Contents
1
Introduction
1.1
Purpose
of the Manual
1.1.1.1 In accordance with Condition
3.1 of Environmental Permit (EP) (EP No. EP-489/2014), an updated Environmental
Monitoring and Audit (EM&A) Manual shall be prepared before the
commencement of construction works. The first submission of Updated EM&A
was made to the Environmental Protection Department (EPD) on 18 September 2015,
and finalised and release via the project’s dedicated website in January 2016.
1.1.1.2
The purpose of this updated EM&A
Manual (hereafter referred to as the Manual) is to guide the setup of an
EM&A programme to ensure compliance with the recommendations in the
approved Environmental Impact Assessment (EIA) Report (Register No.
AEIAR-185/2014), to assess the effectiveness of the recommended mitigation
measures and to identify any further need for additional mitigation measures or
remedial action. This Manual outlines the monitoring and audit programme
proposed for the “Expansion of Hong Kong International Airport into a
Three-Runway System” (the project).
1.1.1.3
In this updated submission, Section 5
incorporates revised sensitive receiver water quality monitoring locations.
Section 10 incorporates an alternative method for passive acoustic monitoring
of Chinese White Dolphin and the alternative approach for undertaking Dolphin
Exclusion Zone Monitoring.
1.2
Project Description
1.2.1.1
The project will consist of a new third runway with associated taxiways,
aprons (or aircraft stands), as well as new passenger concourse buildings and
expansion of the existing Terminal 2 (T2) building. Included in the project
will be related airside and landside works and associated ancillary and
supporting facilities.
1.2.2
Land
Formation
1.2.2.1
Based on the preferred airport development option identified, land is
required to be formed to the north of the existing airport island, which will
provide a platform for the development. The proposed land formation works will
mainly include:
● Land formation of not more than 650 ha
to the north of the existing airport island with partial construction over the
contaminated mud pits. The area of land formation is defined to be the area at
and above the high water mark of +2.3 mPD; and
● Modification and integration of the
existing seawall at the northern, western and eastern sides of the existing
North Runway into the new land formation and re-provisioning of new seawall
around the land formation.
1.2.3
Airfield
Facilities
1.2.3.1
The proposed airfield facilities will mainly include:
● Construction of a third runway,
related taxiway systems, associated airfield infrastructure, aircraft
navigational aids, approach lighting systems and new Hong Kong International
Airport Approach Area (HKIAAA) beacons;
● Construction of the third runway
passenger concourse (TRC) aprons;
● Temporary closure and modification
of the existing North Runway along with related taxiway systems; and
● Expansion of the freighter aprons in
the existing Midfield area between the existing North and South runways.
1.2.4
Passenger
Facilities
1.2.4.1
The proposed passenger facilities will mainly include:
● Construction of the TRC and
passenger fixed link bridges;
● Expansion of the existing passenger
T2;
● Extension of the automated people
mover (APM) and associated depot and maintenance / stabling areas; and
● Expansion of the baggage handling
system (BHS) and associated baggage halls and early bag store.
1.2.5
Ancillary
Facilities
1.2.5.1
New ancillary facilities will be provided to support the operational
needs of the TRC and airfield facilities. These ancillary facilities will be
located on the west and east sides of the proposed land formation area (i.e. within the western support area and the eastern
support area respectively) and will accommodate utility buildings, airport
support developments, air cargo staging, catering, aircraft maintenance,
aircraft engine run-up (engine testing) facilities, ground services equipment
area, early bag storage facility, fire station, fire training facility, petrol
fuelling station, new air traffic control towers (ATCTs), Hong Kong Observatory
(HKO) facility, mobile phone system antenna towers, stores, security gate houses,
etc.
1.2.6
Infrastructure
and Utilities
1.2.6.1
The proposed infrastructure and utilities will mainly include:
● Expansion of the landside and
airside road network in the passenger, cargo and maintenance areas and landside
transportation facilities, including new car parks;
● Construction of new airside road
access, including the construction of new airside road tunnels and ramps, to
connect the new third runway facilities with the existing airport;
● Modification to existing and
construction of new land based infrastructure including the seawater cooling
and flushing system, stormwater drainage system, greywater system, sewerage
network and potable water supply, Towngas supply,
132 kV / 11 kV and other power supply networks; communication networks; and
● Modifications and re-provisions to
existing marine facilities including the underwater aviation fuel pipelines
between Hong Kong International Airport (HKIA) and the off-airport fuel
receiving facilities at Sha Chau, the associated underwater 11 kV cable and
pilot cable and sea rescue boat points.
1.3
Tentative
Construction Programme
1.3.1.1
The tentative programme for operation of the three-runway system (3RS)
will be in 2024. Given the scale and complexity of the project, construction
and the concurrent runway operational configuration will be implemented in
phases. The tentative phasing programme is provided in Appendix
A which is based on the currently
available information. This programme is subject to change during the detailed
design stage.
1.4
Project
Organisation
1.4.1.1
The proposed project organisation is shown in Chart 1-1 below.
Chart
1‑1:
Project Organisation Chart
|
|
1.4.2
Airport Authority Hong Kong (AAHK)
1.4.2.1
AAHK is the project proponent for the development of the project and
will assume overall responsibility for the project.
1.4.3
Environmental
Protection Department (EPD)
1.4.3.1
EPD is the statutory enforcement body for environmental protection
matters in Hong Kong.
1.4.4
Project
Manager (PM)
1.4.4.1
The Project Manager (PM) or the PM’s
Representative is responsible for overseeing the construction works and for ensuring
that the works are undertaken by the Contractor in accordance with the
specification and contract requirements. The duties and responsibilities of the
PM with respect to EM&A include:
● To monitor the Contractor’s
compliance with Contract Specifications, including the effective implementation
and operation of the environmental mitigation measures;
● To employ an Independent
Environmental Checker (IEC) to audit the results of the EM&A works carried
out by the Environmental Team (ET);
● To monitor Contractors’ compliance
with the requirements in the EP and updated EM&A Manual;
● To facilitate ET’s implementation of
the EM&A programme;
● To participate in joint site
inspection by the ET and IEC;
● To oversee the implementation of the
agreed Event and Action Plan in the event of any exceedance; and
● To adhere to the procedures for
carrying out complaint investigation.
1.4.5
Contractors
1.4.5.1 The Contractors
employed by AAHK, including Contractors working on the project on a joint
venture (JV) basis, should report to the PM or the PM’s Representative. The
duties and responsibilities of the Contractors include:
● To comply with the relevant contract
conditions and specifications on environmental protection;
● To facilitate ET’s monitoring and
site inspection activities;
● To participate in the site
inspections undertake by the ET and IEC, and undertake any corrective actions;
● To provide information / advice to
the ET regarding works programme and activities which may contribute to the
generation of adverse environmental impacts;
● To submit proposals on mitigation
measures in case of exceedance of Action and Limit Levels in accordance with
the Event and Action Plans;
● To implement measures to reduce
impact where Action and Limit Levels are exceeded; and
● To adhere to the complaint handling
procedures in accordance with this Manual and the Complaint Management Plan.
1.4.6
Environmental
Team (ET)
1.4.6.1
A full time on-site ET should be employed by the AAHK / PM to conduct
the EM&A programme no later than one month before the commencement of
construction of the project. The ET should not be in any way an associated body
of the Contractor or the IEC for the project. The ET should be headed by the
full time on-site ET Leader (ETL). The ETL should have relevant professional
qualifications in environmental control and possess at least seven years of
experience in EM&A or environmental management. Suitably qualified staff
should be included in the ET, and resources for the implementation of the
EM&A programme should be allocated to enable fulfilment of the project’s
EM&A requirements during construction of the project. The ET should report
to AAHK / PM and the duties should include:
● To carry out field sampling, field
measurement, testing, assessment, and reporting for various environmental
parameters as required in this EM&A Manual;
● To analyse the EM&A data, review
the success of EM&A programme and the adequacy of mitigation measures
implemented, confirm the validity of the EIA predictions and identify any
adverse environmental impacts arising and recommend suitable mitigation measures;
● To monitor compliance with
conditions in the EP, environmental protection, pollution prevention and
control regulations and contract specifications;
● To carry out regular site inspection
at least once per week so as to investigate and audit Contractor’s site
practice, equipment and work methodologies with respect to pollution control
and environmental mitigation;
● To report on the EM&A results to
the AAHK / PM, IEC, EPD and Contractors;
● To vet the Contractor’s method
statements, design plans and submissions and check that the relevant
environmental protection and pollution control measures have been included and
are sufficient to comply with contractual and statutory requirements;
● To inform the AAHK / PM, IEC and
Contractors the recommend suitable mitigation measures in the case of
exceedance of Action and Limit Levels in accordance with the Event and Action
Plans;
● To liaise with the IEC on all environmental
performance matters, and ensure timely submission of all relevant EM&A pro
forma for IEC’s approval;
● To provide advice to the Contractors
on environmental improvement, awareness and enhancement matters, etc. on site;
● To prepare, certify and submit the
Baseline, Monthly, Quarterly, Annual and Final EM&A Review Reports to the
AAHK / PM, IEC and EPD timely;
● To keep a contemporaneous log-book
of each and every instance or circumstance or change of circumstances, which
may affect the compliance with the recommendations of the approved EIA Report
and the EP; and
● To set up and manage the dedicated
complaint hotline and email channel, and manage the complaint handling
procedures in accordance with this Manual and the Complaint Management Plan.
1.4.7
Independent Environmental Checker (IEC)
1.4.7.1
The IEC is empowered to audit the environmental performance of
construction, but is independent from the management of construction works. As
such, the IEC should not be in any way an associated body of the Contractor or
the ET for the project. A full time on-site IEC with a supporting team should
be employed by the AAHK / PM no later than one month prior to the commencement
of the construction of the project. The IEC should be a person who has relevant
professional qualifications in environmental control and at least seven years
of experience in EM&A or environmental management. The duties and
responsibilities of the IEC are:
● To provide proactive advice to the
AAHK / PM on EM&A matters related to the project;
● To verify the environmental
acceptability of permanent and temporary works and relevant design plans;
● To review and verify the monitoring
data and all submissions in connection with the EP, any subsequent Variations of EP (VEPs) and / or
Further EP (FEPs), and
EM&A reports submitted by the ET;
● To arrange and conduct at least
monthly site inspections of the works during the construction phase, and to
carry out ad hoc inspections if significant environmental problems are
identified;
● To validate and check the accuracy
of environmental monitoring;
● To audit the compliance with the
complaint handling procedures in accordance with this Manual and the Complaint
Management Plan;
● To verify the ET’s log-book and the
investigation result of any environmental exceedance, non-compliance and
complaint cases, compliance with the agreed Event and Action Plan and the
effectiveness of corrective actions / measures;
● To feedback audit results to the ET
by signing off relevant EM&A pro forma;
● To verify EM&A reports that have
been certified by the ETL;
● To audit EIA recommendations and requirements
against the status of implementation of environmental mitigation measures on
site;
● To report the works conducted, and
the findings, recommendations and improvements of the site inspections, after
reviewing ET’s and Contractor’s works, to the AAHK / PM on a monthly basis; and
● To review the effectiveness of the
EM&A programme, EIA recommendations and the adequacy of mitigation measures
implemented.
2
Air Quality Impact
2.1 Construction Air Quality Monitoring
2.1.1 General
2.1.1.1
The project is anticipated to give rise to construction dust impacts.
The key activities that would potentially result in dust emissions include land
formation works; construction works on the newly formed land and on the
existing airport island; operation of concrete batching plants, asphalt
batching plants, crushing plant, and barging points; haul roads; diversion of
submarine fuel pipeline; diversion of submarine 11 kV cable; and modifications
to existing outfalls. Construction phase dust monitoring is considered
necessary to check and ensure compliance that the relevant recommended
mitigation measures are properly implemented.
2.1.1.2
The key objectives of the construction phase dust monitoring are:
● To identify the extent of dust
impact during construction phase on sensitive receivers;
● To audit the compliance of the
Contractor with regard to dust control, contract conditions and the relevant
dust impact criteria;
● To determine the effectiveness of
mitigation measures to control fugitive dust emission from activities during
the construction phase;
● To recommend further mitigation
measures if found to be necessary; and
● To comply with Action and Limit
Levels for air quality as defined in this Manual.
2.1.2 Air Quality Parameters
2.1.2.1
Monitoring and audit of 24-hour
Respirable Suspended Particulates (RSP or PM10) and 24-hour Fine Suspended
Particulates (FSP or PM2.5) levels are not proposed. This is because even
under the hypothetical worst case Tier 1 mitigated scenario both 24-hour RSP
and 24-hour FSP would comply with the corresponding Air Quality Objectives
(AQO) at all Air Sensitive Receivers (ASR) throughout the construction period,
except the limited non-compliance with the AQO for 24-hour RSP at up to three
ASR in three of the eight construction years. Hence no significant RSP or FSP
impacts are anticipated. Therefore, only 1-hour Total Suspended Particulates
(TSP) will be monitored and audited at the proposed monitoring locations.
Details of the proposed monitoring locations are presented in Section 2.1.5
2.1.2.2
One-hour TSP levels shall be measured to indicate the impacts of
construction dust on air quality. The TSP levels shall be measured by following
the standard high volume
sampling method as set out in the Title 40 of the Code of Federal Regulations,
Chapter 1 (Part 50), Appendix B. Upon approval of
the AAHK / PM, as an alternative to using high volume sampling method, 1-hour
TSP levels can be measured by direct reading methods which are capable of
producing comparable results as that by the high volume sampling method, to
indicate short event impacts.
2.1.2.3
All relevant data including temperature, pressure, weather conditions,
elapsed-time meter reading for the start and stop of the sampler,
identification and weight of the filter paper, and any other local atmospheric
factors affecting or affected by site conditions etc. shall be recorded down in
detail. A sample data sheet is shown in Appendix
B. The ET may develop project specific
data sheet to suit this EM&A programme.
2.1.3 Monitoring Equipment
2.1.3.1
High volume sampler (HVS) shall be used
for carrying out the 1-hour TSP monitoring.
2.1.3.2
The ET is responsible for provision of the monitoring equipment. They
shall ensure that sufficient number of samplers with an appropriate calibration
kit is available for carrying out the baseline monitoring, regular impact
monitoring and ad hoc monitoring. The samplers shall be equipped with an
electronic mass flow controller and be calibrated against a traceable standard
at regular intervals. All the equipment, calibration kit, filter papers, etc.
shall be clearly labelled.
2.1.3.3
Initial calibration of dust monitoring equipment shall be conducted upon
installation and thereafter at bi-monthly intervals. The transfer standard
shall be traceable to the internationally recognised primary standard and be
calibrated annually. The calibration data shall be properly documented for
future reference by the concerned parties such as the IEC. All the data shall
be converted into standard temperature and pressure condition.
2.1.3.4
The flow-rate of the sampler before and after the sampling exercise with
the filter in position shall be verified to be constant and be recorded down in
the data sheet as shown in Appendix
B.
2.1.3.5
If the ET proposes to use a direct reading dust meter to measure 1-hour
TSP levels, they shall submit sufficient information to the IEC to prove that
the instrument is capable of achieving a comparable result as that of the HVS
and may be used for the 1-hour sampling. The instrument shall also be
calibrated regularly, and the 1-hour sampling shall be determined periodically
by HVS to check the validity and accuracy of the results measured by direct
reading method.
2.1.3.6
Wind data monitoring equipment shall also be provided and set up at
conspicuous locations for logging wind speed and wind direction near to the
dust monitoring locations. The equipment installation location shall be
proposed by the ET and agreed with the IEC. For installation and operation of
wind data monitoring equipment, the following points shall be observed:
● The wind sensors shall be installed
on masts at an elevated level 10 m above ground so that they are clear of
obstructions or turbulence caused by the buildings;
● The wind data shall be captured by a
data logger. The data recorded in the data logger shall be downloaded
periodically for analysis at least once a month;
● The wind data monitoring equipment
shall be re-calibrated at least once every six months; and
● Wind direction shall be divided into
16 sectors of 22.5 degrees each.
2.1.3.7
In exceptional situations, the ET may propose alternative methods to
obtain representative wind data upon approval from the AAHK / PM and agreement
from the IEC.
Proposed Use of Portable Direct Reading Dust Meter and Existing Wind
Data from Chek Lap Kok Wind Station
2.1.3.8
Based on the provisions and
requirements set out in Section 2.1.3.5 above, a proposal of using
portable direct reading dust meter in undertaking the EM&A for the 3RS
project was submitted to the IEC, and agreement from the IEC was obtained. The
proposal concluded that the portable direct reading dust meter is capable to
provide comparable results of monitoring data as that provided by HVS, and with
the benefits of allowing prompt and direct results for the EM&A reporting.
The portable direct reading dust meter will be calibrated every year against
HVS to check the validity an accuracy of the results measured by direct reading
method.
2.1.3.9
On the other hand, the proposed use
of existing wind data from Chek Lap Kok Wind Station operated by HKO for wind
data collection instead of setting up a separate station near the existing
station was submitted to the IEC. Agreement from the AAHK / PM and IEC’s
approval was obtained.
2.1.4
Laboratory
Measurement / Analysis
2.1.4.1
A clean laboratory with constant temperature and humidity control, and
equipped with necessary measuring and conditioning instruments, to handle the
dust samples collected, shall be available for sample analysis, and equipment
calibration and maintenance. The laboratory should be the Hong Kong Laboratory Accreditation Scheme (HOKLAS) accredited or other internationally
accredited.
2.1.4.2
If a site laboratory is set up or a non-HOKLAS accredited laboratory is
hired for carrying out the laboratory analysis, the laboratory equipment shall
be approved by the AAHK / PM and the measurement procedures should be witnessed
by the IEC. Measurement performed by the laboratory shall be demonstrated to
the satisfaction of the AAHK / PM and the IEC. The IEC shall conduct regular
audit to the measurement performed by the laboratory to ensure the accuracy of
measurement results. The ET shall provide the AAHK / PM with one copy of the
Title 40 of the Code of Federal regulations, Chapter 1 (part 50), Appendix B
for his reference.
2.1.4.3
Filter paper of 8” X 10” shall be labelled before sampling of TSP. It
shall be a clean filter paper with no pin holes, and shall be conditioned in a
humidity controlled chamber for over 24-hour and be pre-weighed before use for
the sampling.
2.1.4.4
After sampling, the filter paper loaded with dust shall be kept in a
clean and tightly sealed plastic bag. The filter paper is then returned to the
laboratory for reconditioning in the humidity controlled chamber followed by
accurate weighing by an electronic balance with a readout down to 0.1 mg. The
balance shall be regularly calibrated against a traceable standard.
2.1.4.5
All the collected samples shall be kept in a good condition for six
months before disposal.
2.1.5
Monitoring Locations
Technical
Specifications as Presented in the Original EM&A Manual
2.1.5.1
Two separate air quality monitoring
locations are proposed and summarised in Table 2‑1.
The status and locations of dust sensitive receivers may change after issuing
this Manual. If such cases exist, the ET should propose updated monitoring
locations and seek agreement from EPD, and agreement from the AAHK / PM and IEC
before baseline monitoring commences.
Table 2‑1:
Construction Air Quality Monitoring Stations
ID
|
ID Adopted in EIA
|
Description
|
Monitoring Parameters
|
AR1
|
TC-13
|
Seaview Crescent Block 1
|
1-hour TSP
|
AR2
|
ST-1
|
Village house at Tin Sum
|
1-hour TSP
|
2.1.5.2
When alternative monitoring locations are proposed, the following
criteria, as far as practicable, shall be followed:
● At the site boundary or such
locations close to the major dust emission source;
● Close to the sensitive receptors;
and
● Take into account the prevailing
meteorological conditions.
2.1.5.3
Monitoring equipment must be positioned, sited and orientated properly.
The ET should agree with the AAHK / PM in consultation with the IEC on the
position of the samplers for the installation of the monitoring equipment. When
positioning the samplers, the following points shall be noted:
● A horizontal platform with
appropriate support to secure the samplers against gusty wind shall be
provided;
● No two samplers shall be placed less
than 2 m apart;
● The distance between the sampler and
an obstacle, such as buildings, must be at least twice the height that the
obstacle protrudes above the sampler;
● A minimum of 2 m of separation from
walls, parapets and penthouses is required for rooftop samplers;
● A minimum of 2 m separation from any
supporting structure, measured horizontally is required;
● No furnace or incinerator flue is
nearby;
● Airflow around the sampler is
unrestricted;
● The sampler is more than 20 m from
the dripline;
● Any wire fence and gate, to protect
the sampler, shall not cause any obstruction during monitoring;
● Permission must be obtained to set
up the samplers and to obtain access to the monitoring stations; and
● A secured supply of electricity is
needed to operate the samplers.
2.1.5.4
The ET may, depending on site conditions and monitoring results, decide
whether additional monitoring locations should be included or any monitoring
locations could be removed / relocated during any stage of the construction
phase.
Updated Monitoring
Locations
2.1.5.5
Based on the provisions and
requirements set out in Sections 2.1.5.1 and 2.1.5.2 above, a
change in monitoring location was proposed for AR1 (Block 1 at Seaview
Crescent), and agreement was obtained from the AAHK / PM and IEC and EPD.
The location of the alternative monitoring station, AR1A, is shown in Drawing No. MCL/P132/EMA/2-001.
The location of the originally proposed monitoring location AR1 is also shown
in the same drawing for easy reference. Table 2‑2
summarises the updated locations of the construction air quality monitoring
stations.
2.1.5.6
A change of the monitoring location
in both the baseline and subsequent impact monitoring for AR1 was identified
necessary as access was not granted for setting up the onsite monitoring
station. The new monitoring location AR1A is situated in close proximity
to Seaview Crescent and it is also considered to be a representative location
for monitoring the construction phase air quality impact from the project.
Table 2‑2:
Updated Locations of Construction Air Quality Monitoring Stations
ID
|
ID Adopted in EIA
|
Description
|
Monitoring Parameters
|
AR1A(1)
|
-
|
Man Tung Road Park
|
1-hour TSP
|
AR2
|
ST-1
|
Village house at Tin Sum
|
1-hour TSP
|
Note: (1) alternative air quality monitoring
location
2.1.6 Baseline Monitoring
2.1.6.1
Baseline monitoring should be conducted at all designated monitoring
locations, see Table
2‑1, for at least 14 consecutive days
before commencement of construction work to obtain ambient 1‑hour TSP
samples. The commencement date of baseline monitoring shall be agreed between
the ET / IEC / AAHK / PM to ensure timely submission of the baseline monitoring
report to EPD. The selected baseline monitoring stations should reflect
baseline conditions at the stations. One-hour TSP sampling shall also be done
at least three times per day. The baseline monitoring will provide data for the
determination of the appropriate Action Levels with the Limit Levels set
against statutory or otherwise agreed limits. General meteorological conditions
(wind speed, wind direction and precipitation) and notes regarding any
significant adjacent dust producing sources should also be recorded throughout
the baseline monitoring period.
2.1.6.2
Before commencing the baseline monitoring, the ET shall inform the IEC
of the baseline monitoring programme such that the IEC can conduct on-site
audit to ensure accuracy of the baseline monitoring results. During the
baseline monitoring, there should not be any construction dust generating
activities in the vicinity of the monitoring stations.
2.1.6.3
In case the baseline monitoring cannot be carried out at the designated
monitoring locations during the baseline monitoring period, the ET shall carry
out the monitoring at alternative locations that can effectively represent the
baseline conditions at the impact monitoring locations. The alternative
baseline monitoring locations should be approved by the AAHK / PM and agreed
with the IEC.
