4 from the time of SCAP preparation (i.e. March 2018) to 23 February 2019 (date of last maintenance) has been checked in March 2019. No abnormality on fuel re-filling record have been observed and no fuel tank leakage was recorded, it is considered that no fuel leakage for the above-ground facilities BH3 and BH4 from the time of SCAP preparation till decommissioning/ demolition.

 

 

 

 

6          Conclusion

Enhanced SI programme have been conducted for the underground section, BH1, segment of BH2 running from BH1 to sampling point BH2-S3, and segment at BH2-S6, in October and November 2019 respectively. During the enhanced SI programme, a total of 2 sands and 6 soil samples were collected at BH1, the segment of BH2 running from BH1 to sampling point BH2-S3, and sampling point BH2-S6 and testing of CoCs was undertaken. From the testing results, it is concluded that all the samples at BH1 and the segment of BH2 were below the RBRGs standard for industrial. It is considered that there are no land contamination issues at BH1, the segment of BH2 running from BH1 to sampling point BH2-S3, and segment at BH2-S6, and therefore remediation works are not required.

Final inspection and record checking have been conducted right before decommissioning/ demolition of the above-ground section of EPSS1 (i.e. BH3 and BH4). According to the inspection and record checking results, it is considered that no contaminative activities during the period from the preparation of SCAP till decommissioning/demolition of the above-ground facilities.

Construction works will only be conducted at (i) areas around BH1 and BH2-S3 and (ii) above-ground structures at BH3 and BH4 (see delineated areas by orange dotted-line for BH1, BH3 and BH4 in Appendix F).  No works will be conducted in other areas within the Emergency Power Supply System No. 1 prior to the agreement of Vol. 2 of the CAR for T2 EPPS1, or Remediation Report for T2 EPPS1 (if remediation is required). No works will be conducted for BH2-S6 at current stage and the works for BH2-S6 will be conducted together with the system portion to be included in Vol. 2 of the CAR for T2 EPPS1.