2.1.6.4
In exceptional cases, when insufficient baseline monitoring data or
questionable results are obtained, the ET should liaise with the IEC and EPD to
agree on an appropriate set of data to be used as baseline reference and submit
to EPD for approval.
2.1.6.5
Ambient conditions may vary seasonally and should be reviewed once every
six months. If the ET considers that significant changes in the ambient
conditions have risen, a repeat of the baseline monitoring may be carried out
to update the baseline levels and air quality criteria after consultation and
agreement with the AAHK / PM, IEC and EPD. The monitoring should be undertaken
at times when Contractor’s activities are not generating dust, at least in the
proximity of the monitoring stations. Should change in ambient conditions be
determined, the baseline levels and, in turn, the air quality criteria, shall
be revised. The revised baseline levels and air quality criteria shall be
agreed with the IEC and EPD. If the ET considers that significant changes
in the ambient conditions have risen but a repeat of the 14-day baseline
monitoring is not found feasible due to the presence of ongoing construction
work, the ET may propose an alternative method for updating the baseline levels
and air quality criteria but this shall be subject to the agreement with the
IEC and EPD.
2.1.7 Impact Monitoring
2.1.7.1
The monthly schedule of the compliance and impact monitoring programme
should be drawn up by the ET one month prior to the commencement of the
scheduled construction period.
2.1.7.2
The ET should carry out impact monitoring throughout the entire course
of the Works. For 1-hour TSP monitoring, the sampling frequency of at least
three times in every six days should be undertaken when the highest dust impact
is expected to occur. Highest dust impacts will be determined by the actual
construction site condition, program and the works to be carried out. Before
commencing the impact monitoring, the ET should inform the IEC of the impact
monitoring programme such that the IEC can conduct on-site audit to ensure accuracy
of the impact monitoring results.
2.1.7.3
In case of non-compliance with the air quality criteria, more frequent
monitoring exercise, as specified in the Event and Action Plan, should be
conducted within 24 hours after the result is obtained. This additional
monitoring shall be continued until the excessive dust emission or the
deterioration in air quality is rectified.
2.1.8 Event and Action Plan
2.1.8.1
Baseline 1-hour TSP monitoring was conducted for 14 consecutive days
between 6 November 2015 and 27 November 2015 at two air quality monitoring
stations of AR1A and AR2. The Action Levels for 1-hr TSP during impact
monitoring are established based on the measured baseline TSP levels for
assessing the impact and compliance during the construction of the project. Table 2‑3 shows the air quality criteria, namely Action Level (AL)
and Limit Level (LL) to be used. Should non-compliance of the air quality
criteria occurs, actions in accordance with the Event and Action Plan in Table 2‑4 should
be carried out.
Table 2‑3:
Action and Limit Levels for Air Quality
Parameters
|
Action Level [1]
|
Limit Level (µg/m3)
|
1-hour TSP Level in µg/m3
|
For baseline level ≤ 384 µg/m3,
Action Level = (130% of baseline level + Limit Level)/2
For baseline level ˃ 384 µg/m3, Action
Level = Limit Level
|
500
|
|
Note:
[1] According to the latest submission of
Baseline Monitoring Report approved by EPD, the Action Levels for AR1A and AR2
are 306 µg/m3 and 298 µg/m3 respectively.
Table 2‑4:
Event and Action Plan for Air Quality
Event
|
ET
|
IEC
|
Action
AAHK / PM
|
Contractor
|
Action Level
|
|
|
|
|
1. Exceedance for one sample
|
1. Identify source, investigate the causes of
exceedance and propose remedial measures;
2. Inform IEC and AAHK / PM;
3. Repeat measurement to confirm finding;
4. Increase monitoring frequency to daily.
|
1. Check monitoring data submitted by ET;
2. Check Contractor’s working method.
|
1. Notify Contractor.
|
1. Rectify any unacceptable practice;
2. Amend working methods if appropriate.
|
2. Exceedance for two or more consecutive samples
|
1. Identify source;
2. Inform IEC and AAHK / PM;
3. Advise the AAHK / PM on the effectiveness of the
proposed remedial measures;
4. Increase monitoring frequency to daily;
5. Discuss with IEC and Contractor on remedial actions
required
6. If exceedance continues, arrange meeting with IEC
and AAHK / PM
7. If exceedance stops, cease additional monitoring.
|
1. Check monitoring data submitted by ET;
2. Check Contractor’s working method
3. Discuss with ET and Contractor on possible remedial
measures;
4. Advise AAHK / PM on the effectiveness of the
proposed remedial measures;
5. Supervisor implementation of remedial measures.
|
1. Confirm receipt of notification of failure in
writing;
2. Notify Contractor;
3. Ensure remedial measures properly implemented.
|
1. Submit proposals for remedial actions to IEC within
three working days of notification;
2. Implement the agreed proposals;
3. Amend proposal if appropriate.
|
Limit Level
|
|
|
|
|
1. Exceedance for one sample
|
1. Identify the source, investigate the causes of
exceedance and propose remedial measures;
2. Inform AAHK / PM and Contractor. If the exceedance
is valid, inform EPD;
3. Repeat measurement to confirm finding;
4. Increase monitoring frequency to daily;
5. Assess effectiveness of Contractor’s remedial
actions and keep AAHK / PM, IEC and EPD informed of the results.
|
1. Check monitoring data submitted by ET;
2. Check Contractor’s working method;
3. Discuss with ET and Contractor on possible remedial
measures;
4. Advise AAHK / PM on the effectiveness of the
proposed remedial measures;
5. Monitor the implementation of remedial measures.
|
1. Confirm receipt of notification of failure in
writing;
2. Notify Contractor;
3. Ensure remedial measures properly implemented.
|
1. Take immediate action to avoid further exceedance;
2. Submit proposals for remedial actions to IEC within
three working days of notification;
3. Implement the agreed proposals;
4. Amend proposal if appropriate.
|
2. Exceedance for two or more consecutive sample
|
1. Notify AAHK / PM, IEC, Contractor and EPD;
2. Identify source;
3. Repeat measurement to confirm finding;
4. Increase monitoring frequency to daily;
5. Carry out analysis of Contractor’s working
procedures to determine possible mitigation to be implemented;
6. Arrange meeting with AAHK / PM and IEC to discuss
the remedial actions to be taken;
7. Assess effectiveness of Contractor’s remedial
actions and keep AAHK / PM, IEC and EPD informed of the results;
8. If exceedance stops, cease additional monitoring.
|
1. Check monitoring data submitted by ET;
2. Check Contractor’s working method;
3. Discuss amongst AAHK / PM, ET, and Contractor on
the potential remedial actions;
4. Review Contractor’s remedial actions whenever
necessary to assure their effectiveness and advise AAHK / PM accordingly;
5. Monitor the implementation of remedial measures.
|
1. Confirm receipt of notification of failure in
writing;
2. Notify Contractor;
3. In consultation with IEC, agree with the Contractor
on the remedial measures to be implemented;
4. Ensure remedial measures properly implemented;
5. If exceedance continues, consider what portion of
the work is responsible and instruct the Contractor to stop that portion of
work until the exceedance is abated.
|
1. Take immediate action to avoid further exceedance;
2. Submit proposals for remedial actions to IEC within
three working days of notification;
3. Implement the agreed proposals;
4. Resubmit proposals if problem still not under
control;
5. Stop the relevant portion of works as determined by
AAHK / PM until the exceedance is abated.
|
2.1.9 Mitigation Measures
2.1.9.1
Appropriate dust suppression measures should be adopted as required under
the Air Pollution Control (Construction Dust) Regulation as well as the
Specified Process licences for the concrete batching plants, asphalt batching
plants and rock crushing plant. A control programme can be instigated to
monitor the construction process in order to enforce dust controls and modify
methods of works where feasible to reduce the dust emission down to acceptable
levels. The implementation schedule of the recommended air quality mitigation
measures is presented in Appendix
C.
2.2
Operational Air Quality Monitoring
2.2.1 General
2.2.1.1
The operational air quality impact
assessment presented as part of the EIA Report has concluded that the operation
of the project will not give rise to adverse residual air quality
impacts. The assessment findings for Year 2031 3RS scenario indicated
that cumulative NO2, RSP, FSP, SO2 and CO levels comply
with the relevant AQOs at all ASR. Nevertheless, to be prudent, it is proposed
that AAHK should carry out regular reviews of the operation phase air quality
monitoring results and relevant operation data in order to:
● Monitor the variations in pollutant
concentrations and compare these with the operation air quality assessment
results presented in the EIA Report;
● Determine the effectiveness of
AAHK’s measures and initiatives aimed at further reducing air pollutant
emissions from airport activities and operations; and
● Identify follow-up actions and / or
further investigation that may be undertaken where necessary with a view to
further reducing air emissions associated with the operation of the
project.
2.2.2 Regular Review of Air Quality
Monitoring Results
Existing Air
Quality Monitoring Stations
2.2.2.1
While the establishment of additional air quality monitoring station was
not identified necessary, the EIA Report recommended that the current airport
air quality monitoring stations shall be maintained. These include three
air quality monitoring stations (AQMSs) operated by AAHK, with one at Sha Chau
(SC) and two on the existing airport island, namely the North Station (PH1) and
South Station (PH5), as shown in Drawing No.
MCL/P132/EMA/2-002. The AQMS at
Tung Chung (TC) operated by EPD is also shown in the drawing.
2.2.2.2
The PH1 and PH5 stations are
positioned on the airport island close to the existing north runway (or the
future middle runway after the airport expansion) and the existing south runway
respectively; the SC station is over 2.8 km to the north of the expanded
airport island; while the TC station is located on the southeast side of the
airport island. This network of existing AQMSs is considered to be able to
provide representative monitoring data on the air quality on the expanded
airport island and its surrounding areas. Therefore, the AQMSs currently
operated by AAHK are to be maintained and the monitoring data obtained from
these stations should be used, together with that from the TC AQMS operated by
EPD, for regular reviews of the operation phase air quality.
2.2.2.3
Table 2-5 summaries the existing AQMSs operated by AAHK.
Table 2-5:
Operational Air Quality Monitoring
Station ID
|
Station Name
|
Location
|
Operated by
|
Monitoring Parameters
|
SC
|
Sha Chau
|
Sha Chau
|
Airport Authority
|
Conc. of NO2, RSP, FSP, O3, SO2
and CO reported on hourly basis
|
PH1
|
North Station
|
Existing airport island
|
Airport Authority
|
Conc. of NO2, RSP, FSP, O3, SO2
and CO reported on hourly basis
|
PH5
|
South Station
|
Existing airport island
|
Airport Authority
|
Conc. of NO2, RSP, FSP, O3, SO2
and CO reported on hourly basis
|
Existing Monitoring
Equipment
2.2.2.4 The existing monitoring equipment of NO2,
RSP, FSP, O3, SO2 and CO at the three AQMSs operated by
AAHK are summarised in Table 2-6. As the equipment may
be replaced due to certain period of utilisation, the monitoring equipment
shall be reviewed by the ET prior to the monitoring during operational phase of
the project.
Table
2-6:
The Existing Monitoring Equipment Adopted at South Station, North Station and
Sha Chau Station
Parameters
|
Adopted Technique
|
Existing monitoring equipment
|
NO2
|
Gas Phase Chemiluminescence
|
Ecotech EC9841B / Thermo Scientific 42i
|
RSP
|
Drawing air through a filter at a constant rate,
continuously weighing the filter and calculating near real-time mass
concentrations
|
TEOM 1405DF Ambient Particulate Monitor
|
FSP
|
O3
|
Non-dispersive ultraviolet (UV) photometer
|
Thermo Scientific 49i/ Ecotech EC9810B
|
SO2
|
Ultraviolet Flourescence
|
Thermo Scientific 43i/ Ecotech EC9850B
|
CO
|
Gas Filter Correlation photometry
|
Thermo Scientific 48i/ Ecotech EC9830B
|
Selection of Air Quality Parameters for Review
2.2.2.5
NOx is the key air pollutant
associated with airport operations. The source contribution breakdown for the
cumulative annual average NO2 impact at the key sensitive areas
under the 3RS scenario in the worst assessment year of 2031 presented in Table
5.5.2 of the EIA Report are reproduced in Table 2-7 below.
The dominant emission sources were identified to be from ambient emissions,
which contributed in most cases more than 60% of the total NO2
concentrations. This is followed by proximity infrastructure emissions
(10 – 30%) and airport-related emissions (< 10%), except for Sha Lo Wan.
Table 2-7:
Concentration Breakdown for the Cumulative Annual NO2 Impact at the
Key Sensitive Area under the 3RS scenario in Year 2031
Area
|
ASR
|
Airport Related Emission (µg/ m3)
|
Proximity Infrastructure Emission (µg/ m3)
|
Ambient (µg/ m3)
|
Cumulative Impact (µg/ m3)
|
Tung Chung
|
TC-22
|
2
|
9
|
22
|
33
|
Tung Chung West
|
TC-P7
|
2
|
6
|
22
|
30
|
Tung Chung East
|
TC-P12
|
2
|
4
|
22
|
28
|
Sha Lo Wan
|
SLW-1
|
12
|
4
|
20
|
36
|
Tuen Mun[1]
|
TM-10
|
2 [1]
|
9
|
27
|
38
|
Note:
[1] Airport related
emission is included in ambient in PATH model for Tuen Mun area
2.2.2.6
Based on the operational air quality
assessment findings presented in the EIA Report, NO2 is considered
as the key parameter for which the available monitoring data obtained at AAHK’s
AQMSs together with that obtained at EPD’s AQMS in TC should be regularly
reviewed during the operation phase of the project. The regular review shall
also analyse and present the measured NO and NOx concentrations for
estimating the pollutant contribution due to airport operations. To be prudent,
available monitoring data on RSP and FSP should also be included in the regular
reviews.
Frequency of Review
2.2.2.7
It is recommended that the first
review of NO2, RSP and FSP monitoring results should be carried out
after the first year of operation of 3RS. Regular review should then be carried
out at regular interval of at least every five years during the first 20 years
of operation of the project. The frequency of the reviews may be subject to
changes depending on the review results.
2.2.3
Operational Phase Air Quality Monitoring and Audit
Requirements
2.2.3.1
During the regular review of NO2,
RSP and FSP monitoring results, a detailed examination of the temporal and
spatial variations of pollutant levels measured at AAHK’s AQMSs shall be
presented and the analysis shall also take into consideration the available
monitoring data obtained at EPD’s AQMS in TC. With consideration of the
available data including those on meteorological conditions (i.e., wind
direction, wind speed, temperature, precipitation, etc), the review shall
characterise the mean seasonal and diurnal variation of pollutant concentrations,
with a view to evaluating the significance of the contribution of air quality
impact from airport emissions on the nearby air sensitive receivers. Also, the
regular review shall include the compilation of an updated inventory of major
emission sources, including emissions from aircraft landing take-off (LTO)
cycle, associated with the airport operations. AAHK shall collect the relevant
information for development of the latest airport emissions inventory as part
of the review.
2.2.3.2
As part of the regular review, the
effectiveness of existing measures and initiatives implemented by AAHK aimed at
further reducing air pollutant emissions from airport operation shall also be
evaluated. Follow-up actions and/or further investigation work that may
be undertaken where necessary with a view to further reducing air emissions
associated with the operation of the project should be recommended as part of
the regular review.
2.2.3.3
The detailed air quality monitoring
and auditing requirements should be presented as part of the Airport Operation
related Emissions Control Plan that shall be submitted no later than 3 months
before the operation of the project in accordance to EP Condition 2.24.
3
Hazard to Human Life
3.1
Introduction
3.1.1.1
A hazard identification workshop has been conducted in the EIA Report to
identify potential hazards associated with the construction and operation phase
of the project. Mitigation measures have also been explored to prevent the hazards
from happening and they will be implemented in the project.
3.1.1.2
A hazard assessment has been
conducted in the EIA Report which concluded that the risk level for the
construction phase is within the acceptable region and mitigation measure is
not required. The risk level for the operation phase has been evaluated to be
in As Low As Reasonably Practicable (ALARP) region and the major risk
contributor is aircraft refuelling operation. Practicable and cost effective
mitigations have been proposed to reduce the risk of aircraft refuelling
operation.
3.2
Recommendation
3.2.1.1
The recommended measures as outlined in the Implementation Schedule
included as Appendix
C in this EM&A Manual should be
implemented to meet the Technical Memorandum on Environmental Impact Assessment
Process (EIAO-TM) requirements.
4
Noise Impact
4.1 Aircraft Noise Monitoring
4.1.1 Aircraft Noise Monitoring and Audit
Requirements
4.1.1.1
As per the requirements set out in
Section 7, Appendix C of the EIA Study Brief, the aircraft noise monitoring and
audit plan shall:
● Provide data and information for
verifying predictions on the effectiveness of measures to mitigate aircraft
noise impact of the project;
● Formulate audit requirements,
including any necessary compliance and post-project audit program, in order to
review the monitoring data and identify any remedial works, as necessary,
required to address unacceptable or unanticipated aircraft noise impacts; and
● Provide tools, procedures and
supplementary information, including noise descriptor and flight tracks, which
are useful and relevant for communicating the aircraft noise of the project to
the general public.
4.1.1.2
The Procedures for Mitigation of
Aircraft Noise that shall be submitted no later than 3 months before the
operation of the project in accordance to EP Condition 2.21.
4.1.2 Program Elements
4.1.2.1
Taking into account the EIA Study
Brief requirements as described above, it is proposed that the aircraft noise
monitoring and audit plan should consist of the following key elements:
● An exercise by AAHK to verify
predictions on the effectiveness of measures to mitigate aircraft noise impact
and the preparation of a Prediction Verification Report;
● Review Report, prepared on an annual
basis by AAHK, for detailing the compliance with noise abatement procedures and
unanticipated events, as well as any further necessary investigation and/or
remedial action(s); and
● Noise Contour Report, prepared in at
least every five years by AAHK, to compare actual airport operation to forecast
airport operation with respect to aircraft noise, taking into account data
collected on actual aircraft operational levels, fleet mix, runway and flight
track utilizations; and produce an updated noise contour using the most
currently available and internationally accepted noise modelling methodology.
4.1.2.2
In additional to the above reporting
requirements, AAHK shall continue to engage with the neighbouring communities
in the vicinity of HKIA, other stakeholders and interested parties on aircraft
noise issues associated with the operation of the project.
4.1.3 Prediction Verification
4.1.3.1
The purpose of this task is for
verification of predictions on the effectiveness of measures to mitigate
aircraft noise impact of the project. This verification exercise shall be
undertaken upon availability of relevant airport operation data for the first
full year operation of the third runway of the project. A Prediction
Verification Report, certified by the ETL and verified by the IEC, shall be
submitted to EPD for approval.
4.1.3.2
As part of the prediction
verification exercise, AAHK should collect radar data showing airport and
flight operations for the first full year operation of the proposed third
runway from Civil Aviation Department (CAD). Based on the radar data
collected, the AAHK should carry out aircraft noise contour simulation.
Similar approach adopted to process radar data for the prevailing scenario contour
as presented in Chapter 7 of the EIA Report might be applied (individual radar
data be pre-processed and annual daily average noise contours be produced by
Integrated Noise Model (INM) for daily results) and the detailed methodology
shall be agreed with EPD. The computational model to be used shall also
be agreed with EPD prior to the analysis.
4.1.3.3
The Noise Exposure Forecast (NEF) 25
contour prepared based on radar data should be compared against the noise
contours presented in Chapter 7 of the EIA Report for verifying the
effectiveness of measures to mitigate the aircraft noise impact of the
project. If the comparison of contours shows a reasonable converge, this
would imply the aircraft noise prediction by computer simulation with forecast,
assumptions and proposal of mitigation measures would reliably reflect that by
actual airport and flight operations. In case discrepancies are observed,
explanation shall be given and analysed as part of the Prediction Verification
Report.
4.1.3.4
It shall be noted that the noise
contours presented in Chapter 7 of the EIA Report are based on reasonable
assumptions and input data including air traffic forecast, runway mode of
operation, flight tracks and flight track utilisation, and proposed mitigation
measures. Therefore, whilst it is being compared with the one generated
by actual airport and flight operations, variances within reasonable ranges are
envisaged and considered acceptable. Having said that, it is essential to
ensure that with the mitigation measures recommended in the EIA Report, no
additional noise sensitive receivers should be subject to adverse environmental
impact under the requirements of the EIAO-TM. Detailed examination should
be followed especially for those areas with major variances and the underneath
rationale(s) will be elaborated.
4.1.4 Review Report
4.1.4.1
The Review Report, prepared on an
annual basis by AAHK shall include an analysis of how well aircraft flight
follow each of the aircraft noise mitigation measures recommended in Chapter 7
of the EIA Report. Information to be collected shall include available
radar data showing airport and flight operations from CAD, and this is to be
analysed in terms of flight tracks and runway utilisation for checking the
effective implementation of the noise reduction measures. AAHK may make
references to available operational noise data collated by the relevant
authorities. Wind record in the year should also be collected from HKO.
The Review Report should review the data collected including measured noise
levels at representative locations, statistics of flight tracks, flight tracks
dispersion and aircraft using proposed mitigation measures and existing noise
mitigation measures, etc.
4.1.4.2
The annual review and reporting process
will allow AAHK to measure exactly how it stands compared to predicted
operations used in the preparation of the EIA Report. If there are any major
variances / discrepancies / abnormalities that are observed during the ongoing
process of data collection and analysis for preparation of the annual review
when compared with the assumptions / measures adopted in the assessment, early
investigation shall be carried out for identification of the possible causes of
the variances / discrepancies / abnormalities and whether these would
significantly affect the aircraft noise environment.
4.1.5 Noise Contour Report
4.1.5.1
As the aircraft noise impact
assessment was undertaken on the basis of projected air traffic movements and
estimated fleet mix, it is recommended that at regular intervals of at least
every five years during the first 20 operational years of the project, actual
flight data obtained from local Air Traffic Control radar systems should be
acquired and analysed with a similar aircraft noise modelling methodology to
confirm the representativeness of the earlier noise analyses. The first Noise
Contour Report shall be prepared upon availability of the airport operation
data for the first full year operation of the third runway of the project. In
accordance with the requirements set out in Condition 2.22 of the EP, an
updated NEF 25 contour shall also be submitted no later than 3 months after a
full year of operation of the 3RS project. Similar approach adopted to process
radar data for prevailing scenario contour might be applied and the detailed
methodology shall be agreed with EPD.
4.1.5.2
At such time that it is determined
that the noise contours obtained using actual airport data may start to
encroach onto any additional noise sensitive receivers, or when it is
considered that there are major deviations from the assumptions adopted in the
EIA Report, additional analysis would be necessary to update the NEF 25
contour. The need and feasibility of introducing additional mitigation
measures should also be assessed to ensure that no adverse environmental impact
would be resulted from the implementation of the project with respect to
aircraft noise.
4.1.6 Community Liaison
4.1.6.1
AAHK has been actively engaging with
neighbouring communities in the vicinity of the airport, other stakeholders
groups and interested parties to communicate issues and gauge views on aircraft
noise and other environmental aspects. Briefings and airport visits are
organised to explain subjects including but not limited to flight paths under
the planned 3RS and the proposed aircraft noise mitigation measures. These
engagement activities will continue after commencement of the project and a
community liaison plan that presents details of the planned programme,
including proposed communication channels, tools, procedures and supplementary
information, including noise descriptor and flight tracks in accordance with
Section 7.3, Appendix C of the Study Brief and activities that would facilitate
communications with stakeholders on aircraft noise issues, will be developed by
AAHK as part of the detailed Aircraft Noise Monitoring and Audit Plan presented
in Section 4.1.7 below.
4.1.7 Detailed Aircraft Noise Monitoring
and Audit Plan
4.1.7.1
The above subsections set out a clear
EM&A framework with respect to aircraft noise. It is not yet mature
to define all the monitoring and audit details as at the course of assessment
whilst the EM&A task will only be started with operation commencement of
the third runway of the project because computation model and data analysis
tools are in rapid evolution nowadays.
4.1.7.2
Prior to commencement of project operation,
a detailed Aircraft Noise Monitoring and Audit (ANM&A) Plan, proposing (i)
work programme; (ii) actual data collection; (iii) methodologies / procedures,
including proposed computation model, to process data into indicators of
measures / assumptions adopted; (iv) quality control and assurance procedure;
(v) action / investigation plan if any non-compliance, including associated
Action and Limit Levels; (vi) community liaison plan; (vii) relevant proforma
forming part of the reports; (viii) any foreseeable uncertainties, etc, should
be submitted to EPD for agreement.
4.1.7.3
In accordance with the requirements
set out in EP Condition 2.23, the ANM&A Plan shall include information on
aircraft noise monitoring at representative locations in Tung Chung, Ma Wan,
Tsing Yi, Tsuen Wan, Ting Kau, Siu Lam and Tuen Mun. The ANM&A Plan shall
make use of available aircraft noise and flight track monitoring data including
measured noise levels in terms of dB(A) and their distribution, flight tracks, aircraft
fleet mix data and other relevant information at the above-mentioned locations.
The ANM&A Plan shall also include an action plan, as approved by
Director-General of Civil Aviation, to review the noise data to assess the
effectiveness of the mitigation measures and to take appropriate action with
reference to the prevailing internationally recognised standards in aircraft
noise mitigation.
4.1.7.4
Before submission to the Director of
Environmental Protection for approval, the ANM&A Plan shall be certified by
the ETL and verified by the IEC as conforming to the information and
recommendations described in the EIA Report, and taking into account any
specific requirements with respect to the latest in-situ conditions of the
project.
4.1.7.5
When developing the detailed plan,
references should be made to relevant international guidelines such as SAE
ARP4721 Part 1 – Monitoring Aircraft Noise and Operations in the Vicinity of
Airports: System Description, Acquisition, and Operation, if applicable, for
the purpose of review and describe the project operation. The latest monitoring
and audit practice / presentation adopted by similar international airports
should be reviewed and reference during the course of preparation of this
detailed plan.
4.2
Fixed
Noise Sources Monitoring
4.2.1 Maximum Permissible Sound Power
Levels of Fixed Plant
4.2.1.1
The maximum permissible sound power
levels of the identified fixed noise sources of the project were predicted in
the EIA Report. The specified sound power levels should be
implemented and refined by the Contractor as appropriate to ensure that the
noise impact associated with the fixed plant operations would comply with the
noise standards stipulated in the EIAO-TM and Noise Control Ordinance (NCO).
4.2.2 Commissioning Test
4.2.2.1
Prior to the operation of the
project, the Contractor should conduct noise commissioning tests for all major
fixed plant noise sources (excluding the ground noise sources associated with
the aircraft taxiing and the operation of auxiliary power units (APUs)) within
HKIA to ensure the noise emission at the fixed plant noise source comply with
the EIA Report assessed scenario. The test should be carried out by a
qualified person possessing at least seven years of noise control experience
and a corporate membership of Hong Kong Institute of Acoustics or
equivalent. The noise commissioning test report should be submitted
to the AAHK / PM, ET and IEC for approval. The ET and IEC should review design
changes to ensure the cumulative noise impact from fixed noise sources comply
with the EIA Report assessed scenario.
4.2.2.2
Noise commissioning tests are also
required for noise enclosure of aircraft engine run-up facilities. ISO 10847 –
In-situ determination of insertion loss of outdoor noise barriers of all types
shall be employed to ensure the required noise reduction (insertion loss) in
the EIA Report (at least 15 dB(A)) would be achieved. The test should be
carried out by a qualified person possessing at least seven years of noise
control experience and a corporate membership of Hong Kong Institute of
Acoustics or equivalent. The noise commissioning test report should be
submitted to the AAHK / PM, ET and IEC for approval.
4.2.2.3
No adverse noise impacts are
anticipated from aircraft taxiing and APU operation, hence no environmental
monitoring and audit is proposed.
4.2.3 Mitigation Measures
4.2.3.1
The relevant noise mitigation
measures have been recommended in the EIA Report. The implementation
schedule of the mitigation measures is given in Appendix
C.
4.3
Construction
Airborne Noise Monitoring
4.3.1 Noise Parameter
4.3.1.1
The construction noise level should be measured in terms of the
A-weighted equivalent continuous sound pressure level (Leq). Leq(30
minutes) should be used as the monitoring parameter for the time period
between 0700-1900 hours on normal weekdays. For all other time periods, a
Construction Noise Permit (CNP) under the NCO would apply.
4.3.1.2
As supplementary information for data auditing, statistical results such
as L10 and L90 should also be obtained for reference. A
sample data record sheet based on the one presented in the “EM&A Guidelines
for Development Projects in Hong Kong” is shown in Appendix
B for reference.
4.3.2 Monitoring Equipment
4.3.2.1
As referred to in the Technical Memorandum (TM) issued under the NCO,
sound level meters in compliance with the International Electrotechnical
Commission Publications 651:1979 (Type 1) and 804:1985 (Type 1) specifications should
be used for carrying out the noise monitoring. Immediately prior to and
following each noise measurement the accuracy of the sound level meter should
be checked using an acoustic calibrator generating a known sound pressure level
at a known frequency. Measurements may be accepted as valid only if the
calibration level from before and after the noise measurement agrees to within
1.0 dB.
4.3.2.2
Noise measurements should be made in accordance with standard acoustical
principles and practices in relation to weather conditions. Handheld wind meter should be used for measuring and
checking the wind speed (in m/s) during the noise monitoring.
4.3.2.3
The ET is responsible for the
availability of monitoring equipment and should ensure that sufficient noise
measuring equipment and associated instrumentation are available for carrying
out the baseline monitoring, regular impact monitoring and ad hoc monitoring.
All the equipment and associated instrumentation should be clearly labelled.
4.3.3 Monitoring Locations
4.3.3.1
The noise monitoring locations are
summarised in Table 4‑1. The status and
locations of noise sensitive receivers may change after issuing this manual. If
such case exists, the ET should propose updated monitoring locations and seek
approval from the AAHK / PM and agreement from the IEC and EPD of the proposal.
Table 4‑1:
Construction Noise Monitoring Stations
ID
|
ID adopted in EIA
|
Description
|
NM1
|
TC-1
|
Seaview Crescent Block 1
|
NM2
|
TC-5
|
Tung Chung West Development (Monitoring to start after
occupation of development in 2023/24, subject to the construction programme
of the project)
|
NM3
|
TC-30
|
Ho Yu College
|
NM4
|
TC-37
|
Ching Chung Hau Po Woon Primary School
|
NM5
|
TS-1
|
House, Tin Sum
|
NM6
|
SLW-1
|
House No. 1, Sha Lo Wan
|
4.3.3.2
When alternative monitoring locations are proposed, the monitoring
locations should be chosen based on the following criteria:
● Monitoring at sensitive receivers close
to the major site activities which are likely to have noise impacts;
● Monitoring at the noise sensitive
receivers as defined in the Technical Memorandum; and
● Assurance of minimal disturbance to
the occupants during monitoring.
4.3.3.3 The monitoring station should normally be at a point 1
m from the exterior of the sensitive receivers building facade and be at
position 1.2 m above the ground. If there is a problem with access to the
normal monitoring position, an alternative position may be chosen, and a
correction to the measurements should be made. For reference, a correction of
+3 dB(A) should be made to the free field measurements. The ET should agree
with the IEC on the monitoring position and the corrections adopted. Once the positions
for the monitoring stations are chosen, the baseline monitoring and the impact
monitoring should be carried out at the same positions.
Updated Monitoring
Locations
4.3.3.4
Based on the provisions and requirements
set out in Sections 4.3.3.1 and 4.3.3.2 above, a change in
monitoring location was proposed for NM1, NM2 and NM3. Agreement from the
AAHK / PM, IEC and EPD’s approval were obtained for the changes. The locations
of the alternative monitoring stations, including NM1A, NM2* and NM3A, are
shown in Drawing No.
MCL/P132/EMA/4-001. The locations of the originally proposed monitoring
locations (NM1, NM2 and NM3) are also shown in the same drawing for easy
reference. Table 4‑2 summarises the updated
locations of the construction noise monitoring stations.
4.3.3.5
The noise monitoring location in both
the baseline and subsequent impact monitoring for NM1 was changed to NM1A as
access to NM1 was not granted for setting up an onsite monitoring station.
4.3.3.6
The noise monitoring location in both
the baseline and subsequent impact monitoring for NM3 was changed to NM3A also
as access to NM3 was not granted for setting up an onsite monitoring station.
Moreover, when construction works of Tung Chung East Development near NM3A is
in place, the monitoring will be temporary suspended with duration subjected to
the programme of the development works and actual site conditions, and will be
resumed when the development works is completed. Actual arrangement of this
station will be reflected in relevant Monthly EM&A Reports.
4.3.3.7 Baseline noise monitoring at NM2 was undertaken at
NM2* as Tung Chung West Development had not yet been constructed. When the
future residential buildings in Tung Chung West Development become occupied,
the impact monitoring would be carried out at a representative location with
noise sensitive land uses and the exact location will be proposed by the ET for
agreement with the IEC and EPD prior to commencement of the impact monitoring.
Table 4‑2:
Construction Noise Monitoring Stations
ID
|
ID adopted in EIA
|
Description
|
NM1A(1)
|
-
|
Man Tung Road Park
|
NM2*(1) / NM2
|
TC-5
|
Tung Chung Battery* /
Tung Chung West Development (Monitoring to start after
occupation of development in 2023/24, subject to the construction programme
of the project)
|
NM3A(1)
|
-
|
Site Office at the northern edge of the reclaimed land
(Monitoring to be temporarily suspended during
construction works of Tung Chung East Development subject to programme of the
works and actual site conditions)
|
NM4
|
TC-37
|
Ching Chung Hau Po Woon Primary School
|
NM5
|
TS-1
|
House, Tin Sum
|
NM6
|
SLW-1
|
House No. 1, Sha Lo Wan
|
Note: (1)
alternative noise monitoring location
4.3.4 Baseline Monitoring
4.3.4.1
The ET should carry out baseline noise monitoring prior to the
commencement of the project-related construction activities. The baseline
monitoring should be carried out daily for a period of at least two weeks. The
commencement date of baseline monitoring shall be agreed between the ET / IEC /
AAHK / PM to ensure timely submission of the baseline monitoring report to EPD.
Before commencing the baseline monitoring, the ET should develop and submit to
the IEC the baseline monitoring programme such that the IEC can conduct on-site
audit to check accuracy of the baseline monitoring results.
4.3.4.2
There should not be any construction activities in the vicinity of the
stations during the baseline monitoring.
4.3.4.3
In exceptional cases, when insufficient baseline monitoring data or
questionable results are obtained, the ET should liaise with the AAHK / PM, IEC
and EPD to agree on an appropriate set of data to be used as a baseline
reference and submit to the AAHK / PM and IEC for agreement and EPD for
approval.
4.3.5 Impact Monitoring
4.3.5.1
Noise monitoring should be carried out at all the designated monitoring
stations when there are project-related construction activities undertaken. The
monitoring frequency should depend on the scale of the construction activities.
The following is an initial guide on the regular monitoring frequency for each
station on a weekly basis when noise generating activities are underway:
● One set of measurements between
0700-1900 hours on normal weekdays.
4.3.5.2
If construction works are extended to include works during the hours of
1900-0700 as well as public holidays and Sundays, additional impact monitoring
(including monitoring locations) during respective periods of restricted hours
should be subject to the CNP requirements by EPD. Applicable permits under NCO
should also be obtained by the Contractor.
4.3.5.3
For schools located near the HKIA
(e.g. NM4), noise monitoring should be carried out at the monitoring stations
for the schools during the school examination periods. The ET should liaise
with the school’s personnel and the Examination Authority to ascertain the
exact dates and times of all examination periods during the course of the
contract.
4.3.5.4
In case of non-compliance with the construction noise criteria, more
frequent monitoring, as specified in the Event and Action Plan in Table 4‑4, should be carried out. This additional monitoring
should be continued until the recorded noise levels are rectified or proved to
be irrelevant to the construction activities.
4.3.6 Event and Action Plan for Noise
4.3.6.1
The Action and Limit Levels for construction noise are defined in Table 4‑3. Should non-compliance of the criteria occur, action in
accordance with the Event and Action Plan in Table 4‑4, should be carried out.
Table 4‑3:
Action and Limit Levels for Construction Noise
Time Period
|
Action
|
Limit
|
0700-1900 hours on normal weekdays
|
When one valid documented complaint is received.
|
75* dB(A)
|
Note:
* reduce to 70 dB(A) for schools and 65 dB(A) during school examination
periods.
Table 4‑4: Event and Action Plan
for Construction Noise
Event
|
ET
|
IEC
|
Action
AAHK / PM
|
Contractor
|
Action Level
|
1. Notify AAHK / PM, IEC and Contractor;
2. Carry out investigation;
3. Report the results of investigation to the AAHK /
PM, IEC and Contractor;
4. Discuss with IEC and Contractor on remedial
measures required;
5. Increase monitoring frequency to check mitigation
effectiveness.
|
1. Review the investigation results submitted by the
ET;
2. Review the proposed remedial measures by the
Contractor and advise the AAHK / PM accordingly;
3. Advise AAHK / PM on the effectiveness of the
proposed remedial measures.
|
1. Confirm receipt of notification of failure in
writing;
2. Notify Contractor;
3. In consolidation with IEC, agree with the
Contractor on the remedial measures to be implemented;
4. Supervise the implementation of remedial measures.
|
1. Submit noise mitigation proposals to AAHK / PM and
IEC;
2. Implement noise mitigation proposals.
|
Limit Level
|
1. Inform AAHK / PM, IEC and Contractor;
2. Repeat measurements to confirm findings;
3. Inform EPD after confirming the validity of
exceedance;
4. Increase monitoring frequency;
5. Identify source and investigate the cause of
exceedance;
6. Carry out analysis of Contractor’s working
procedures;
7. Discus with AAHK / PM, IEC and Contractor on
remedial measures required;
8. Assess effectiveness of Contractor’s remedial
actions and keep AAHK / PM, IEC and EPD informed of the results;
9. If exceedance stops, cease additional monitoring.
|
1. Discuss amongst AAHK / PM, ET and Contractor on the
potential remedial actions;
2. Review contractor’s remedial actions whenever
necessary to assure their effectiveness and advise AAHK / PM accordingly.
|
1. Confirm receipt of notification of failure in
writing;
2. Notify Contractor;
3. In consolidation with IEC, agree with the
Contractor on the remedial measures to be implemented;
4. Supervise the implementation of remedial measures;
5. If exceedance continues, consider stopping the
Contractor to continue working on that portion of work which causes the
exceedance until the exceedance is abated.
|
1. Take immediate action to avoid further exceedance;
2. Submit proposals for remedial actions to AAHK / PM
and IEC within three working days of notification;
3. Implement the agreed proposals;
4. Submit further proposal if problem still not under
control;
5. Stop the relevant portion of works as instructed by
AAHK / PM until the exceedance is abated.
|
|
|
|
|
|
|
4.3.7 Mitigation Measures
4.3.7.1
Recommended construction noise control and mitigation measures are
proposed in the EIA Report. The Contractor should be responsible for the design
and implementation of these measures under the supervision of the AAHK / PM and
be monitored by the ET. The implementation schedule of the recommended noise
mitigation measures is presented in Appendix
C.
4.4 Road Traffic and Marine Traffic Noise Monitoring
4.4.1.1
No adverse road or marine traffic
noise impacts are anticipated from operation of the project, hence no
environmental monitoring and audit is proposed.
5
Water Quality Impact
5.1 Construction Water Quality
Monitoring
5.1.1 Introduction
5.1.1.1
The main potential water quality
impact during construction phase is the release of suspended solids (SS) during
land formation. Water jetting and field joint excavation works for the
submarine cable diversion may also generate some SS release. Environmental
monitoring for these marine works are described in Section 5.1.8.
5.1.1.2
The potential risk of contaminants
released from pore water during ground improvement via deep cement mixing (DCM)
within the contaminated mud pit areas has also been identified as a concern.
While the results of the water quality impact assessment suggests that
potential contaminant release from pore water would be insignificant, it is
recognised that full scale ground improvement works over the completed and
capped contaminated mud pits (CMPs) have not previously been implemented in
Hong Kong. Therefore, specific environmental monitoring for the initial DCM
activities are included as part of the EM&A requirements and are described
in Section 5.1.9.
5.1.2 Water Quality Parameters
5.1.2.1
Monitoring of Dissolved Oxygen (DO),
Dissolved Oxygen Saturation (DO%), pH, temperature, turbidity, salinity, and SS
should be undertaken at all designated monitoring locations. Current speed and
direction should also be measured at all monitoring locations except for
sensitive receivers that are enclosed or surrounded by silt curtains (namely
SR1A and SR8).
5.1.2.2
For monitoring of DCM works, there
will be an initial intensive monitoring of DO, DO%, pH, temperature, turbidity,
salinity, total alkalinity, SS, heavy metals and nutrients at designated
DCM-specific monitoring stations. Thereafter, total alkalinity and two
representative heavy metals will be monitored at the general monitoring
locations.
5.1.2.3
The general and DCM-specific
monitoring locations are described in Section 5.1.5. All parameters
should be measured in-situ while total alkalinity should be measured on-site
and SS, heavy metals and nutrients which should be determined by laboratory. DO
should be presented in mg/L and in % saturation.
5.1.2.4
Other relevant data should also be
recorded, including monitoring location, time, tidal stages, weather
conditions, sea conditions and any special phenomena and work underway at the
construction site.
5.1.3
Sampling Procedures and Monitoring Equipment
5.1.3.1 Water samples for all monitoring parameters should be
collected, stored, preserved and analysed according to the Standard
Methods, APHA 22nd ed. and/or other methods as agreed by the EPD.
In-situ measurements at monitoring locations including temperature, DO,
turbidity, pH, salinity and water depth should be collected by equipment with
the characteristics and functions listed in the following sections.
5.1.3.2 Sample data record sheets based on the one presented
in the “EM&A Guidelines for Development Projects in Hong Kong” are shown in
Appendix
B for reference.
5.1.3.3 The following monitoring equipment and facilities
should be provided by the ET.
Dissolved Oxygen and Temperature
Measuring Equipment
5.1.3.4
The instrument should be portable and
weatherproof using a DC power source. It should have a membrane electrode with
automatic temperature compensation complete with a cable. The equipment should
be capable of measuring:
● A dissolved oxygen level in the
range of 0-20 mg/L and 0-200 % saturation; and
● A temperature of 0-45 degree Celsius with a capability of measuring to ±0.1 degree Celsius
pH Measuring Equipment
5.1.3.5
A portable pH meter capable of
measuring a range between 0.0 and 14.0 should be provided to measure pH under
the specified conditions according to the Standard Methods, APHA.
Turbidity Measurement
Instrument
5.1.3.6
The instrument should be portable and
weatherproof using a DC power source. It should have a photoelectric sensor
capable of measuring turbidity between 0-1000 NTU.
Salinity
5.1.3.7 A portable salinometer capable of measuring salinity
in the range of 0-40 ppt should be provided for measuring salinity of the water
at each monitoring location.
Total Alkalinity
5.1.3.8
A digital titrator capable of
dispensing 0.002ml at one single dispense should be provided to measure the
amount of sulphuric acid used in determination of total alkalinity.
Nutrient, Heavy Metals
and Suspended Solids (SS)
5.1.3.9
A water sampler comprising a
transparent PVC cylinder with a capacity of not less than two litres, and could
be effectively sealed with latex cups at both ends, should be used. The sampler
should have a positive latching system to keep it open and prevent premature
closure until released by a messenger when the sampler is at the selected water
depth (e.g. Kahlsico Water Sampler or a similar instrument approved by the AAHK
/ PM and ET).
5.1.3.10
Water samples for nutrients, heavy
metals and SS analysis should be stored in high density polythene bottles with
no preservatives added, packed in ice (cooled to 4 ºC without being frozen),
and delivered to the laboratory within 24 hours of collection.
Water Depth Detector
5.1.3.11
A portable, battery-operated echo
sounder should be used for the determination of water depth at each designated
monitoring station. The unit would either be handheld or affixed to the bottom
of the work boat, if the same vessel is to be used throughout the monitoring
programme.
Positioning Device
5.1.3.12
A hand-held or boat-fixed type
digital Global Positioning System (dGPS) with way point bearing indication or
other equivalent instrument of similar accuracy should be provided and used
during monitoring to ensure the monitoring vessel is at the correct location
before taking measurements.
Calibration of In-situ Instruments
5.1.3.13
In-situ monitoring instruments for
the monitoring of temperature, DO, turbidity, pH and salinity should be
checked, calibrated and certified by a laboratory accredited under HOKLAS (or
other international accreditation scheme that is HOKLAS-equivalent) before use,
and subsequently re-calibrated at three monthly intervals throughout all stages
of the water quality monitoring. Responses of sensors and electrodes should be
checked with certified standard solutions before use.
5.1.3.14
Wet bulb calibration for the DO meter
should be carried out before commencement of monitoring and after completion of
all measurements each day. A zero check in distilled water should be performed
with the turbidity probe at least once per monitoring day. The probe should
then be calibrated with a solution of known NTU. In addition, the turbidity
probe should be calibrated at least twice per month to establish the
relationship between turbidity readings (in NTU) and levels of suspended solids
(in mg/L). Accuracy check of the digital titrator should be performed at
least once per monitoring day.
5.1.3.15
For the on-site calibration of field
equipment, the BS 1427:2009, Guide to on-site test methods for the analysis of
waters should be observed.
5.1.3.16
Sufficient stocks of spare parts
should be maintained for replacements when necessary. Backup monitoring
equipment should also be made available so that monitoring can proceed
uninterrupted even when some equipment is under maintenance, calibration etc.
5.1.4 Laboratory Measurement / Analysis
5.1.4.1 Analysis of nutrients, heavy metals and SS should be
carried out in a HOKLAS laboratory (or other international accredited
laboratory that is HOKLAS-equivalent). Sufficient water samples should be
collected at the monitoring stations for carrying out the laboratory nutrients,
heavy metals and SS determination. The nutrients, heavy metals and SS
determination work should start within 24 hours after collection of the water
samples. The analysis of nutrients, heavy metals and SS should follow the
standard methods summarised in Table 5‑1.
Table 5‑1:
Laboratory Analysis for SS, Nutrients and Heavy Metals
Parameters
|
Instrumentation
|
Analytical Method
|
Reporting Limit
|
Suspended Solid (SS)
|
Analytical Balance
|
APHA 2540D
|
2 mg/L
|
Nutrients
|
|
|
|
Ammonia as N
|
FIA
|
APHA 4500
|
0.01 mg/L
|
Unionised ammonia (NH3)*
|
By calculation
|
By calculation
|
By calculation
|
Nitrite as N
|
FIA
|
APHA 4500
|
0.01 mg/L
|
Nitrate as N
|
FIA
|
APHA 4500
|
0.01 mg/L
|
TKN as N
|
Titration
|
APHA 4500
|
0.1 mg/L
|
Total Phosphorus
|
Colorimetric
|
APHA 4500
|
0.01 mg/L
|
Reactive Phosphorus
|
FIA
|
APHA 4500
|
0.01 mg/L
|
Heavy Metals
|
|
|
|
Cadmium (Cd)
|
ICP-MS
|
USEPA 6020A
|
0.1 µg/L
|
Chromium (Cr)
|
ICP-MS
|
USEPA 6020A
|
0.2 µg/L
|
Copper (Cu)
|
ICP-MS
|
USEPA 6020A
|
0.2 µg/L
|
Nickel (Ni)
|
ICP-MS
|
USEPA 6020A
|
0.2 µg/L
|
Lead (Pb)
|
ICP-MS
|
USEPA 6020A
|
0.2 µg/L
|
Zinc (Zn)
|
ICP-MS
|
USEPA 6020A
|
1 µg/L
|
Arsenic (As)
|
ICP-MS
|
USEPA 6020A
|
1 µg/L
|
Silver (Ag)
|
ICP-MS
|
USEPA 6020A
|
0.1 µg/L
|
Mercury (Hg)
|
ICP-MS
|
APHA 7470A
|
0.05 µg/L
|
Note:
* Calculation based on the
laboratory result of ammonia nitrogen (NH4-N) and in-situ measured
pH, salinity and temperature.
5.1.4.2
If in-house or non-standard methods are
proposed, details of the method verification should, if required, be submitted
to EPD. In any circumstances, the sample testing should have comprehensive
quality assurance (QA) and quality control (QC) programmes. The laboratory
should be prepared to demonstrate the QC programmes to EPD or their
representative if and when required.
5.1.4.3
Additional duplicate samples may be
required by EPD for inter laboratory calibration. Remaining samples after
analysis should be kept by the laboratory for three months in case repeat
analysis is required.
5.1.4.4
If a site laboratory is set up or a
non-HOKLAS and non-international accredited laboratory is hired for carrying
out the laboratory analysis, the laboratory equipment, analytical procedures,
and QC shall be approved by EPD. All the analysis shall be witnessed by
the AAHK / PM. The ETL shall provide the AAHK / PM and IEC with one copy
of the relevant chapters of the “APHA Standard Methods for the Examination of
Water and Wastewater” 22nd edition and any other relevant document
for their reference.
5.1.5
Monitoring
Locations
General Monitoring Locations (during absence of the
enhanced silt curtain)
5.1.5.1
A total of 25 water quality monitoring
locations (comprising 14 impact stations, eight sensitive receiver stations and
three control stations) have been proposed for the construction and
post-construction phases. The coordinates are shown in Table
5‑2 and the locations are shown in Drawing No. MCL/P132/EMA/5-001 and MCL/P132/EMA/5-002b. The final locations and number of monitoring points
should be agreed with EPD at least two weeks before undertaking any works.
Table 5‑2:
Water Quality Monitoring Stations (baseline and impact monitoring)
Monitoring Stations
|
|
Coordinates
|
Parameters
|
|
|
Description
|
Easting
|
Northing
|
Baseline Monitoring
|
Impact Monitoring (excl. intensive DCM)
|
Construction Activities Monitored
|
C1
|
Control
|
804247
|
815620
|
DO, pH, Temperature,
Salinity, Turbidity, SS
|
General Parameters
DO, pH, Temperature,
Salinity, Turbidity, SS
DCM Parameters
Total Alkalinity, Two
Representative Heavy Metals
|
General Parameters
From commencement of advance
marine works (submarine 11 kV cable diversion) until completion of all marine
filling works for land formation
DCM Parameters
From commencement until
completion of all marine-based DCM works
|
C2
|
Control
|
806945
|
825682
|
C3(1)
|
Control
|
817803
|
822109
|
SR2(1)
|
Planned marine park / hard
corals at The Brothers / Tai Mo To
|
814166
|
821463
|
IM1
|
Impact
|
806458
|
818351
|
DO, pH, Temperature, Salinity, Turbidity, SS
Total Alkalinity
|
General Parameters
DO, pH, Temperature, Salinity, Turbidity, SS
DCM Parameters
Total Alkalinity, Two Representative Heavy Metals
|
General Parameters
From commencement of land formation until completion
of all marine filling works
DCM Parameters
From commencement until completion of all marine-based
DCM works
|
IM7
|
Impact
|
806835
|
821349
|
IM2
|
Impact
|
806193
|
818852
|
DO, pH, Temperature,
Salinity, Turbidity, SS
Total Alkalinity
|
General Parameters
DO, pH, Temperature,
Salinity, Turbidity, SS
DCM Parameters
Total Alkalinity, Two
Representative Heavy Metals
|
General Parameters
From commencement of land formation
until completion of nearest 1 km of seawall
DCM Parameters
From commencement until
completion of all marine-based DCM works
|
IM3
|
Impact
|
806019
|
819411
|
IM4
|
Impact
|
805039
|
819570
|
IM5
|
Impact
|
804924
|
820564
|
IM6
|
Impact
|
805828
|
821060
|
IM8
|
Impact
|
807838
|
821695
|
IM9*
|
Impact
|
808811
|
822094
|
DO, pH, Temperature,
Salinity, Turbidity, SS, Total Alkalinity, Heavy metals and Nutrients
|
General Parameters
From commencement of land formation
until completion of nearest 1 km of seawall
DCM Parameters
From commencement until
completion of all marine-based DCM works
|
IM12*
|
Impact
|
811519
|
821162
|
IM10*
|
Impact
|
809838
|
822240
|
General Parameters
From commencement of land
formation until completion of all marine filling works
DCM Parameters
From commencement until
completion of all marine-based DCM works
|
IM11*
|
Impact
|
810545
|
821501
|
IM13
|
Impact (for submarine 11 kV cable diversion)
|
Mobile station (500 m envelope of water jetting works)
|
n/a
|
General Parameters only
DO, pH, Temperature, Salinity, Turbidity, SS
|
General Parameters only
From commencement until completion of water jetting
works
|
IM14
|
Impact (for submarine 11 kV cable diversion)
|
Mobile station (500 m envelope of field joint
excavation works)
|
General Parameters only
From commencement until completion of field joint
excavation works
|
SR1A(2)(3)
|
Hong Kong-Zhuhai-Macao
Bridge (HZMB) Hong Kong Boundary Crossing Facilities (HKBCF) Seawater Intake
for cooling
|
812586
|
820069
|
DO, pH, Temperature,
Salinity, Turbidity, SS
|
General Parameters only
DO, pH, Temperature,
Salinity, Turbidity, SS
|
General Parameters only
From commencement of advance
marine works (submarine 11 kV cable diversion) until completion of all marine
filling works for land formation
|
812660
|
819977
|
(since 5 Jan 2019)
|
SR3
|
Sha Chau and Lung Kwu Chau
Marine Park / fishing and spawning grounds in North Lantau
|
807571
|
822147
|
SR4A(3)
|
Sha Lo Wan
|
807810
|
817189
|
SR5A(3)
|
San Tau Beach SSSI
|
810696
|
816593
|
SR6(4)
|
Tai Ho Bay, Near Tai Ho
Stream SSSI
|
814663
|
817899
|
SR6A(4)
|
814739
|
817963
|
(since 8 Aug 2019)
|
SR7
|
Ma Wan Fish Culture Zone
(FCZ)
|
823742
|
823636
|
SR8(5)
|
Seawater Intake for cooling
at Hong Kong International Airport (East)
|
811593
|
820417
|
(before 1 Jul 2017)
|
811418
|
820246
|
(1 Jul 2017 to 4 Jan 2019)
|
811623
|
820390
|
(since 5 Jan 2019)
|
Notes:
* Denotes monitoring stations for providing baseline
nutrient and heavy metal data for DCM-specific monitoring
(1) According to the
Baseline Water Quality Monitoring Report, C3 station is not adequately
representative as a control station of impact/ SR stations during the flood
tide. The control reference has been changed from C3 to SR2 from 1 September
2016 onwards.
(2) With the operation of HKBCF,
water quality monitoring at SR1A was commenced on 25 October 2018. The
monitoring location of SR1A was shifted closer to the intake to better reflect
the water quality in the immediate vicinity starting from 5 January 2019. The
approval from the IEC and EPD on the updated monitoring location had been
sought before the relocation.
(3) The monitoring locations for
SR1, SR4 and SR5 have been updated (to SR1A, SR4A and SR5A) based on the
Baseline Water Quality Monitoring Report.
(4) As the access to SR6 was
obstructed by the construction activities and temporary structures for Tung
Chung New Town Extension, the monitoring location has been relocated to SR6A
starting from 8 August 2019. The approval from the IEC and EPD on the updated
monitoring location had been sought before the relocation.
(5) The monitoring location for SR8
is subject to further changes due to silt curtain arrangements and the
progressive relocation of this seawater intake. The approval from
the IEC and EPD on the updated monitoring location had been sought before the
relocation.
5.1.5.2
For SR8, the monitoring location has
been modified slightly due to the installation of localised silt curtains which
are required for protecting this sensitive receiver. To ensure the water
quality monitoring at this location is able to represent the water quality at
the seawater intake, the monitoring location will be moved closer to the
intakes and within the area protected by the localised silt curtain.
5.1.5.3
For submarine 11 kV cable diversion
works, two specific impact stations (IM13 and IM14) are proposed for the
construction phase. These impact stations will be mobile stations located
within a 500 m envelope of the respective water jetting / field joint
excavation works. The indicative areas are shown in Drawing No. MCL/P132/EMA/5-001. Exact locations will depend on the tidal conditions
(i.e. the impact station should always be downstream of the respective water
jetting / field joint excavation works). In case where relocation of the
impact stations is required, a minimum of 2 mobile impact stations at
representative locations should be proposed by ET and approved by the AAHK / PM
and IEC.
5.1.5.4
The status and locations of water
sensitive receivers may change after issuing this Manual. If such case exists,
the ETL should propose updated monitoring locations and seek approval from the
IEC and EPD. The selection of these locations should follow the below
criteria:
● Impact (IM) stations should be
within the 500 m envelope of construction works;
● Sensitive receivers (SR) stations
should be at close proximity to key sensitive receivers; and
● Control stations (C), as far as
practicable, should be at representative locations of the water body being
monitored while undisturbed by the project.
Impact Monitoring Locations (during deployment of the enhanced silt
curtain)
5.1.5.5
During deployment of the enhanced
silt curtain as specified in the Silt Curtain Deployment Plan, some of the IM
stations surrounding the land formation footprint (IM1 to IM12) will be
relocated to the locations shown in Drawing No.
MCL/P132/EMA/5-002c to maintain an
appropriate buffer distance away from the enhanced silt curtain. The
coordinates are shown in Table 5‑3.
Table 5‑3:
Location of IM1 to IM12 during
Deployment of the Enhanced Silt Curtains
Monitoring Stations
|
Easting
|
Northing
|
IM1
|
807132
|
817949
|
IM2
|
806166
|
818163
|
IM3
|
805594
|
818784
|
IM4
|
804607
|
819725
|
IM5
|
804867
|
820735
|
IM6
|
805828
|
821060
|
IM7
|
806835
|
821349
|
IM8
|
808140
|
821830
|
IM9
|
808811
|
822094
|
IM10
|
809794
|
822385
|
IM11
|
811460
|
822057
|
IM12
|
812046
|
821459
|
5.1.5.6
After the enhanced silt curtain is removed, the location of IM1 to IM12 will
revert to the locations shown in Drawing No.
MCL/P132/EMA/5-002b.
DCM-Specific Monitoring Locations
5.1.5.7
For the initial intensive
DCM-specific water quality monitoring programme, monitoring should be conducted
within 3 months of commencement of actual full scale DCM works and as soon as
there are five DCM rigs working within a work front of 500m x 500m within the
CMPs. Details of the DCM-specific water quality monitoring programme are
specified in the Detailed Plan on DCM. A total of 12 monitoring stations will
be deployed with the following arrangement:
i. Two monitoring stations upstream and
at 150 m envelope of DCM group works area (Control stations);
ii. Five monitoring stations downstream
and at 150 m envelope of DCM group works area (Impact 1 stations);
iii. Five monitoring stations downstream
and at 250 m envelope of DCM group works area (Impact 2 stations);
iv. Monitoring stations should be at
least 50 m apart; and
v. Downstream monitoring stations
should be perpendicular to the tidal direction.
5.1.5.8 Drawing No. MCL/P132/EMA/5-003 shows an indicative arrangement for the DCM work
front.
5.1.5.9 After completion of the initial intensive DCM-specific
water quality monitoring programme, DCM monitoring locations will revert to the
general (control and impact) monitoring locations presented in Table 5‑2.
5.1.6 Baseline Monitoring
5.1.6.1
Baseline conditions for water quality
shall be established and agreed with EPD prior to the commencement of works.
The purpose of the baseline monitoring is to establish ambient conditions prior
to the commencement of the marine works and to demonstrate the suitability of
the proposed impact and control monitoring stations. The baseline conditions
shall be established by measuring DO, DO%, pH, temperature, turbidity,
salinity, and SS at all designated stationary monitoring stations. To provide
the baseline water quality for the DCM-specific monitoring, total alkalinity
shall be measured at all the relevant stationary impact stations, plus
nutrients and heavy metals at the “IM*” stations (which represent the
contaminated mud pit locations). The measurements should be taken three days
per week, at mid-flood and mid-ebb tides, for at least four weeks prior to the
commencement of marine works. Samples should be taken at three depths (at 1m
below surface, at mid-depth, and at 1m above bottom) for locations with water
depth >6m. For locations with water depth between 3m and 6m, two depths
(surface and bottom) should be taken. Locations with water depth <3m, only
surface depth should be taken. The commencement date of baseline monitoring
shall be agreed between the ET / IEC / AAHK / PM to ensure timely submission of
the baseline monitoring report to EPD. Duplicate water samples should be taken
and analysed.
5.1.6.2 As far as possible there should not be any marine
construction activities in the vicinity of the stations during the baseline
monitoring.
5.1.6.3 In exceptional cases when insufficient baseline
monitoring data or questionable results are obtained, the ET should seek
approval from the IEC and EPD on an appropriate set of data to be used as
baseline reference.
5.1.6.4 Baseline monitoring schedule should be faxed to EPD at
least two weeks prior to the commencement of baseline monitoring. The interval
between two sets of monitoring should be not less than 36 hours.
5.1.7 Efficiency of Silt Curtain System
5.1.7.1 Type II and/or Type III silt curtains (as defined by
the United States Army Corporation of Engineers (USACE) classification system
for silt curtains) have been recommended in the EIA Report. These are to be
implemented as a double layer arrangement. Details of the silt curtain
arrangements and the pilot test on the efficiency of the silt curtain system
are specified in the Silt Curtain Deployment Plan. The ET should conduct tests
to confirm that the silt curtain system specified in the Silt Curtain
Deployment Plan satisfies the requirements in the EIA Report.
5.1.7.2
A pilot test should be carried out
during the early stage of construction to confirm whether the silt removal
efficiency of the double layer floating type silt curtains can achieve 61 %
silt removal efficiency for sand blanket laying and marine filling activities.
The pilot test should be undertaken during the highest current speed condition
(covering both flood and ebb tide) and include measurements of current speed
and direction, turbidity and suspended solids. The water quality monitoring
points to be selected should be close to the locations of the marine works.
Monitoring should be conducted on both sides of the silt curtains deployed. If
the pilot test is conducted in dry season, a verification test should be
carried out during wet season at the highest current speed condition to
re-confirm the findings. The details for the pilot test should be proposed by
the ET and agreed with the IEC and EPD, taking into account of the Contractor’s
proposed actual locations of the works.
5.1.7.3
Regardless of the measured efficiency
of the silt curtain system, the Event and Action Plan should only be based on
the monitoring results at the designated stationary monitoring stations.
5.1.8 General Impact Monitoring
5.1.8.1 During marine construction works, impact monitoring
should be undertaken at all designated monitoring stations three days per week
(refer to Table 5‑2 for the activities to be
monitored). Monitoring should be undertaken at mid-flood (within ± 1.75 hour of
the predicted time) and mid-ebb (within ± 1.75 hour of the predicted time)
tides. Samples should be taken at three depths (at 1m below surface, at
mid-depth, and at 1m above bottom) for locations with water depth >6m. For
locations with water depth between 3m and 6m, two depths (surface and bottom)
should be taken. Locations with water depth <3 m, only surface depth should
be taken. The interval between two sets of monitoring should be not less than
36 hours except when the Action Level and/or Limit Level is/are exceeded, in
which case the monitoring frequency may be increased. For DCM impact
monitoring, please refer to Section 5.1.9.
5.1.8.2 Two consecutive measurements of DO concentrations
(mg/L), DO saturation (%) and turbidity (NTU) should be taken in-situ according
to the stated sampling method. Where the difference in value between the first
and second measurement of DO or turbidity parameters is more than 25 % of
the value of the first reading, the reading should be discarded and further
readings would be taken. Water samples for SS (mg/L) measurements should be
collected at the same depths. Duplicate water samples should be taken and
analysed.
5.1.8.3
In addition to the above in-situ
measurements, water temperature and pH should be determined at all designated
monitoring stations at the same depths, as specified above. The monitoring
location / position, time, weather conditions and any special phenomena should
also be recorded.
5.1.9 DCM Impact Monitoring
Initial Intensive DCM Monitoring
5.1.9.1
According to the current design, DCM would
be conducted within the CMPs during land formation. As specified in the
Detailed Plan for DCM, within 3 months of the commencement of full-scale DCM
works and as soon as there are five DCM rigs working within a work front of 500
m x 500 m within the CMPs, the ET is required to conduct an initial intensive
DCM-specific water quality monitoring programme for a period of at least four
weeks to ensure that the criteria for various contaminants are complied. This
would be conducted for a group of five DCM rigs as specified in Section
5.1.5.7.
5.1.9.2
Daily monitoring at mid-flood (within
± 1.75 hour of the predicted time) and mid-ebb (within ± 1.75 hour of the
predicted time) tides is required during the initial intensive DCM monitoring
as shown in Chart 5-1. Samples should be taken at three depths (at 1m below
surface, at mid-depth, and at 1 m above bottom) for locations with water depth
>6m. For locations with water depth between 3 m and 6 m, two depths (surface
and bottom) should be taken. Locations with water depth <3m, only surface
depth should be taken.
5.1.9.3
Two consecutive measurements of DO,
DO%, pH, temperature (oC), turbidity (NTU), and salinity (ppt)
should be taken in-situ according to the stated sampling method. Water samples
for total alkalinity (ppm), SS (mg/L), nutrients (mg/L) and heavy metals (µg/L)
measurements should be collected at the same depths. Monitoring parameters for
nutrients and heavy metals include those listed in Table 5‑1.
Duplicate water samples should be taken and analysed. If no exceedance
(referring to those that are attributable to DCM works as determined by the
findings of exceedance investigation reports) is recorded within two weeks,
then the monitoring frequency can be reduced to every two days. If no
exceedance is recorded after another two weeks, the initial intensive DCM
specific monitoring will be terminated and DCM monitoring will continue as part
of the regular DCM monitoring.
Chart 5‑1:
Flow Chart for DCM Monitoring
|
|
* During regular DCM monitoring, exceedances for total
alkalinity and the two representative heavy metals should be confirmed by ET
and verified by the IEC as project-related.
|
Regular DCM Monitoring
5.1.9.4
After completion of the initial
intensive DCM monitoring, regular DCM monitoring will be conducted as part of
the general impact monitoring presented in Section 5.1.8 for the
remaining duration of the DCM works. During this period, total alkalinity and
two representative heavy metals will be monitored at all stationary control and
impact monitoring stations as specified in Table 5‑2.
The two representative heavy metals shall be proposed by the ET taking into
account the findings of the initial intensive DCM monitoring. The selection
criteria for determining the representative heavy metals should include but not
limited to the following:
● Low natural (baseline)
concentrations in the marine environment
● Present in elevated concentrations
in the CMPs (based on past vibrocores taken from the CMPs)
● Concentrations in the CMPs should be
higher than in non- contaminated mud pit areas; and
● Not associated with strong temporal
variations and/or external influences (e.g. Pearl River Delta discharges,
construction activities by concurrent projects)
5.1.9.5
Two consecutive measurements of total
alkalinity (ppm) should be taken according to the stated sampling and analysis
method, and laboratory water samples for heavy metals (µg/L) measurements
should be collected at the same depths. Duplicate water samples should be taken
and analysed.
5.1.9.6
During this regular DCM monitoring
period, if there is any exceedance of the Limit Levels for total alkalinity and
the two representative heavy metals for two consecutive sampling days and such
exceedance is confirmed by the ET (with verification by the IEC) to be a result
of the DCM works, intensive DCM monitoring will be re-initiated as shown in Chart 5-1. Monitoring parameters during the intensive DCM monitoring will be the
same as those conducted for the initial intensive DCM monitoring until such
time as no further exceedances are detected and regular DCM monitoring resumes.
5.1.10 Post-Construction Monitoring
5.1.10.1
Upon completion of all marine
construction works, a post project water quality monitoring exercise should be
carried out for four weeks, in the same manner as the impact monitoring during
construction phase.
5.1.11 Event and Action Plan for Water
Quality
5.1.11.1
The Action Level and Limit Level for water quality (excluding sensitive
receiver stations representing seawater intakes) are defined in Table 5‑4.
Table 5‑4:
Action and Limit Levels for Water Quality
Parameters
|
Action Level
|
Limit Level
|
DO in mg/L
(Surface, Middle & Bottom)
|
Surface and Middle
5 percentile of baseline data for surface and middle
layer
|
Surface and Middle
5 mg/L or 1 percentile of baseline data for surface
and middle layer for Fish Culture Zone (SR7)
4 mg/L or 1 percentile of baseline data for surface
and middle layer for other stations
|
Bottom
5 percentile of baseline data for bottom layer
|
Bottom
2 mg/L or 1 percentile of baseline data for bottom
layer
|
Temperature in °C
(for intensive DCM monitoring only)
|
1.8°C above the temperature recorded at representative
control stations at the same tide of the same day
|
2°C above the temperature recorded at representative
control stations at the same tide of the same day
|
SS in mg/L
|
95 percentile of baseline data or 120% of upstream
control station at the same tide of the same day, whichever is higher
|
99 percentile of baseline data or 130% of upstream
control station at the same tide of the same day, whichever is higher
|
Turbidity in NTU
|
Total Alkalinity in ppm
|
Nutrient
|
Ammonia (NH3)
|
Unionised ammonia (NH3)
(with 0.021 mg/L as the upper limit)
|
Nitrite (NO2)
|
Nitrate (NO3)
|
TKN
|
Total Phosphorus
|
Reactive Phosphorus
|
Heavy Metals
|
Cadmium (Cd)
|
Chromium (Cr)
|
Copper (Cu)
|
Nickel (Ni)
|
Lead (Pb)
|
Zinc (Zn)
|
Arsenic (As)
|
Silver (Ag)
|
Mercury (Hg)
|
Notes:
1. For DO measurement, non-compliance
occurs when monitoring result is lower than the limits.
2. For parameters other
than DO, non-compliance of water quality results when monitoring results is
higher than the limits.
3. Depth-averaged results
are used unless specified otherwise.
4. All the figures given in
the table are used for reference only and the EPD may amend the figures
whenever necessary.
5. For all mobile impact
stations, the baseline data will be represented by the nearest stationary
monitoring station.
5.1.11.2
The Action Level and Limit Level for
water quality impact monitoring have been established and presented in the
Baseline Water Quality Monitoring Report. The summary tables of the Action
Level and Limit Level for water quality are presented in Table
5‑5 and Table 5‑6.
Table 5‑5:
Action and Limit Levels for General Impact Water Quality Monitoring and Regular DCM
Monitoring
Parameters
|
Action Level
|
Limit Level
|
DO in mg/L
(Surface, Middle & Bottom)
|
Surface and Middle
4.5 mg/L
|
Surface and Middle
4.1 mg/L
5 mg/L for Fish Culture Zone (SR7) only
|
Bottom
3.4 mg/L
|
Bottom
2.7 mg/L
|
Suspended Solids (SS) in mg/L
|
23
|
or 120% of upstream control station at the same tide
of the same day, whichever is higher
|
37
|
or 130% of upstream control station at the same tide
of the same day, whichever is higher
|
Turbidity in NTU
|
22.6
|
36.1
|
Total Alkalinity in ppm
|
95
|
99
|
Representative Heavy Metals for regular DCM monitoring
(chromium and nickel)
|
Same as that for the intensive DCM monitoring
|
Same as that for the intensive DCM monitoring
|
Note:
1. For DO measurement, non-compliance
occurs when monitoring result is lower than the limits.
2. For parameters other
than DO, non-compliance of water quality results when monitoring results is
higher than the limits.
3. Depth-averaged results are
used unless specified otherwise.
4. The Action and Limit
Levels specified in this table does not apply to SR1A and SR8 (see Section
5.11.1.3).
Table 5‑6:
Action and Limit Levels for Intensive DCM Monitoring
Parameters
|
Action Level
|
Limit Level
|
DCM-Specific
Parameters
|
|
|
Temperature in °C
|
1.8°C above the temperature recorded at upstream
control stations at the same tide of the same day
|
2°C above the temperature recorded at upstream control
stations at the same tide of the same day
|
Total Alkalinity in ppm
|
95
|
or 120% of upstream control station at the same tide
of the same day, whichever is higher
|
99
|
or 130% of upstream control station at the same tide
of the same day, whichever is higher
|
Nutrient (mg/l)
|
|
|
Ammonia (NH3)
|
0.18
|
0.20
|
Unionised ammonia (NH3)
(with 0.021 mg/L as the upper limit)
|
0.01
|
0.01
|
Nitrite (NO2)
|
0.12
|
0.13
|
Nitrate (NO3)
|
1.05
|
1.18
|
TKN
|
0.6
|
0.7
|
Total Phosphorus
|
0.06
|
0.07
|
Reactive Phosphorus
|
0.04
|
0.04
|
Heavy Metals (µg/l)
|
|
|
Cadmium (Cd)
|
0.1
|
0.1
|
Chromium (Cr)
|
0.2
|
0.2
|
Copper (Cu)
|
1.9
|
5.1
|
Nickel (Ni)
|
3.2
|
3.6
|
Lead (Pb)
|
0.2
|
0.2
|
Zinc (Zn)
|
6
|
8
|
Arsenic (As)
|
3
|
4
|
Silver (Ag)
|
0.1
|
0.1
|
Mercury (Hg)
|
0.05
|
0.05
|
Other Water Quality
Parameters
|
DO in mg/L
(Surface and Middle)
|
80% of upstream control station* at
the same tide of the same day or 4
mg/l, whichever is lower
|
70% of upstream control station* at
the same tide of the same day or 4
mg/l, whichever is lower
|
DO in mg/L
(Bottom)
|
80% of upstream control station* at
the same tide of the same day or 2
mg/l, whichever is lower
|
70% of upstream control station* at
the same tide of the same day or 2
mg/l, whichever is lower
|
Suspended Solids (SS) in mg/L
|
120% of upstream control station* at
the same tide of the same day
|
130% of upstream control station* at
the same tide of the same day
|
Turbidity in NTU
|
Note:
1. Non-compliance of water
quality results when monitoring results is higher than the limits, except for
DO measurement whereby non-compliance results when monitoring results is lower
than the limits.
2. Depth-averaged results
are used unless specified otherwise.
3. For Cd, Cr, Pb, Ag and
Hg, the percentile values are below detection limit, hence the Action and Limit
Levels represent detection limit.
4. Where the water quality
results at control stations for individual parameters are below detection
limit, the value of the detection limit will be adopted.
5. (*) Upstream control station refers
to average of the two control station results, unless the difference between
the two control station results is >25%, in which case the higher (for SS
and turbidity) and lower (for DO) of the two shall apply.
5.1.11.3
For sensitive receiver stations
representing seawater intakes for cooling (e.g. SR1A and SR8), only the Action
and Limit Levels for SS parameter would be applicable (as the operation of
these intakes would not be significantly affected by the other water quality
parameters). At these cooling water intakes, the Action and Limit Levels for SS
are dependent on the operational tolerance of individual intakes. The ET will
propose suitable Action and Limit Levels for SS at individual sensitive
receiver stations representing seawater intakes. This shall be agreed with the
IEC and the respective operators of the intakes prior to commencement of construction
activities or commencement of operation of the seawater intake (whichever is
later) and documented in the Baseline Monitoring Report and EM&A reports.
5.1.11.4
As agreed with the IEC and the respective
operators, the Action and Limit Levels for SR1A and SR8 are shown in Table 5‑7.
Table 5‑7:
Action Level and Limit Level for SR1A and SR8
SS (mg/l)
|
Action
Level
|
Limit Level
|
SR1A
|
33
|
42
|
SR8
|
52
|
60
|
5.1.11.5
The actions in accordance with the
Event and Action Plan in Table 5‑8 and Table 5‑9 should be carried out if the water quality
assessment criteria are exceeded at any designated monitoring points.
Table 5‑8:
Event and Action Plan for General Impact Water Quality Monitoring
Event
|
ET
|
IEC
|
Action
AAHK / PM
|
Contractor
|
Action Level being exceeded by one sampling day
|
1. Repeat in-situ measurement to confirm findings;
2. Identify reasons for non-compliance and sources of
impact;
3. Inform IEC and Contractor;
4. Check monitoring data, all plant, equipment and
Contractor’s working methods;
5. Discuss mitigation measures with IEC and
Contractor;
6. Repeat in-situ monitoring on the day after the
exceedance.
|
1. Discuss with ET and Contractor on the mitigation
measures;
2. Review proposals on mitigation measures submitted
by Contractor and advise AAHK / PM accordingly;
3. Assess the effectiveness of the implemented
mitigation measures.
|
1. Discuss with IEC on the proposed mitigation
measures;
2. Make agreement on the mitigation measures to be
implemented;
3. Assess the effectiveness of the implemented
mitigation measures.
|
1. Inform AAHK / PM and confirm receipt of ET’s
notification of the non-compliance in writing;
2. Rectify unacceptable practice;
3. Check all plant and equipment;
4. Provide report of the status and condition of plant,
equipment and mitigation measures to ET
5. Consider changes of working methods;
6. Discuss with ET and IEC and propose mitigation
measures.
|
Action Level being exceeded
by more than two consecutive sampling days
|
1. Repeat in-situ measurement to confirm findings;
2. Identify reasons for non-compliance and sources of
impact;
3. Inform IEC and Contractor;
4. Check monitoring data, all plant, equipment and
Contractor’s working methods;
5. Discuss mitigation measures with IEC and
Contractor;
6. Ensure mitigation measures are implemented;
7. Repeat in-situ monitoring on the day after the
exceedance and prepare to increase the monitoring frequency to daily.
|
1. Discuss with ET and Contractor on the mitigation
measures;
2. Review proposals on mitigation measures submitted
by Contractor and advise AAHK / PM accordingly;
3. Assess the effectiveness of the implemented
mitigation measures.
|
1. Discuss with IEC on the proposed mitigation
measures;
2. Make agreement on the mitigation measures to be
implemented;
3. Assess the effectiveness of the implemented
mitigation measures.
|
1. Inform AAHK / PM and confirm receipt of ET’s
notification of the non-compliance in writing;
2. Rectify unacceptable practice;
3. Check all plant and equipment;
4. Provide report of the status and condition of
plant, equipment and mitigation measures to ET
5. Consider changes of working methods;
6. Discuss with ET and IEC and propose mitigation
measures to AAHK / PM and IEC within three working days;
7. Implement the agreed mitigation measures.
|
Limit Level being exceeded by one sampling day
|
1. Repeat in-situ measurement to confirm findings;
2. Identify reasons for non-compliance and sources of
impact;
3. Inform IEC, Contractor and EPD;
4. Check monitoring data, all plant, equipment and
Contractor’s working methods;
5. Discuss mitigation measures with AAHK / PM, IEC and
Contractor;
6. Ensure mitigation measures are implemented;
7. Repeat in-situ monitoring on the day after the
exceedance and prepare to increase the monitoring frequency to daily
|
1. Discuss with ET and Contractor on the mitigation
measures;
2. Review proposals on mitigation measures submitted
by Contractor and advise AAHK / PM accordingly;
3. Assess the effectiveness of the implemented
mitigation measures.
|
1. Discuss with ET, IEC and Contractor on the proposed
mitigation measures;
2. Request Contractor to critically review the working
methods;
3. Make agreement on the mitigation measures to be
implemented;
4. Assess the effectiveness of the implemented
mitigation measures.
|
1. Inform AAHK / PM and confirm receipt of ET’s
notification of the non-compliance in writing;
2. Rectify unacceptable practice;
3. Check all plant and equipment;
4. Provide report of the status and condition of
plant, equipment and mitigation measures to ET
5. Consider changes of working methods;
6. Discuss with AAHK / PM, ET and IEC and propose
mitigation measures to AAHK / PM and IEC within three working days;
7. Implement the agreed mitigation measures.
|
Limit Level being
exceeded by more than one consecutive sampling days
|
1. Repeat in-situ
measurement to confirm findings;
2. Identify reasons
for non-compliance and sources of impact;
3. Inform IEC,
Contractor and EPD;
4. Check monitoring
data, all plant, equipment and Contractor’s working methods;
5. Discuss mitigation
measures with AAHK / PM, IEC and Contractor;
6. Ensure mitigation
measures are implemented;
7. Increase the
in-situ monitoring frequency to daily until no exceedance of Limit Level for
two consecutive days.
|
1. Discuss with ET
and Contractor on the mitigation measures;
2. Review proposals
on mitigation measures submitted by Contractor and advise AAHK / PM
accordingly;
3. Assess the
effectiveness of the implemented mitigation measures.
|
1. Discuss with IEC,
ET and Contractor on the proposed mitigation measures;
2. Request contractor
to critically review the working methods;
3. Make agreement on
the mitigation measures to be implemented;
4. Assess the
effectiveness of the implemented mitigation measures;
5. Consider and
instruct, if necessary, the Contractor to slow down or to stop all or part of
the construction activities until no exceedance of Limit Level.
|
1. Inform AAHK / PM
and confirm receipt of ET’s notification of the non-compliance in writing;
2. Rectify
unacceptable practice;
3. Check all plant
and equipment;
4. Provide daily
report of the status and condition of plant, equipment and mitigation
measures to ET until no further exceedance;
5. Consider changes
of working methods;
6. Discuss with AAHK
/ PM, ET and IEC and propose mitigation measures to AAHK / PM and IEC within
three working days;
7. Implement the
agreed mitigation measures;
8. As directed by
AAHK / PM, to slow down or to stop all or part of the construction
activities.
|
Note: Where the Action Level is
the same as the Limit Level, the actions specified for Limit Level exceedances
shall apply.
Table 5‑9:
Event and Action Plan for DCM Process
Event
|
ET
|
IEC
|
Action
AAHK / PM
|
Contractor
|
Action Level being exceeded by one sampling day
|
1. Repeat in-situ measurement
to confirm findings;
2. Identify reasons for
non-compliance and sources of impact;
3. Inform IEC and Contractor;
4. Check monitoring data, all
plant, equipment and Contractor’s working methods;
5. Discuss mitigation
measures with IEC and Contractor;
6. During intensive DCM monitoring and if not already
undertaking daily monitoring, increase monitoring frequency in accordance
with Chart 5.1 (applies to DCM-specific parameters only). During
regular DCM monitoring, repeat monitoring on the day after the exceedance.
|
1. Discuss with ET and
Contractor on the mitigation measures;
2. Review proposals on
mitigation measures submitted by Contractor and advise AAHK / PM accordingly;
3. Assess the effectiveness of the implemented
mitigation measures.
|
1. Discuss with IEC on the
proposed mitigation measures;
2. Make agreement on the
mitigation measures to be implemented;
3. Assess the effectiveness of the implemented
mitigation measures.
|
1. Inform AAHK / PM and
confirm receipt of ET’s notification of the non-compliance in writing;
2. Rectify unacceptable
practice;
3. Check all plant and
equipment;
4. Provide report of the
status and condition of plant, equipment and mitigation measures to ET;
5. Consider changes of
working methods;
6. Discuss with ET and IEC and propose mitigation
measures.
|
Action Level being exceeded by more than two
consecutive sampling days
|
1. Repeat in-situ measurement
to confirm findings;
2. Identify reasons for
non-compliance and sources of impact;
3. Inform IEC and Contractor;
4. Check monitoring data, all
plant, equipment and Contractor’s working methods;
5. Discuss mitigation
measures with IEC and Contractor;
6. Ensure mitigation measures
are implemented;
7. During intensive DCM monitoring and if not already
undertaking daily monitoring, increase monitoring frequency in accordance
with Chart 5.1 (applies to DCM-specific parameters only). During
regular DCM monitoring, repeat monitoring on the day after the exceedance and
prepare to increase the monitoring frequency to daily.
|
1. Discuss with ET and
Contractor on the mitigation measures;
2. Review proposals on mitigation
measures submitted by Contractor and advise AAHK / PM accordingly;
3. Assess the effectiveness of the implemented
mitigation measures.
|
1. Discuss with IEC on the
proposed mitigation measures;
2. Make agreement on the
mitigation measures to be implemented;
3. Assess the effectiveness of the implemented
mitigation measures.
|
1. Inform AAHK / PM and
confirm receipt of ET’s notification of the non-compliance in writing;
2. Rectify unacceptable
practice;
3. Check all plant and
equipment;
4. Provide report of the
status and condition of plant, equipment and mitigation measures to ET;
5. Consider changes of
working methods;
6. Discuss with ET and IEC
and propose mitigation measures to AAHK / PM and IEC within 3 working days;
7. Implement the agreed mitigation
measures.
8. As directed by AAHK / PM, to slow down all or part
of the construction activities.
|
Limit Level being exceeded by one sampling day
|
1. Repeat in-situ measurement
to confirm findings;
2. Identify reasons for
non-compliance and sources of impact;
3. Inform IEC, Contractor and
EPD;
4. Check monitoring data, all
plant, equipment and Contractor’s working methods;
5. Discuss mitigation
measures with IEC, AAHK / PM and Contractor;
6. Ensure mitigation measures
are implemented;
7. During intensive DCM monitoring and if not already
undertaking daily monitoring, increase monitoring frequency in accordance
with Chart 5.1 (applies to DCM-specific parameters only). During
regular DCM monitoring, repeat monitoring on the day after the exceedance.
|
1. Discuss with ET and
Contractor on the mitigation measures;
2. Review proposals on
mitigation measures submitted by Contractor and advise AAHK / PM accordingly;
3. Assess the effectiveness of the implemented
mitigation measures.
|
1. Discuss with IEC, ET and
Contractor on the proposed mitigation measures;
2. Request Contractor to
critically review the working methods;
3. Make agreement on the
mitigation measures to be implemented;
4. Assess the effectiveness of the implemented mitigation
measures.
|
1. Inform AAHK / PM and
confirm receipt of ET’s notification of the non-compliance in writing;
2. Rectify unacceptable
practice;
3. Check all plant and
equipment;
4. Provide report of the
status and condition of plant, equipment and mitigation measures to ET;
5. Consider changes of
working methods;
6. Discuss with AAHK / PM, ET
and IEC and propose mitigation measures to AAHK / PM and IEC within three
working days;
7. Implement the agreed mitigation measures.
|
Limit Level being
exceeded by more than one consecutive sampling days
|
1. Repeat in-situ measurement
to confirm findings;
2. Identify reasons for
non-compliance and sources of impact;
3. Inform IEC, Contractor and
EPD;
4. Check monitoring data, all
plant, equipment and Contractor’s working methods;
5. Discuss mitigation
measures with IEC, AAHK / PM and Contractor;
6. Ensure mitigation measures
are implemented;
7. During intensive DCM monitoring and if not already
undertaking daily monitoring, increase monitoring frequency in accordance with
Chart 5.1 (applies to DCM-specific parameters only). During regular
DCM monitoring, re-initiate the intensive DCM monitoring in accordance with Chart
5.1.
|
1. Discuss with ET and
Contractor on the mitigation measures;
2. Review proposals on
mitigation measures submitted by Contractor and advise AAHK / PM accordingly;
3. Assess the effectiveness of the implemented
mitigation measures.
|
1. Discuss with IEC, ET and
Contractor on the proposed mitigation measures;
2. Request contractor to
critically review the working methods;
3. Make agreement on the
mitigation measures to be implemented;
4. Assess the effectiveness
of the implemented mitigation measures;
5. Consider and instruct, if necessary, the Contractor
to slow down or to stop all or part of the construction activities until no
exceedance of Limit Level.
|
1. Inform AAHK / PM and
confirm receipt of ET’s notification of the non-compliance in writing;
2. Rectify unacceptable
practice;
3. Check all plant and equipment;
4. Provide report of the
status and condition of plant, equipment and mitigation measures to ET;
5. Consider changes of
working methods;
6. Discuss with AAHK / PM, ET
and IEC and propose mitigation measures to AAHK / PM and IEC within three
working days;
7. Implement the agreed
mitigation measures;
8. As directed by AAHK / PM, to stop all or part of
the construction activities.
|
5.1.12
Mitigation
Measures
5.1.12.1 The implementation schedule of the
recommended water quality mitigation measures is presented in Appendix C.
5.2 Operation Water Quality Monitoring
5.2.1 Introduction
5.2.1.1 As it has been assessed that there would not be any
significant changes in the water quality during operation of the project, no
marine water quality monitoring is considered necessary during the operation
phase.
5.2.1.2 Water quality monitoring for the spent cooling water
discharges will be undertaken in accordance with the future Water Pollution
Control Ordinance (WPCO) license conditions.
5.2.1.3 Water quality monitoring is proposed for the greywater
treatment facility during commissioning of the facility to ensure the treated
effluent quality complies with the reuse standards as defined in the EIA
Report, which are reproduced in Table 5‑10.
Table 5‑10:
Treated Effluent Quality Criteria for Greywater Treatment Facility
Parameters
|
Criteria Level
|
SS
|
≤ 5 mg/L
|
BOD5
|
≤ 10 mg/L
|
COD
|
≤ 50 mg/L
|
Oil and Grease
|
≤ 10 mg/L
|
Surfactants (total)
|
≤ 5 mg/L
|
E. coli
|
< 1 count / 100ml
|
pH
|
6.0 – 9.0
|
Turbidity
|
< 2 NTU
|
Faecal Coliforms
|
Non detectable / 100ml
|
5.2.2 Commissioning Test for Greywater
Treatment Facility
5.2.2.1
During commissioning of the greywater
treatment facility, monitoring of pH, turbidity, SS, 5-day Biological Oxygen
Demand (BOD5), Chemical Oxygen Demand (COD), oil and grease, E.coli,
faecal coliforms and surfactants for the treated effluent should be undertaken
to ensure the treatment facility will be able to treat the greywater to levels
in compliance with the reuse standards as listed in Table 5‑10.
Details of the proposed monitoring for treated effluent including the
monitoring location, monitoring frequency, effluent sampling and testing
methods should be proposed by the ET, which will then be checked by the IEC for
agreement with the AAHK / PM and EPD at least two weeks before commencement of
the commissioning.
5.2.2.2
During operation of the greywater
treatment facility, regular water quality monitoring for the treated effluent
discharges will be undertaken, which shall monitor compliance of the treated
effluent against both the reuse standard specified in Table
5‑10, and the discharge standard (for discharge to foul sewer) as
per the future WPCO license conditions for discharge to foul sewer. Reuse of
the treated effluent shall be suspended if the monitoring results do not comply
with the reuse standards. The treated greywater will be discharged to the
sewerage system until the greywater treatment system resumes compliance.
6
Sewerage and Sewage Treatment Implications
6.1
Construction
Phase Monitoring
6.1.1.1
After implementation of the recommended mitigation measure for sewage
from construction workforce as detailed in Appendix
C, no sewerage impacts are expected
from the site during construction stage. No specific sewage monitoring during
construction phase is thus required.
6.2
Operation
Phase Monitoring
6.2.1.1 The gravity sewer from the airport discharge manhole
to Tung Chung Sewage Pumping Station (TCSPS) will be upgraded by AAHK to cater
for the ultimate design sewage flow from the expanded airport. AAHK will
start planning construction of the gravity sewer upgrading in 2022 or when the sewage flow in the affected gravity sewer
exceeds 80% of the design capacity of the sewer, whichever is earlier, so as to
ensure timely completion of the mitigation works before the flow would exceed
the design capacity of the sewer. For this, it
is recommended that AAHK should conduct
annual monitoring for the sewage flow build-up of the gravity sewer from the
airport discharge manhole to TCSPS from 2020 onwards, i.e., one year before the
scheduled commencement of operation of the proposed third runway.
6.2.1.2 Moreover, in order to ensure the additional sewage
generated from the 3RS project would not impose adverse impacts in respect of
sewage septicity and odour issues on the existing sewerage networks including
the public sewerage system, it is recommended to start routine monitoring of
hydrogen sulphide (H2S) levels for the sewerage system of 3RS upon
commencement of operation of the project,
6.2.1.3
The ET should propose suitable method
for carrying out the annual sewage flow monitoring for the concerned gravity
sewer as well as details of the routine H2S monitoring system for
the sewerage system of 3RS, which shall be checked by IEC and agreed by the
AAHK / PM and EPD at least one year before commencement
6.2.1.4
of operation of 3RS.
7
Waste Management Implications
7.1
Construction
Phase Monitoring
7.1.1
Monitoring
Requirements
7.1.1.1 Waste Management
Plan (WMP) for the construction of the project was submitted to EPD no later
than 3 months before the commencement of construction in accordance to EP
Condition 2.19. The Contractors are responsible for waste management activities
during construction phase. The Contractors must ensure that all wastes produced
during the construction phase are handled, stored and disposed of in accordance
with EPD’s regulations and requirements and in line with good waste management
practices. Contract-specific WMPs should be prepared and implemented by
individual Contractors in accordance with Environment, Transport and Works Bureau
(ETWB TC(W)) No. 19/2005 Environmental Management on Construction Site and the
Construction WMP. The
contract-specific WMPs shall be updated from time to time and shall be reviewed
and advised by the ET. All submissions shall be submitted to AAHK / PM for
agreement and verified by the IEC.
7.1.1.2
The Contractors should also refer to
the Construction and Demolition Material Management Plan (C&DMMP) which
will be submitted to Public Fill Committee (PFC) before commencement of
construction of the project to facilitate them in the preparation of the
contract-specific WMP. The C&DMMP should provide ways to minimise the
generation and maximise the reuse of the construction and demolition (C&D) material
at the construction phase of the project. The C&DMMP should also describe
the arrangement for collection and disposal of C&D materials to be
generated from the construction phase.
7.1.1.3
During construction phase, the Contractors should perform regular site
inspection (at least once per week) to determine if wastes are being managed in
accordance with approved procedures and the contract-specific WMP. Waste materials generated during the construction
works, such as inert C&D material, general refuse and chemical wastes, are
recommended to be monitored on a weekly basis to ensure that proper storage,
transportation and disposal practices are being implemented. This monitoring of
waste management practices will ensure that these solid and liquid wastes are
not disposed into the nearby harbour waters. The Contractors would be
responsible for the implementation of any mitigation measures to minimise waste
or redress problems arising from the waste materials.
7.1.2
Audit Requirements
7.1.2.1 It is recommended
that the waste generated during construction phase should be audited
periodically (at least once per week) by the ET to determine if wastes are
being managed in accordance with approved procedures and the contract-specific
WMPs. The audits should look at all aspects of waste management including waste
generation, storage, transportation and disposal. An appropriate audit
programme would be to undertake a first audit near the commencement of the
construction works, and then to audit periodically thereafter. In addition,
routine site inspections by the Contractors should check the implementation of
the recommended good site practices and other waste management mitigation
measures. The results of the waste management
audits should be reported in the EM&A reports.
7.1.2.2 In case of any complaint is received, the ET shall
check compliance with the procedures for carrying out complaint investigation
and propose the necessary improvement actions. In case non-compliance of the
WMP, contract-specific WMPs, any statutory and
contractual requirements, the Event and Action Plan as shown in Chart 7-1 shall be triggered.
7.1.2.3 The Action and Limit Levels for construction waste are
defined in Table 7-1. Should non-compliance occur,
actions in accordance with the Event and Action Plan in Chart 7-1, should be carried out.
Table 7-1:
Action and Limit Level of Construction Waste
Monitoring Location
|
Action Level
|
Limit Level
|
Construction Area
|
When one valid documented complaint is received.
|
Non-compliance of the WMP, contract-specific WMPs, any
statutory and contractual requirements
|
Chart 7-1:
Event and Action Plan for Non-compliance of the WMP, Contract-specific WMPs,
Any Statutory and Contractual Requirements
Action
Level
|
Limit
Level
|
|
|
|
|
7.1.2.4 The ET shall check the disposal records for C&D
materials and audit the trip-ticket system (TTS) for off-site delivery of
surplus inert C&D materials to the designated disposal grounds. The ET
shall also check that all wastes are appropriately recorded and disposed in
accordance with the contract-specific WMPs.
7.1.2.5
A summary of all key types of waste
arising and the reuse and disposal methods proposed during the construction
phase is presented in Table 7‑2.
Table 7‑2:
Summary of Waste Arising during Construction Phase
Waste Type
|
Key Sources of Waste Generation
|
Timing of Waste Generation (1)
|
Estimated Total Quantity of Waste Generation (1)
|
Waste Reuse or Disposal
|
Handling Methods
|
Inert C&D Material
|
Excavation for APM & BHS tunnels, new APM depot
and airside tunnels; piling works for TRC & other buildings;
superstructure construction works; surplus surcharge material; modification
of existing northern seawall; excavation and demolition as well as superstructure
construction works for T2 expansion; excavation for improvement of road
networks; and Horizontal Directional Drilling (HDD) for diversion of existing
submarine pipelines
|
Q1 of 2016 to Q3 of 2024
|
9,543,500 m3
(in-situ volume)
|
About 3,639,230 m3 of the inert C&D
materials generated would be reused on-site as fill materials for the
proposed land formation works. The remaining 5,904,270 m3
would be delivered off-site to any identified projects that need fill
materials and/or to the government’s PFRF for beneficial use by other
projects in Hong Kong.
|
Segregation of inert C&D material to avoid
contamination from other waste arising
Stockpile areas should be covered and applied with
regular water spraying
|
Non-inert C&D Material
|
Site clearance of the golf course area; demolition
works for T2 expansion; and superstructure construction works for various
buildings / facilities
|
Q3 of 2017 to Q3 of 2024
|
96,200 m3
(in-situ volume)
|
The non-inert C&D material will be disposed of at
landfills after on-site sorting and segregation of recyclable materials
|
Separation of non-inert C&D materials from inert
C&D materials
Stored in compatible containers in designated area
on-site
|
Excavated Marine Sediments
|
Excavation at the cable field joint area
|
Q3 of 2017
|
About 10,200 m3
(in-situ volume)
|
Type 1 open sea disposal for Category L sediment or
Type 1 open sea disposal at dedicated sites for Category Mp sediment,
according to PNAP ADV-21 (subject to endorsement by MFC of CEDD and EPD as
well as obtaining dumping permit from EPD under DASO)
|
Stockpile with tarpaulin covers with earth bunds and
sand bags barriers, if applicable.
|
Piling works of the TRC, APM & BHS tunnels,
airside tunnels and other facilities on the proposed land formation area
|
Q4 of 2017 to Q2 of 2023
|
About 705,350 m3
(in-situ volume)
|
Treatment by cement mixing and stabilisation and
on-site reuse of treated sediments as backfilling materials in accordance
with the Proposal of Further Development on Treatment Level / Details and
Reuse Mode for Marine Sediment.(2)
|
Piling works of marine sections of the approach lights
for the third runway
|
2018 to 2019 (subject to detailed design)
|
Western approach lights: about 530 m3 of
marine sediments (in-situ volume)
Eastern approach lights: about 1,060 m3 of
DCM-treated sediment (in-situ volume)
|
Treatment by cement mixing and stabilisation and
on-site reuse of treated sediments as backfilling materials in accordance
with the Proposal of Further Development on Treatment Level / Details and
Reuse Mode for Marine Sediment.(2)
|
Piling works of new HKIAAA beacons
|
2018 to 2019 (subject to detailed design)
|
About 220 m3
(in-situ volume)
|
Treatment by cement mixing and stabilisation and on-site
reuse of treated sediments as backfilling materials in accordance with the
Proposal of Further Development on Treatment Level / Details and Reuse Mode
for Marine Sediment. (2)
|
Basement works of T2 expansion
|
Q3 of 2017 to Q4 of 2019
|
About 50,730 m3
(in-situ volume)
|
Treatment by cement mixing and stabilisation and
on-site reuse of treated sediments as backfilling materials in accordance
with the Proposal of Further Development on Treatment Level / Details and
Reuse Mode for Marine Sediment. (2)
|
Excavation works of APM depot
|
Q1 of 2018 to Q3 of 2020
|
About 9,770 m3
(in-situ volume)
|
Treatment by cement mixing and stabilisation and
on-site reuse of treated sediments as backfilling materials in accordance
with the Proposal of Further Development on Treatment Level / Details and
Reuse Mode for Marine Sediment. (2)
|
Chemical Waste
|
Used cleansing fluids, solvents, lubricating oil, waste
fuel, etc., from maintenance and servicing of construction plant and
equipment
|
2016 to Early 2024
|
Anticipated as small quantity
To be quantified in the site Waste Management Plan to
be prepared by the Contractor
|
Disposal of at the Chemical Waste Treatment Centre or
other licensed recycling facilities
|
Stored in compatible containers in designated area
on-site
|
General Refuse & Floating Refuse
|
Food scraps, waste paper, empty containers, etc.
generated from the construction workforce
|
2016 to Early 2024
|
General refuse: maximum daily arising of up to 9,100
kg
|
Encourage segregation of recyclable materials (e.g.,
paper, tin-cans, etc.) for collection by outside recyclers
Collection of non-recyclable refuse by a reputable
collector for disposal at designated landfill sites.
|
Provide on-site collection points together with
recycling bins
|
Floating refuse trapped or accumulated in the newly
constructed seawall
|
2017 to Early 2024
|
Floating refuse: roughly 65 m3/year to be
collected from the newly constructed seawall
|
Collection by a reputable waste collector for disposal
at designated landfill sites
|
Provide on-site collection points
|
Note: (1) Timing and the quantity of waste
generation was based on the information provided in the EIA Report of the
Project. The update information on waste generation is provided in
“Construction Waste Statistic” presented in the EM&A Reports.
(2) Proposal of Further Development on Treatment Level / Details and Reuse Mode
for Marine Sediment was developed in accordance with the Waste Management Plan
(WMP) of 3RS and has been approved by EPD. The details of the proposal can be
found in Table 4.1 of the online version of 3RS WMP.
7.1.3
Mitigation
Measures
7.1.3.1
The implementation schedule of the recommended waste management
mitigation measures is presented in Appendix
C and the WMP.
7.2
Operation
Phase Monitoring
7.2.1.1
Wastes produced during operation phase would be generated by a variety
of landside and airside activities and mainly comprise of general refuse,
chemical waste, sludge from greywater treatment plant and floating refuse that
may be trapped on the artificial seawall of the expanded airport site.
7.2.1.2 Operation WMP shall
be submitted to EPD no later than 3 months before the commencement of operation
of the project in accordance to EP Condition 2.25.
7.2.1.3 During operation phase, weekly inspection should be
carried out along the artificial seawall of the expanded airport island to
check for any entrapment or accumulation of floating refuse by contractor.
Where an appreciable amount of floating refuse is found on the artificial
seawall during the weekly inspection, the locations of such refuse will be
recorded and arrangements with the contractor will immediately be made to
collect and clear the refuse from the seawall.
7.2.1.4 With the implementation of the recommended mitigation
measures for handling, transportation and disposal of the identified waste
arisings, no adverse residual impacts are anticipated during operation phase of
the project. Therefore, no other specific waste monitoring during operation
phase is required.
8
Land Contamination
8.1
Construction
Phase Monitoring
8.1.1.1
Since some of the assessment areas (i.e. fuel tank room within T2 building,
fuel tank room to the west of CAD antenna farm, seawater pump house and
switching station, pumping station and fire training facility) were not
accessible for site reconnaissance, further site reconnaissance would be
conducted once these areas are accessible in
order to identify any land contamination concern for the areas. Subject to the
further site reconnaissance findings, a supplementary Contamination Assessment
Plan (CAP) for additional site investigation (SI) (if necessary) shall be
prepared by the ET in accordance with EP Condition 2.20 and submitted to EPD
for endorsement prior to the commencement of SI at these areas.
8.1.1.2 Since all the areas identified with potential
contamination issues are under on-going use, the SI works are proposed to be
carried out after removal / decommissioning of the concerned facilities but
prior to the commencement of construction works at those areas.
8.1.1.3 After completion of the SI, the Contamination
Assessment Report (CAR) will be prepared and submitted to EPD for approval
prior to the commencement of construction works at the golf course, the
underground and above-ground fuel storage tank areas, emergency power
generation units, airside petrol filling station and fuel tank room. Should
remediation be required, Remediation Action Plan (RAP) and Remediation Report
(RR) will be prepared for EPD’s approval prior to commencement of the proposed
remediation and any construction works respectively.
8.1.1.4 All soil and groundwater remediation works should be
carried out to clean up to levels in compliance with the relevant Risk-based
Remediation Goals (RBRG) prior to commencement of any construction works at all
areas identified with contamination issues (if any).
8.1.1.5 During construction
phase, EM&A is to be carried out in the form of regular site inspections.
All related procedures and facilities for handling or storage of chemicals and
chemical wastes will be audited regularly to ensure they are in order, intact
and reported in the EM&A reports accordingly.
8.2
Operation
Phase Monitoring
8.2.1.1 As land remediation
is not anticipated during the operation phase, no environmental monitoring and
audit for land contamination is considered necessary.
9
Terrestrial Ecological Impact
9.1
Ecological
Mitigation Measures
9.1.1.1
Mitigation measures were recommended in accordance with Annex 16 of the
EIAO-TM. The recommended mitigation measures extracted from Section 12.7 of EIA
Report are listed below and the implementation schedule is presented in Appendix
C. In relation to the pre-construction
egretry survey, the requirement of submission of an Egretry Survey Plan is also
specified in EP Condition 2.14.
Avoidance
Land Formation Area
9.1.1.2
The land formation area is not
located in a habitat of high ecological sensitivity, therefore the impact to
terrestrial ecology is greatly avoided in the project design stage and no
specific terrestrial ecological mitigation measures is deemed necessary for the
loss of terrestrial habitat.
HDD Daylighting
Location
9.1.1.3
The originally proposed daylighting
location is immediately opposite the existing AFRF which minimises the pipe
connection works. However given the presence of the egretry, the daylighting
location is now shifted northwards. This measure aims to avoid direct impacts
to the egretry (an avoidance measure based on the outcomes of the impact
assessment) and furthermore, the daylighting location and mooring of flat top
barge, if required, will be kept away from the egretry (original daylighting
location refers to Section 12.6.3.1 of the EIA Report and alternative location
specified as blue zone in Drawing MCL-P132-EMA-9-001). The vegetation at the northeastern side of Sheung
Sha Chau Island near the proposed daylighting location is short and shrubby
which is less suitable for egretry use. Only a small works area (about 10 m x
10 m) will be needed at the tentative daylighting location. This alternative is
chosen as the preferred option owing to the ecological concerns, despite a
longer pipe connection being required. The final daylighting location within
the blue zone is subject to further adjustment to avoid direct encroachment on
the egretry, giving due consideration to the findings of the pre-construction
monitoring for Sha Chau egretry, which was conducted before the commencement of
the HDD drilling works at HKIA. With the adjustment of the daylighting
location, direct encroachment onto the egretry will be avoided.
Timing of
Construction Works
9.1.1.4 All HDD and related construction works on Sheung Sha
Chau Island will all be scheduled outside the ardeids’ breeding season (between
April and July). No night-time construction work will be allowed on Sheung Sha
Chau Island during all seasons except the contingency event as specified in
Sections 12.6.3.4 and 12.6.3.5 of the EIA Report. With these avoidance measures
the impact can be largely minimised.
Minimisation
Preservation of
Nesting Vegetation
9.1.1.5 The HDD daylighting location proposed in the blue zone
identified in Drawing
MCL-P132-EMA-9-001 will be located
within a rock area near the seashore, whilst the connecting pipelines will be
aligned along the seashore (above the shoreline). This proposed arrangement
will avoid the need for tree cutting, therefore trees that are used by ardeids
for nesting will be preserved.
9.2
Pre-construction
Egretry Survey
9.2.1.1
As a mitigation measure to avoid
disturbance to the egretry, the HDD daylighting location and associated works
will be conducted outside the Sha Chau egretry’s boundary. The location of the
HDD daylighting location is indicated as blue zone in Drawing MCL-P132-EMA-9-001. It is noted that the egretry’s
status and location could change from time to time even in the absence of human
disturbance. Therefore, a pre-construction survey is recommended to update the
latest boundary of the egretry during the breeding season before commencement
of the HDD drilling works at HKIA. The survey will update the latest boundary
of the egretry and to ensure the daylighting location will avoid direct
encroachment on the egretry. Subject to the pre-construction survey findings,
the daylighting location/ works area will be adjusted to avoid the future
egretry location.
9.2.1.2
The pre-construction survey has been
conducted once per month in the breeding season, i.e. between April and July,
prior to the commencement of HDD drilling works. The survey works was conducted
by qualified ecologist with at least three years’ experience on egretry
monitoring. Ardeid species and abundance were recorded whilst the latest
boundary of the egretry was identified. The information collected through the
pre-construction survey was incorporated into the Egretry Survey Plan, which
has been submitted to EPD no later than 1 month before the commencement of HDD
drilling works. The result of the egretry survey and the decision on HDD
daylighting location has been agreed with EPD and Agriculture Fisheries and
Conservation Department (AFCD) by submission of an Egretry Survey Plan prior to
the commencement of HDD drilling works.
9.3
Ecological
Monitoring
9.3.1.1
During the HDD construction works
period from August to March, ecological monitoring shall be undertaken monthly
at the HDD daylighting location on Sheung Sha Chau Island to identify and
evaluate any impacts with appropriate actions taken as required to address and
minimise any adverse impact found. Attention shall also be given to the months
either side of the ardeids breeding season, i.e. March and August, to identify
any early or late breeding activities that might be subject to disturbance. The
monitoring during works period shall be undertaken by experienced ecologist
competent in detecting any potential disturbance to the egretry.
10
Marine Ecological Impact
10.1
Introduction
10.1.1.1 The EIA Report has predicted the
project would lead to
some
ecological impacts and has recommended
a series of measures to avoid, minimise, and mitigate the impacts to an
acceptable level.
According to EIAO-TM Annex 16, an ecological EM&A programme would be needed to ensure
the recommended measures are properly implemented. In addition, the
EM&A programme also serves other purposes, including but not limited to
verifying the accuracy of the ecological assessment study, detecting any
unpredicted ecological impacts and recommending adaptive management in response
to unpredicted impacts.
10.1.1.2 It is recommended that an EM&A programme for
ecology be undertaken during the baseline (pre-construction), construction,
post-construction and operation phases of the project. The objectives of the pre-construction phase EM&A
are to undertake baseline monitoring for the corals and Chinese White Dolphins
(CWDs). The construction, post-construction and operational audit objectives
are to ensure that the ecological mitigation measures recommended in the EIA
Report are carried out as specified and are effective. The construction
and operation phase monitoring will be to monitor the CWDs over the
construction period and also determine the effectiveness of the mitigation on
CWD numbers. The EM&A will also be undertaken to verify the predictions in
the EIA Report.
10.2 Ecological
Monitoring
10.2.1.1 It is predicted in
the EIA Report that there will be direct
impact on the coral communities along the northern seawall of the existing
airport island. A pre-construction phase dive survey is recommended in the EIA Report to review the feasibility of coral
translocation and preparation of translocation and monitoring plan where
necessary. It is also predicted in the EIA Report
that the area immediately north of the existing airport platform, which
is predominantly used as a travelling area for the CWD, will be affected by the
project but that alternative routes for travelling east and west during
construction phase and initial operational phase will be available to CWDs,
potentially shifted to an area further north of the new platform.
10.2.1.2
In addition, habitat will be lost
permanently as a result of the 3RS project and there will be construction phase
disturbance to the CWDs movement and behaviour. Therefore, it is proposed
to conduct ecological monitoring during the baseline, construction,
post-construction and operation phases of the project, with the aims to monitor
the effects on the CWDs over the construction period, including the potential
shift in the CWD travelling areas and habitat use, to monitor the effectiveness
of the High Speed Ferry (HSF) speed and routing restrictions to the CWDs, as
well as the proposed new Marine Park (when it comes into operation) on CWD
distribution and numbers. Post-construction refers to the 12 months period
after the completion of marine works while operational monitoring refers to the
completion of the 3RS project as a whole.
10.2.1.3
The CWD monitoring will be conducted
by the ET, led by a CWD monitoring team leader with five years of post-graduate
experience in CWD monitoring. An overarching goal of these surveys is to
provide a dataset that can be compatible with the AFCD long term monitoring, be
stratified in such a way as to allow the calculation of density and abundance
for the various different phases listed above and to facilitate the calculation
of trends from these estimates, providing some assessment of how the project
and cumulative effects may be impacting the CWDs.
10.2.1.4
Methods of the baseline,
construction, post-construction and operation phase surveys will be as
consistent as possible with the AFCD long-term monitoring programme to allow
for direct comparisons of results among different phases, thus allowing an
evaluation of trends and impact assessments. Further details are provided
below.
10.2.1.5 Regular meetings
with the Authority and relevant Government Departments e.g. EPD and AFCD will
be arranged on a quarterly basis when the construction phase surveys commence
to review CWD distribution and abundance trends. The data collected from
vessel line transect survey, land-based surveys and theodolite tracking and the
Passive Acoustic Monitoring (PAM) will be reviewed to derive the distribution
and abundance trends, which will be checked against the transect survey
conducted under other projects and AFCD’s long-term monitoring. It will also be
conducted in conjunction with the review of stranding data to interpret the
full picture of CWD’s latest status during construction phase. It is
expected that the 3RS reclamation activities would result in the temporary
movement of CWDs away from 3RS works areas during the construction period, and
this may be indicated by a further decline in CWD abundance in the Northwest
Lantau survey area over the period of construction. Actions may also be
explored, where necessary, for remediating unpredictable impacts or changes in
abundance that are identified during the monitoring, recognising that actions
that serve to prolong the period of reclamation activity may in themselves have
an adverse impact on CWDs.
10.2.2 Pre-construction Phase Coral Dive Survey
10.2.2.1
It is proposed to conduct a
pre-construction phase dive survey for corals along the northern and
northeastern seawall of the existing airport island and at the daylighting
location on Sha Chau that may subject to direct habitat loss and disturbance as
a precautionary measure prior to marine construction works. The aim is to
identify any coral colonies suitable for translocation. The potential for coral
translocation will depend on the conservation value, the health status and the translocation
feasibility. A detailed coral translocation plan has been submitted to EPD no
later than 3 months before the commencement of marine construction works at
areas with potential to affect coral colonies in accordance to EP Condition
2.12. The determination of the translocation was based on the conservation
importance of the coral species (including hard corals, soft corals and
octocorals), the coral health conditions, size of the communities and
feasibility for translocation (e.g. attached to large boulders but <50 cm in
diameter and considered as manageable of translocation with minimal destruction
of the coral communities). Locations of pre-construction coral dive surveys for
the directly affected site are shown in Drawing No. MCL/P132/EMA/10-001,
the locations for the potential recipient site(s) were determined as part of
the translocation plan. In addition, it should be noted that the daylighting
location on Sha Chau will be finalised based on the findings from the
pre-construction egretry survey as indicated in Section 9.2, as well as
to avoid affecting any coral colonies in the area. Therefore, pre-construction
phase coral dive survey will only be carried out at Sha Chau if there are any
marine works with potential to affect coral colonies as identified by the ET.
The preliminary methodology for coral dive survey will be as follows:
Coral Dive Survey at
Directly Affected Site and Potential Recipient Site(s)
10.2.2.2
Based on the sub-tidal coral dive
survey at hard substrates conducted in the EIA Report, the underwater
visibility within the western Lantau waters are generally low. It is proposed
to conduct the pre-construction survey at sites which would be directly
affected by the project. Suitable substrates with coral communities will be
identified, supervised by qualified marine ecologists with at least 5 years of
coral dive survey experience.
10.2.2.3 The
pre-construction survey was conducted by spot-check dive followed by Rapid
Ecological Assessment (REA) should coral communities recorded. The survey was
conducted at hard bottom subtidal habitats along the northern artificial
seawall of the existing airport island, and at the proposed daylighting
location on Sha Chau as shown in Drawing No. MCL/P132/EMA/10-001
during daytime. If coral communities suitable for translocation are identified
at these directly affected sites, coral dive surveys including spot-check dive
followed by REA will also be conducted at potential recipient site(s).
10.2.2.4
The spot-check dive survey was
conducted by swimming in a search pattern along pre-determined areas at a
density sufficient to cover any major coral areas and to assess the type of
benthos existing in the proposed survey area, recording any presence of hard
corals (order Scleractinia), octocorals (sub-class Octocorallia), and black
corals (order Antipatharia). Information including estimated number of
colonies, number of species, coral cover, and partial mortality (if any) will
be recorded during the actual dive.
10.2.2.5
The following data was recorded
during the survey:
● Temperature, time and date;
● Location (GPS);
● Depth range;
● Visibility;
● Substratum type (i.e. hard
substratum seabed, intertidal rocky area); and
● Other invertebrates present.
10.2.2.6 Any special
features encountered in the coral areas, such as non-typical reef structures,
unusual coral species associations, unique or peculiar assemblages of the local
incipient reef formations, and reefs that are almost completely dominated by
one particular species, will be recorded.
10.2.2.7 Representative
photographs of the habitat and coral species, and other ecological features will
be taken to facilitate the determination of suitable similar habitats as
recipient site.
Rapid Ecological
Assessment Survey
10.2.2.8
With reference to the data collected during
the spot-check dive survey, REA surveys will be carried out at locations where
coral communities were identified and at potential recipient site(s). Transects
of 100m in length will be laid following the contour of the seabed at areas
where corals communities identified during the spot-check dives / at potential
recipient site(s).
10.2.2.9
The REA survey will be conducted
underwater in a two-tier approach to assess the sub-littoral substrata and
benthic organisms in an area:
● Tier I assessed the relative
coverage of major benthic groups and substrata.
● Tier II provided an inventory of
sedentary/ sessile benthic taxa, which will be ranked in terms of their
abundance at the survey site.
10.2.2.10 The taxon categories will be ranked
in terms of relative abundance of individuals, rather than the contribution to
benthic cover along each transect. The ranks will be made by visual assessments
of abundance, rather than quantitative counts of each taxon.
10.2.2.11 The benthic coverage, taxon abundance,
and ecological attributes of the transects will be recorded in a swath of about
2m wide, with about 1m on either side of the transects.
10.2.2.12 Representative photographs of any
important ecological features and corals will be taken to facilitate the
determination of suitable similar habitats as recipient site and as baseline
information for future post-translocation monitoring.
10.2.3 CWD Monitoring Phases
10.2.3.1
The CWD monitoring by vessel surveys
will be conducted during baseline, construction, post construction and
operational phases. Supplementary surveys including land-based theodolite
tracking and underwater acoustic monitoring using PAM or equivalent devices are
also proposed to provide additional information (such as behaviour change of
CWD associated with concurrent activities and habitat use of CWD during day and
night) for facilitating the review of effectiveness of mitigation measures
proposed and the need for adaptive management.
10.2.3.2
Monitoring for CWDs is proposed to be
conducted by vessel surveys at a frequency of two full surveys per month of the
Northeast Lantau (NEL) and Northwest Lantau (NWL) covering the Airport West
(AW), West Lantau (WL) and Southwest Lantau (SWL) transects, including focal
follows and photo-identification, during the baseline, construction,
post-construction and operational phases. The full surveys refer to completion
of two survey transects for NEL / NWL, WL and SWL per month, irrespective of
the number of days of effort required. Ad hoc monitoring of other CWD
habitat areas will be undertaken as required and on an as-needed basis to be
determined during the course of the monitoring. The monitoring periods for
vessel surveys will be as follows:
1) Baseline Monitoring – 6 months of baseline surveys has been undertaken before the
commencement of land-formation related construction works at a frequency of two
full surveys per month. The commencement date of baseline survey was agreed
between the ET / IEC / AAHK / PM to ensure timely submission of the baseline
monitoring report to EPD and relevant authorities. The purpose of the baseline
monitoring is to establish pre-construction conditions prior to the
commencement of the marine construction works. The vessel-based dolphin
monitoring transects in baseline monitoring are shown in Drawing No. MCL/P132/EMA/10-002.
2) Construction Phase Monitoring – This will be conducted for the duration
of the land-formation related construction works for the project at a frequency
of two full surveys per month with regular reviews on frequency on at least an
annual basis. The purpose of the construction phase monitoring is to evaluate
conditions during construction and provide data for the preparation of Marine
Park establishment and management plan.
3) Post Construction Phase Monitoring – This will be conducted upon the completion of
marine construction works for 12 months at a frequency of two full surveys per
month. The purpose of the post construction phase monitoring is to evaluate
conditions after completion of all marine works and collect data for the review
of recovery of the marine environment.
4) Operation Phase Monitoring - This will be conducted for a period of at least 12 months after the
full implementation of proposed Marine Park at a frequency of two full surveys
per month. The main purpose of the monitoring is to detect any rebound in use
of areas north and east of HKIA during the implementation of the proposed
Marine Park as mitigation for habitat loss for the airport expansion, and to
evaluate the overall, long-term impacts of the project on CWDs. The vessel
based dolphin monitoring transects in construction, post-construction and
operation phases monitoring are shown in Drawing No. MCL/P132/EMA/10-003,
with transects for operation phase monitoring subject to refinement based on
the actual boundaries for the extension of Hong Kong International Airport
Approach Areas (HKIAAA) and 3RS Marine Park.
10.2.3.3 The vessel
monitoring data will be used to monitor the effectiveness of the mitigation
measures proposed for the amelioration of construction, post-construction and operation
phase impacts. In particular, the vessel monitoring data in the northwest
Lantau area together with the data of marine traffic tracking system (e.g.
Automatic Identification System (AIS) data) will be used as an audit tool to
review and determine the effectiveness of the reduction in speed for the
diverted SkyPier HSF on disturbance to the CWDs around the north of Sha Chau
and Lung Kwu Chau Marine Park (SCLKCMP) (see Drawing No. MCL/P132/EMA/10-002).
In addition to the proposed vessel transect monitoring, some additional
monitoring is proposed in the form of land-based theodolite tracking, combined
with underwater acoustic monitoring to provide additional information on CWD
behaviour and occurrence during 3RS construction works to supplement the
details on CWD abundance patterns obtained from vessel transect surveys. The
main aim for these two monitoring types is to supplement the vessel transect
survey findings detailed above and to help in verifying the predictions in the
EIA Report. The effectiveness of these additional measures in monitoring data
collection will be reviewed during the construction phase, to confirm the need
and required frequency that will be applied for post-construction and operation
phase monitoring.
10.2.3.4 Land-based
theodolite tracking is proposed to cover the 6-months baseline and it will also
cover the whole duration of the land formation related construction works to
provide adequate seasonal data with the data serving to provide fine-scale
information on CWD behaviour and activity during construction, specifically
swimming and movement patterns of CWD groups, and to further capture CWD
response to vessels and travel patterns. The theodolite station established on
Sha Chau is proposed to be used, given its good aspect overlooking the proposed
3RS reclamation area north of HKIA. Another land-based monitoring station at
north of Lung Kwu Chau is proposed to supplement the vessel monitoring data in
determining the effectiveness of the reduction in speed for the SkyPier HSF on
disturbance to the CWDs (Drawing
No. MCL/P132/EMA/10-004). The
frequency of the theodolite tracking will be two days per month at both Sha
Chau station and Lung Kwu Chau station during the 6-month baseline monitoring
survey and the first six months of SkyPier HSF route diversion and speed
restriction plan implementation (hereafter referred to as SkyPier HSF
Plan). During the construction phase, the frequency of the theodolite
tracking for impact monitoring will be one day per month at the Sha Chau
station and one day per month at the Lung Kwu Chau station. The frequency of
CWD land-based monitoring will be subject to review after reviewing the data
from the baseline monitoring and from the initial six months of SkyPier HSF
Plan implementation. Should any changes in the theodolite stations or tracking
frequency be proposed as a result of the review, the proposed changes will be
agreed with EPD and AFCD. Any available land-based survey data collected near
the Lung Kwu Tan and Urmston Road areas by other projects will also be reviewed
to supplement the survey results for the report to Advisory Council on the
Environment (ACE) on the effectiveness of the mitigation measures on
CWDs.
10.2.3.5
Underwater acoustic monitoring using
PAM or equivalent devices as adopted in the EIA assessment will also be
undertaken during the same periods including 6 months of baseline and within
the whole duration for land formation related construction works. Data
would be used in tracking diurnal patterns of CWD presence and vocal activity,
and providing information on ambient noise level in the underwater environment.
As the information obtained from these surveys does not quantify CWD density
and abundance, it is not useful to set an Action / Limit Level based on data
from these supplemental PAM or equivalent devices. It is proposed to deploy the
PAM station at the southern water of SCLKCMP boundary in order to coincide and
supplement the data collected from the land-based monitoring station at south
of Sha Chau (Drawing No. MCL/P132/EMA/10-005), which will be
subject to review. Should any changes in the PAM station be proposed as a
result of the review, the proposed changes will be agreed with EPD and AFCD.
10.2.3.6
In conjunction with the above
monitoring efforts, and given the uncertainty on the levels of HSF traffic from
SkyPier / the Intermodal Transfer Terminus (ITT) in future years, the EM&A
will also monitor actual numbers of HSFs operating from SkyPier after the HZMB
and HKBCF commence operations by obtaining HSF movement data including AIS
vessel tracking data from the SkyPier operators.
10.2.4
CWD Monitoring Methods
Small Vessel Line Transect Surveys
10.2.4.1
Vessel-based CWD surveys provide data
for density and abundance estimation and other assessments using
distance-sampling methodologies, specifically, line-transect analysis.
These surveys also include photo-identification of individual dolphins within
the monitoring area when conditions are suitable, to provide data on individual
use of this specific area. Focal follow data from the vessel may also
potentially be collected, depending on a series of factors such as the presence
of special features for identification of individuals (like presence of
scratches, nick marks, cuts, wounds and distinguished color patterns) and
favourable weather conditions.
10.2.4.2 The surveys involve small vessel line-transect data
collection and have been designed to be similar to, and consistent with,
previous surveys for monitoring of small cetaceans in Hong Kong. The survey was
designed to provide systematic, quantitative measurements of density, abundance
and habitat use by line transect methods.
10.2.4.3 The transects to be
monitored will cover NEL, NWL, AW, WL and SWL and will be consistent with the
AFCD long-term monitoring programme (except AW) during the baseline,
construction, post-construction and operation phases. Due to the progressive
extension of the works area that will be demarcated by floating booms during
construction and permanent land formation footprint during operation, the
transects will be adjusted in the construction, post-construction and operation
phases to outside the area that can no longer be accessed by the survey vessel.
The AW transect has not been previously surveyed in the AFCD programme due to
the restrictions of HKIAA. Nevertheless, this transect was established during
the EIA of the 3RS project, with the aim to collect project specific baseline
information within the HKIAAA to fill the data gap that was not covered by the
AFCD programme. This will provide a larger sample size for estimating the
densities and patterns of movement in the broader study area of the project.
The baseline, construction, post construction and operation phase line
transects are shown in Drawing
No. MCL/P132/EMA/10-002 and MCL/P132/EMA/10-003
respectively.
10.2.4.4
A 15-20 m vessel with a flying bridge
observation platform about 4 to 5 m above water level and unobstructed forward
view, and a team of three to four observers will be deployed to undertake the
surveys. Two observers are to be on search effort at all times when
following the transect lines with a constant speed of 7 to 8 knots (i.e. 13 to
15 km per hour), one using binoculars and the other using unaided eyes and
recording data.
10.2.4.5 When CWDs are seen,
the observer team will be taken off-effort, the dolphins will be approached and
photographed for photo-ID information (using a Canon 7D [or similar] camera and
long 300 mm+ telephoto lens), then followed until they leave the study area or
are lost. At that point, the boat returns (off effort) to the survey line and
begins to survey on effort again. CWD density (D), abundance (N), and their
associated precision (CV) will only be calculated from dolphin sightings and
effort data collected under conditions of Beaufort 0-3 and visibility of approximately
1200 m or greater (in practice, surveys should normally be postponed when
visibility is below 1 km and/or when Beaufort 5 is reached), using conventional
line transect methods and the formulae as detailed below:
10.2.4.6 Based on the vessel
survey data, seasonal differences in dolphin density and use of the study area
will then be examined annually, using the solar seasons (Winter:
December-February, Spring: March-May, Summer: June-August, Autumn:
September-November) and/or oceanographic seasons (Dry: October-March, Wet:
April-September).
10.2.4.7 Focal follows of
dolphins would be used for providing supplementary information only where
practicable (i.e. when individual dolphins or small stable groups of dolphins
with members that could be readily identified with unaided eyes during
observations and weather conditions are favourable). These involve the
boat following (at an appropriate distance to minimize disturbance) an
identifiable individual dolphin for an extended period of time, and collecting
detailed data on its location, behaviour, response to vessels, and associates.
This type of data allows information to be gathered on the movement paths and
travel corridors used by dolphins in the survey region.
Land-based Surveys and Theodolite Tracking
10.2.4.8 Land-based
monitoring has been able to obtain fine-scale information on the time of day
and movement patterns of the CWDs. A digital theodolite (Sokkia/Sokkisha
Model DT5 or similar equipment) with 30-power
magnification and 5-s precision will be used to obtain the vertical and horizontal angle of each
dolphin and vessel position. Angles
are converted to geographic coordinates (latitude and longitude) and
data will be recorded using Pythagoras software, Version 1.2 (Gailey &
Ortega-Ortiz, 2002). This
method delivers precise positions of multiple
spatially distant targets in a short amount of time. The technique
is fully non-invasive, and allows for time and cost-effective descriptions of
dolphin habitat use patterns at all times of day (Würsig et al. 1991; Piwetz et
al. 2012). Examples of modern statistical techniques to describe
movements relative to habitat and anthropogenic influences are described in
Gailey et al. (2007) and Lundquist et al. (2012).
10.2.4.9 Land-based
observation and theodolite tracking station will be set up at two locations
facing east/south/west on the southern slopes of the island of Sha Chau, and an
audit location for SkyPier HSF facing north, northeast, and northwest, at Lung
Kwu Chau. The proposed location (D and E) are shown with position
coordinates, height of station and approximate distances of consistent theodolite
tracking capabilities for CWDs in Table 10‑1
and shown in Drawing
MCL/P132/EMA/10-004.
Table 10‑1:
Land-based Survey Station Details
Station
|
Location
|
Geographical
Coordinates
|
Station
Height (m)
|
Approx. Tracking
Distance (km)
|
D
|
Sha Chau
|
22° 20’ 43.5” N
113° 53’ 24.66” E
|
45.66
|
2
|
E
|
Lung Kwu Chau
|
22° 22’ 44.83” N
113° 53’ 0.2” E
|
70.40
|
3
|
10.2.4.10 The frequency of the
theodolite tracking will be two days per month at both the Sha Chau station and
Lung Kwu Chau station during the 6-month baseline monitoring and during the
initial six months of implementation of the SkyPier HSF Plan. The
monitoring frequency during the construction phase for marine works will be one
day per month at both Sha Chau station and Lung Kwu Chau station. The
monitoring frequency and stations in the construction phase are subject to
review based on the baseline monitoring findings and a review of the
effectiveness of the SkyPier HSF Plan route diversion and speed control
measures during the first six months that these are in effect. Surveys will be
undertaken during a period of about 5-6 hours per day from the monitoring
stations, with some days longer than this but others truncated due to
weather-related deterioration of sighting conditions. Three surveyors
(one theodolite operator, one computer operator, and one person scanning with
binoculars) will be involved in each survey. Observers will search for dolphins
using unaided eyes and handheld binoculars (7X50). A theodolite tracking
session will be initiated when an individual CWD or group of CWD is
located. Where possible, a distinguishable individual will be selected,
based on colouration, within the group. The focal individual is then
continuously tracked via the theodolite, with a position recorded each time the
dolphin surfaces. If an individual cannot be positively distinguished from
other members, the group will be tracked by recording positions based on a
central point within the group whenever the CWDs surface (Bejder, 2005;
Martinez, 2010). Tracking continues until animals are lost from view, move
beyond the range of reliable visibility (>1-3 km, depending on station
height), or environmental conditions obstruct visibility (e.g., intense haze,
Beaufort sea state >4, or sunset), at which the research effort will be
terminated. During the baseline phase, in addition to the tracking of
CWDs, all vessels that move within 2-3 km of the station will be tracked, with
effort made to obtain at least two positions for each vessel. It is
anticipated that this will not be feasible during the construction phase in the
3RS construction area, and possibly for some space outside this area also, due
to the anticipated high volume of construction-related traffic.
Theodolite Tracking Data Analysis
10.2.4.11 Theodolite tracking will include focal follows of CWD groups and vessels
(the latter to be undertaken when possible). Focal follow data will be filtered
to include only CWD tracks with greater than 2 positional fixes and 10 minutes
or greater in duration. The ten minute window has been statistically validated
for theodolite tracking analyses (Gailey et al. 2007, Lundquist 2012), and such
a logical bound is also described in Turchin (1998). If two consecutive
dolphin tracks are more than 5 min apart, they will be split and analysed
separately. A broad time of day category is assigned for each track
(morning = first position recorded before 12 pm; afternoon = first position
recorded at 12 pm or later). CWD response variables that will be calculated for
each track include mean reorientation rate, swimming speed and linearity. Reorientation
rate is the degrees per minute of changes in direction of a tracked individual
or group of CWDs. Mean swimming speed is calculated by dividing the distance
travelled by the duration between two consecutive positions (Gailey et al.
2007). Linearity is an index of net movement ranging from 0 to 1, with 0
equating to no net movement and 1 equating to straight line movement. It is
calculated by taking the sum of distances travelled for each leg and dividing
by the net distance between the first and last fix of a track.
10.2.4.12 In order to
evaluate variation in CWD movement patterns in the presence of vessels, it is
necessary to establish a distance threshold. Consistent with general practice
and the data gathered for the EIA of this study, when vessels are within 500 m
of the focal individual or group, they will be considered present. The 500 m
threshold was chosen since Sims et al. (2012) showed that most vessels exceeded
background noise when less than 500m away, but not at greater distances.
The threshold has been used in other marine mammal situations for similar
reasons and direct measurement of animal reactions, such as in Lundquist et al.
(2012) for southern right whales (Eubalaena australis). As it is not
possible to record geographic locations of all targets simultaneously,
positions for CWDs and vessels will be interpolated post hoc (i.e.
during analysis in the lab), allowing for a more precise estimation of vessel
distances from dolphins at a given time. All types of vessels within 500m
are considered, including high speed ferries. The high speed ferries
travel through the area much more rapidly than fishing, recreational,
industrial vessels carrying cargo and will therefore be noted and assessed as a
separate category.
10.2.4.13 ArcMap will be used to plot CWD and vessel positions, Microsoft
Excel will be used to conduct computational analysis of leg speed, and
linearity and R statistical software will be used to perform statistical
analyses. Data will be tested for normality and transformed if residuals are
not normally distributed. Because dolphin focal follows tend to vary in
duration, each CWD track is split into 10-minute segments. In order to reduce
pseudo-replication, analysis will be run to determine the temporal lag at which
two segments from the same focal group are no longer auto-correlated.
Univariate statistical analyses (one-factor Analysis of Variance, ANOVA) will
be run to evaluate variation between factors.
10.2.4.14 Similar to
vessel-based surveys, seasonal differences in relative CWD occurrence and use
of the study area will be examined for land-based surveys, using both the solar
seasons (Winter: Dec-Feb, Spring: Mar-May, Summer: Jun-Aug, Autumn: Sep-Nov)
and oceanographic seasons (Dry: Oct-Mar, Wet: Apr-Sep; see Chen et al. 2010).
In addition, behavioural descriptions and potential avoidance/association by
CWDs relative to vessels or other on-water anthropogenic activities will be
analysed by multi-variate analyses, as in Gailey et al. (2007) and Lundquist et
al (2012).
Passive Acoustic Monitoring (PAM)
10.2.4.15 Acoustic data will
be gathered to listen for CWDs occurrence patterns and to obtain anthropogenic
noise information simultaneously. Autonomous PAM was designed to provide
daytime and night-time information on CWD occurrence and vocal activity. This
work involves a type of PAM (Wiggins and Hildebrand 2007) termed an Ecological
Acoustic Recorder (EAR) (Lammers et al. 2008), with bottom-mounted broad-band
recording capability operable from 20 Hz to 32 kHz. The EAR is proposed to
be positioned at the south of Sha Chau Island to coincide with the land-based
theodolite survey (Drawing
No. MCL/P132/EMA/10-005).
Analysis (by a specialized team of acousticians) involves manually browsing
through every acoustic recording and logging the occurrence of vessel transits
and other unusual sounds. This approach for data analysis is adopted because
generally high ambient noise conditions in these waters have meant that an automatic
algorithm cannot be reliably used to detect dolphin sounds. All data
therefore need to be re-played by computer and listened to by human ears for
accurate assessment of dolphin group presence. Vessels will be logged when
discrete transits passing the EAR can be differentiated from background noise,
and thus there can be more than one vessel detection per file.
10.2.4.16 To improve the length
of deployments, speed of data gathering, and efficiency in data analysis, the
C-POD and its successor the F-POD (developed by Chelonia Limited, UK) are
proposed in replacement of the previous EAR in early 2021 at the same location.
The C-POD/F-POD can detect cetaceans by recognising the trains of echolocation
clicks in the range 20-160 kHz and records the click trains automatically. The
C-POD has also been adopted by the AFCD in marine mammal monitoring for
collection of useful data on night-time usage of dolphins at the SCLKCMP and
the Brothers Marine Park (BMP). Analysis is performed using the proprietary
software (CPOD.exe/ FPOD.exe developed by Chelonia Limited, UK). Objective
automated data analyses to detect and identify echolocation click trains
produced by marine mammals are conducted. The click data detected by the
C-POD/F-POD are processed using the KERNOF classifier in the software to
identify click trains and their likely sources and to ensure similar sounds,
such as boat sonar noise in the ambient environment, are not counted as dolphin
detection. Experienced analysts then perform visual validation to assess the
overall rate of false dolphin detection positive minutes (DPMs) as identified
by the classifier. The visual validation is based on a representative sampling
of all detections and examining the characteristics of clicks, multi-path
clusters, and click trains.
10.2.4.17 Comparisons of CWD
detections during theodolite tracks with corresponding C-POD/ F-POD click
records will be made post hoc, that is after both sets of data have been
separately analysed, positions are known, and the positions can be compared to
frequencies of CWD detections.
10.2.4.18 A review of CWD sightings
from the land-based survey data in relation to the PAM device will also be
undertaken to provide data on the approximate locations of the CWDs at the time
their signals are detected. Thus, overlaps of land-based CWD sightings and the
PAM records of CWDs will be analysed.
10.2.5 Review of Construction Phase CWD
Monitoring Programme
10.2.5.1 Subject to details
of the marine construction programme established during the detailed design
stage, the aforementioned CWD monitoring programme will be reviewed by the
ET. Where the CWD monitoring programme requires revision or updating
according to the detailed construction programme, the ET will revise or update
the monitoring programme accordingly, and the revised monitoring programme will
be verified by IEC before submission to EPD and AFCD for approval prior to
commencement of the marine construction works.
10.2.6
Cumulative
Impacts for Travel Corridors/ Areas and Connectivity between Core Habitat Areas
10.2.6.1 It is clear from
past and present data that the area north of the existing airport is used for a
variety of CWD behavioural functions, including travel between Northwest and
Northeast Lantau. The longer that cumulative construction activities
exist in and near this general area, the greater will be the effect on
efficient habitat use of CWD, with both the project and the HZMB Hong Kong Link
Road (HKLR) / HKBCF / Tuen Mun-Chek Lap Kok Link (TM-CLKL) projects forcing the
CWDs to move further north towards the Tuen Mun area. However, the corridor/
area between the project and waters to the north should still be available and
useable for CWDs to transit between western and eastern waters north of the
airport. As these implications could increase with all the projects being
constructed and implemented concurrently, a long-term monitoring programme is
recommended, consistent with that being undertaken by AFCD (i.e. by using
vessel transect monitoring) as discussed in Section 10.2.4 above.
10.3 Detailed
Implementation of Dolphin Exclusion Zone
10.3.1 Dolphin Exclusion Zone Plan
10.3.1.1 According to
Environmental Permit No. EP-489/2014 Condition 3.1(v), detailed implementation
of Dolphin Exclusion Zone (DEZ) shall be included in this updated EM&A
Manual. This section provides the technical guidelines for the implementation
of DEZ. The actual marine construction activities that require the
implementation of DEZ were determined in the DEZ Plan, which was prepared by
the ET based on an objective assessment of noise levels and noise intensities
from different marine construction activities as methodologies were finalised.
10.3.1.2 A DEZ with 250 m
radius from the boundary of the works will be established for marine
construction activities that require the implementation of DEZ. The DEZ Plan
has been submitted to EPD for approval at least 1 month prior to commencement
of construction activities requiring DEZ. The DEZ serves as a short-term
approach to provide appropriate and immediate action should CWDs be sighted
within the DEZ for construction activities requiring a DEZ. Should the Action
Level for CWD monitoring be exceeded, the DEZ monitoring area shall be
increased to 500 m for daytime works until the ET notify the resume of the 250
m DEZ. Details of the DEZ are described below:
10.3.2 Daytime Monitoring of Dolphin Exclusion Zone
10.3.2.1 In the 3RS EIA
Report, the impact significances of acoustic disturbance from daytime and
night-time reclamation related construction works were evaluated as
“Low-Moderate” and “Moderate” respectively. DEZs have been adopted in Hong Kong
for other previous projects involving similar marine works activities as the
3RS project and are therefore proposed as a precautionary and a mitigation
measure respectively to address the impacts identified from certain daytime and
night-time marine works activities.
10.3.2.2 A DEZ set at a
certain distance from potentially harmful marine works activities (e.g. certain
marine works known to be very noisy) will be established during all periods of
each of the marine construction activities requiring a DEZ. The DEZ monitoring will be carried out from
the shore or on a stationary barge or vessel depending on the type of
construction activity requiring the DEZ, with an unobstructed elevated view of
the DEZ, by using naked eyes and occasionally with the aid of binoculars (e.g.
Steiner Navigator 7X50 HD-stabilized Compass or model with similar or more
advanced specification) for confirmation, or by using combination of high
definition pan-tilt-zoom network camera and closed-circuit television system
(CCTV). The use of CCTV or alternative approach proposed by the contractor for
achieving effective DEZ monitoring must be tested in the site before actual use
for DEZ monitoring, and all the tests shall be witnessed and verified by AAHK,
ET and IEC. The actual monitoring locations will be proposed in the DEZ Plan
which will be determined by the ET and thereafter subject to update based on
the marine construction programme.
10.3.2.4
Prior to the commencement of construction activities that require the
implementation of a DEZ, the DEZ will be thoroughly scanned for dolphins for an
initial period of 30 minutes. If dolphins are observed in the DEZ, the dolphin
observers will immediately inform the Site Supervisor or relevant person
through mobile phone or handheld transceivers to delay the commencement of the
construction activities in the works area within the DEZ, until the dolphins leave
and the DEZ is continuously free of dolphin for a period of 30 minutes.
10.3.2.5 If dolphins are observed within the
DEZ during construction works, the dolphin observers will inform the Site
Supervisor or relevant person through mobile phone or handheld transceivers to
cease the construction activities within the DEZ. The dolphin observers will
continue to monitor the dolphins. When the dolphins leave the DEZ and the DEZ
is clear of dolphins for a period of 30 minutes, the dolphin observers will
inform the Site Supervisor or relevant person that the construction activities
within the DEZ could be resumed.
10.3.2.6 If dolphins are observed in close
vicinity but outside the DEZ, the dolphin observers will also inform the Site
Supervisor about the presence of the dolphins. The dolphin observers will
remain in position and closely observe the movement of the dolphins as well as
searching for the appearance of any other dolphins within the DEZ.
10.3.2.7 All vessel captains involved in
construction activities in and around the DEZ shall be advised to pay special
attention to the presence of dolphins around the DEZ and to use appropriate
slow speed when travelling within or near to the DEZ area in order to reduce
chance of collision with or other adverse impacts to the dolphins.
10.3.2.8 In case of injury
or live-stranded dolphins being found within the DEZ, the dolphin observers
will immediately inform the Site Supervisor to suspend the construction
activities within the works area around the DEZ and contact AFCD through “1823”
marine mammal stranding hotline.
10.3.2.9 Each DEZ monitoring
team has to fill in a data record sheet for data keeping purpose when they are
on duty. General information not limited to those listed below will be recorded
at the beginning of the monitoring:
● Date;
● Surveyors;
● Monitoring Location;
● Construction Activity;
● Weather;
● Beaufort Sea State;
● Commencement Time of Monitoring; and
● Commencement Time of Construction Activity.
10.3.2.10 In case dolphins are detected within the DEZ, the
information included but not limited to the following will be recorded:
● Sighting No.;
● Group Size;
● First Sighting Time within DEZ;
● Last Sighting Time within DEZ;
● Cessation Time of Construction Work;
● Re-start Time of Construction Work;
● Location of Dolphins; and
● Behaviour.
10.3.3 Night-time Monitoring of Dolphin
Exclusion Zone
10.3.3.1 The PAM result during
the 3RS EIA study suggested that night-time CWD activity in the 3rd runway
footprint area may be more extensive than previously thought, and therefore
implications for disturbance and loss of area could be higher than the daytime
use alone would indicate. Therefore, the implementation of an effective DEZ
monitoring scheme during night-time periods was also recommended in the 3RS EIA
Report.
10.3.3.2 Night-time DEZ monitoring will be conducted by using
night vision device (NVD) that greatly enhance the small amount of available
light at night to make visual observing of CWDs possible. The NVD is suggested
to be in the form of hand-held, head-mounted or tripod-mounted units depending
on the location of the DEZ monitoring station (e.g. ATN model PS15-CGTI Night
Vision Goggles with 3X lens or model with similar or more advanced
specification and performance).
10.3.3.3 Similar to daytime
DEZ monitoring, the use of NVD to assist the implementation of DEZs shall be
carried out from the shore or a stationary barge or other vessel, and
experienced personnel shall be used, dedicated 100% to the dolphin searching
effort (i.e. not ancillary to other activities). Night-time DEZ monitoring will
follow a similar procedure to the daytime DEZ monitoring except for the
complete use of NVD over naked eyes for scanning. It is recommended that two
night-time observers scan the exclusion zone, with appropriate staggered rest
periods to avoid eye fatigue and general fatigue.
10.3.3.4 All selected NVD
shall be tested before actual use for night-time DEZ monitoring. This test is
to be conducted by experienced dolphin-monitoring researchers, preferably at a
site or sites where dolphins occur with regularity and can be tracked by
theodolite in the late afternoon hours, so that visual day-time tracking can be
“handed off” to night-time NVD sighting as darkness descends. All tests shall
be witnessed and verified by the AAHK/ PM, ET and IEC. Only after such
dedicated testing has provided confidence that the NVD technique allows for
reliable detection of dolphin at night shall the use of NVD be adopted. The
feasibility of using PAM involving the use of hydrophones or automated cetacean
detectors with real-time data capability, or CCTV involving high definition
network camera with night vision could be explored by the Contractor for the
DEZ monitoring in case the NVD is found to be ineffective for night-time CWD
detection. Alternative night-time monitoring devices, including using PAM or CCTV should be witnessed and verified by the AAHK/ PM, ET
and IEC with satisfactory performance, prior to the adoption for implementation
of night-time DEZ monitoring.
10.4 Acoustic Decoupling
10.4.1.1 According to Environmental
Permit No. EP-489/2014 Condition 3.1(v), detailed implementation of acoustic
decoupling shall be included in this updated EM&A Manual. This section
provides the technical guidelines for the acoustic decoupling devices to be
implemented to minimise the indirect disturbance to CWD during marine
construction.
10.4.1.2 CWD whistle
communication frequencies in the 4-8 kHz octave band are well above the
frequencies produced by most large vessels used in shipping and marine
construction activities. Based on available experience in Hong Kong,
these types of vessels are not considered to be a significant source of
acoustic disturbance. Main engines of the proposed working vessels are
therefore not considered to be a significant source of acoustic disturbance and
will not be considered as source of noise and vibration. However, there is
still a small possibility that noise would be transmitted from the noisy
Powered Mechanical Equipment (PME) on vessels (i.e. air compressors, generators
and winch generators) into the sea. Therefore, acoustic decoupling
measures for noisy equipment which are not embedded on vessels are required to
minimise the possible noise impact on CWD / marine ecology.
10.4.1.3 Noise isolation pad could be one of the acoustic decoupling
devices to separate the noisy PME from the deck or hull in order to reduce
noise transmission to the sea via the vessel. The size of the isolation
pad for the identified noisy PME should be large enough to cover the whole base
with thickness of at least 24 mm. A schematic diagram of noise isolation pad is
shown Drawing
MCL/P132/EMA/10-006.
10.4.1.4 The noisy PME on vessels
should be fixed on noise isolation pad instead of directly mount on the
deck. Contractor should ensure the foundation of equipment is flat and
level prior to installation. Adequate clearance all around the PME should
be kept to avoid direct vibration transmission to other materials and
machineries.
10.5 Action/Limit Levels and Event Action
Plan for CWD
10.5.1.1 As mentioned in
Section 10.2.1.5 and the EIA Report, it is expected that the 3RS reclamation
activities would result in the temporary movement of CWDs away from 3RS works
areas during the construction period, and this may be indicated by a further
decline in CWD abundance in the Northwest Lantau survey area over the period of
construction. As part of the set of required mitigation measures for the
construction of the project, an Event and Action Plan framework has been
developed that is intended to detect any deterioration in ambient environmental
quality that could endanger CWDs or result in an overall decline in CWD numbers
in Lantau waters (NEL, NWL, AW, WL and SWL) as a whole below a certain
threshold level. Appropriate remedial actions are described and would be taken
as part of the plan, intended to prevent unacceptable deterioration in
environmental quality or a reduction in CWD numbers in Lantau waters as a whole
below the Limit Level that may be caused by 3RS construction works.
10.5.1.2 The Event and
Action Plan has been reviewed and consolidated based on the data from the
baseline CWD monitoring surveys, with reference to historical data on some key
parameters that are indicative of the health of the CWD population (and
specifically the portion that uses Hong Kong waters as part of their range),
and can be monitored as part of regular EM&A efforts during construction, providing
early warning when particularly serious impacts may be occurred. The results
would be used as a management tool, so that if the decline in overall CWD
encounter rate is determined to be from the 3RS construction process,
appropriate measures may then be triggered / considered to minimise possible
impacts with short term response to events after reviewing the monitoring data
for each month. A set of criteria that may trigger certain identified actions
have been developed and are detailed in the following sections.
10.5.2 Action Response Approach
10.5.2.1 The approach
proposed for formulating the AL and LL for construction phase CWD monitoring
involves using the encounter rate. The encounter rate provides a direct
indicator of the health of CWD population and it can be determined from the
EM&A effort (i.e. CWD monitoring). Actions will be taken when these levels
in the overall Lantau waters covering NWL, AW, NEL, WL and SWL have been
triggered.
10.5.2.2 Both the Encounter Rate of Number of Dolphin Sightings
(STG) and Encounter Rate of Number of Dolphins (ANI) from the baseline survey
are adopted as the parameters for determining the AL and LL. The calculation of
the CWD encounter rates for determining AL and LL made use of the dataset from
the CWD Baseline Monitoring undertaken for this project as part of the EM&A
requirement under the Environmental Impact Assessment Ordinance (EIAO). The
formulas for calculating STG and ANI encounter rates are shown below:
Quarterly Encounter Rate of Number of Dolphin
Sightings (STG)
Quarterly Encounter Rate of Number of Dolphins
(ANI)
(Notes:
1. Only data collected under Beaufort 3 or below condition was used;
2. A quarter refers to three survey
months, and data collected within a quarter was counted and calculated to
obtain the total no. of on-effort sightings, total no. of dolphins from
on-effort sightings and total amount of survey effort)
10.5.2.3 According to the
approved 3RS EIA Report, 3RS construction works are expected to result in CWDs
temporarily moving away from the project works area during the construction
phase. The use of the encounter rate approach, making use of the quarterly
dolphin vessel survey findings to compare with baseline STG and ANI values provides
a short to medium term frequency method for monitoring and responding
appropriately to changes in CWD abundance as project works progress. It is
proposed that AL and LL are established for Lantau waters covering NEL, NWL,
AW, WL and SWL as a whole, as it has been anticipated in the EIA Report that
the number of CWDs in North Lantau waters will decline due to the project, and
CWDs may move to other areas around Lantau including West Lantau and Southwest
Lantau. A combined encounter rate can present a general picture of the entire
waters around the Project area and Lantau.
10.5.2.4 Natural seasonal fluctuations of CWD encounter rates
across the four seasons may cause non-project related triggering of the AL
and/or the LL, therefore historical CWD data has been reviewed to take into
account the effect of seasonal fluctuations on the CWD encounter rate. The
seasonal variations of CWD quarterly encounter rates based on the AFCD long
term marine mammals monitoring over the past six years covering the NEL, NWL,
WL and SWL waters were reviewed. The findings showed that in general, the first
quarter or winter/spring (Q1, i.e. January to March) of the year is the low
season for CWD encounters, with the values of STG and ANI consistently being
the lowest during Q1 compared to other quarters over the years with a
decreasing trend. The CWD encounter rates generally increase in late spring/
early summer (Q2, i.e. April to June). The CWD baseline monitoring conducted
between mid-December 2015 and mid-June 2016 for the 3RS project shows a similar
trend (i.e. encounter rates are lowest in during Q1 (winter/spring) and
increase during Q2 (late spring/early summer).
10.5.2.5 The dataset of the CWD
Baseline Monitoring for this project has been taken mainly during Q1 to Q2 of
2016, during which time the quarterly encounter rates for STG and ANI were
collected in the Q1, thereby capturing the low season. The dataset is therefore
suitable for establishing the AL and/or LL for future impact monitoring. Review
of the AL and LL has been undertaken in the 1st annual EM&A
report with full year data collected covering the peak season encounter rates.
It is recommended to maintain the existing AL/LL derived from the CWD Baseline
Monitoring Report. The criteria for triggering the AL and LL during CWD impact
monitoring are detailed in Table 10‑2 and Table 10‑3 below.
Table 10‑2:
Approach for Defining Action Level and Limit Level
|
NEL, NWL, AW, WL and SWL as a Whole
|
Action Level
|
Running
quarterly* STG & ANI < low season quarterly encounter rates derived
from baseline monitoring data
|
Limit Level
|
Two consecutive
running quarterly^ (3-month) STG & ANI < low season quarterly
encounter rates derived from baseline monitoring data
|
Table 10‑3:
Derived Values of Action Level and Limit Level
|
NEL, NWL,
AW, WL and SWL as a Whole
|
Action Level
|
Running quarterly* STG < 1.86 & ANI < 9.35
|
Limit Level
|
Two consecutive running quarterly^ (3-month) STG < 1.86 & ANI
< 9.35
|
[Notes for Table 10-2 and Table 10-3:
*Action Level – running quarterly STG & ANI will be calculated from the
three preceding survey months; If both quarterly STG and ANI are lower than the
baseline values 1.86 and 9.35 respectively the AL will be triggered.
^Limit Level – two consecutive running quarterly encounter rates will be
reviewed; If both STG and ANI for two consecutive running quarters are lower
than the baseline values, the Limit Level will be triggered.]
10.5.2.6 The adoption of the
running quarter encounter rate approach will allow a short to medium term
response to events that may trigger the AL / LL after reviewing the monitoring
data for each month. This is preferable to the traditional quarterly encounter
rate approach whereby AL / LL may only be triggered after 3 to 4 months of
impact monitoring. Therefore, the running quarter encounter rate approach is
expected to be more effective in mitigating short term effects that may arise
from 3RS construction phase impacts.
10.5.2.7 The review of
encounter rates has been undertaken in the 1st annual EM&A report with full
year data collected covering the peak season encounter rates, and no update to
the Event and Action Plan for CWD was recommended. Should any updates to the
Event and Action Plan be required in subsequent annual review when more data
are available, agreement will be sought from the EPD / AFCD after certification
by the ETL and verification by the IEC prior to implementation of the updated
Event and Action Plan.
10.5.3 Event and Action Plan for CWD
10.5.3.1 Details of events
and actions corresponding to the AL and LLs are presented in Table
10-4.
Table 10-4:
Event and Action Plan for CWD
Event
|
Dolphin Expert / ETL
|
IEC
|
Action
AAHK / PM
|
Contractor
|
Action Level
|
1. Check monitoring data;
2. Repeat data analysis to confirm findings;
3. Review all available and relevant data covered in the
EM&A and the survey data collected at the Lantau waters, i.e. NWL, SWL,
WL and NEL to ascertain the exceedance is due to natural variation or works
related;
4. Identify source(s) of impact;
5. Inform the AAHK/ PM, IEC and Contractor;
6. Instruct an increase in the DEZ area to be monitored
from 250m to 500m for daytime works; and
7. Increase site inspection and audit frequency to ensure
all the dolphin protective and/or precautionary measures (e.g. consider
enhancing dolphin watch patrols, phasing of construction works, review of
construction methods, etc.) and other relevant measures are fully and
properly implemented.
|
1. Check monitoring data submitted by ET and the
Contractor;
2. Check the data review outcome by ET with the ETL; and
3. Conduct additional site inspection and audit with ET
to ensure all the dolphin protective measures are fully and properly
implemented and advise AAHK / PM the audit results and findings accordingly.
|
1. Discuss the need for increase site inspection and
audit frequency proposed by ET with the ETL, IEC, and the Contractor; and
2. Check the audit results and findings from ET and IEC.
|
1. Inform the AAHK /PM and confirm notification of the
non-compliance in writing;
2. Conduct site inspection and audit with the ETL and
IEC; and
3. Ensure all the dolphin protective measures are fully and
properly Implemented.
|
|
|
|
|
Limit Level
|
1. Check monitoring data;
2. Repeat statistical data analysis to confirm findings;
3. Review all available and relevant data covered in the
EM&A and the survey data collected at the Lantau waters, i.e. NWL, SWL, WL
and NEL to ascertain the exceedance is due to natural variation or project
related;
4. Identify source(s) of impact;
5. Inform the AAHK / PM, IEC and Contractor;
6. Repeat review with the Contractor representatives and
IEC to ensure all the dolphin protective measures are fully and properly
implemented and advise on additional measures if necessary;
7. Review previous occurrence of non-compliance events to
investigate if there is a longer term trend that needs attention; and
8. ET provides evidence of the suspected source of impact
that may be caused by any of the construction activity under works contracts
of the project, ET arranges a meeting to discuss with AAHK / PM, IEC and
Contractors on the need for further monitoring and/or any other potential mitigation
measures (e.g. consider modified design, or consider controlling or
temporarily stopping relevant marine works etc.), consultation with EPD and
AFCD and submit to IEC any proposal on additional dolphin monitoring and/or
mitigation measures for certification where necessary.
|
1. Check monitoring data submitted by ET and Contractor;
2. Discussing monitoring results and findings with the
ET, Dolphin Experts and the Contractor;
3. Review with the Contractor representatives and ET to
ensure all the dolphin protective measures are fully and properly
implemented;
4. Discuss further mitigation measures with AAHK / PM, ET
and Contractor;
5. Review proposals for additional monitoring and any
other mitigation measures submitted by ET and Contractor and advise AAHK / PM
of the results and findings accordingly; and
6. Supervise / audit the implementation of additional
monitoring and/or any other mitigation measures and advise AAHK / PM the results
and findings accordingly.
|
1. Convene an expert panel involving IEC (and dolphin
experts), EPD and AFCD to review the situation and determine any necessary
actions based on the options / mitigation details as proposed by the ET/
Contractors.
2. Discuss further mitigation measures with the ET, IEC
and Contractor; and
3. Supervise the implementation of additional monitoring
and/or any other mitigation measures.
|
1. Inform the AAHK/ PM and confirm notification of the
non-compliance in writing;
2. Discuss further mitigation measures with the ETL, IEC
and AAHK / PM;
3. Review with ET and IEC again to ensure all the dolphin
protective measures are fully and properly implemented and carried out
additional measures when advised by ET and agreed by AAHK / PM and IEC;
4. Jointly submit with ET to IEC and expert panel a
proposal of additional dolphin monitoring and/or any other mitigation
measures when necessary; and
5. Implement the agreed additional dolphin monitoring
and/or any other mitigation measures.
|
10.6 Ecological
Audit Requirement
10.6.1 Baseline, Construction and
Post-Construction Phases
10.6.1.1 Specific marine
ecological mitigation and precautionary measures are proposed for the
construction phase in the EIA Report. The Project Design Team and
Contractor should be responsible for the design and implementation of these
measures under the supervision of the AAHK / PM and monitored by the ET.
The implementation schedule of the recommended ecological mitigation measures
is presented in Appendix
C. The key construction phase mitigation and precautionary measures for
the CWDs are:
● Acoustic decoupling of noisy
construction equipment – Air compressors and other noisy equipment (i.e. generators and winch
generators) that must be mounted on construction vessels will be
acoustically-decoupled to the greatest extent as feasible, for instance by
using noise isolation pad. These noise isolation pad should be made of
materials having a density in excess of 250 kg/m3 of thickness at least
24mm with vibration absorbing efficiency of at least 10 dB;
● Construction vessel speed limits,
predefined vessel routing and skipper training – A “Marine Travel Routes and Management Plan for Construction and
Associated Vessels” has been prepared by the ET and submitted to the relevant
Authority according to EP Condition 2.9 no later than 3 months prior to the
commencement of construction for approval, to define the routings for
construction vessels within Hong Kong waters;
● Dolphin Exclusion Zones – DEZ will be implemented during
certain marine construction works known to be very noisy (e.g. ground
improvement, water jetting works for submarine cables diversion, open trench
dredging at the field joint locations and seawall construction, etc.). Details
of the actual marine construction activities that require the implementation of
DEZ will be determined in the DEZ Plan when the detailed design of the
construction works are available;
● Spill response plan – According to EP Condition 2.16, a
Spill Response Plan has been submitted by the ET no later than 3 months before
the commencement of construction of the project; and
● SkyPier high speed ferries’ speed
and routing restrictions – According to EP Condition 2.10, a Marine Travel Routes and Management
Plan for High Speed Ferries of SkyPier has been submitted by the ET no later
than 3 months before the commencement of construction of the project.
10.6.1.2 Further details are
provided in the Implementation Schedule provided in Appendix
C.
10.6.1.3 In addition to the
above measures, the EP Condition 2.11 also require the Project Proponent to submit
a Marine Mammal Watching Plan no later than 3 months before the commencement of
reclamation related marine works or works involving deployment of silt curtains
of the project.
10.6.1.4 During the
pre-construction, construction phase and post-construction phases the
Contractors will be required to undertake the following ecological measures of
the recommended EIA mitigation and precautionary measures, while the ET will
conduct the ecological monitoring and conduct regular site inspection to review
the implementation of mitigation measures. The IEC will be required to conduct
regular site audit and to verify the submissions and findings prepared by the
ET:
● Implementation of acoustic
decoupling for land formation works and the vessel restrictions requirements,
as provided by the specifications prepared prior to commencement of marine
construction works;
● Implementation of the DEZ during
marine works in accordance with the specifications prepared by the ET prior to
commencement of marine construction works;
● The ET shall review and submit the
“Marine Travel Routes and Management Plan for Construction and Associated
Vessels”, to be verified by the IEC, no later than 3 months before the
commencement of construction of the project and audit the construction vessel
adherence to this specification. During the construction phase, the ET is
required to review the specific Plan submitted by the Contractors regularly,
where necessary, the Plan shall be reviewed to reflect the marine travel routes
arrangement of the construction and associated vessels in different phases of
the marine works;
● The ET shall review and submit the Spill Response
Plan, to be verified by the IEC, no later than 3 months before the commencement of construction of the
project;
● The ET shall review and submit the “Marine Travel
Routes and Management Plan for High Speed Ferries of SkyPier”, to be verified
by the IEC, no later than 3 months before the commencement of construction of
the project. The ET is required to audit the
compliance of SkyPier high speed ferries’ speed and routing restrictions in
accordance with the Plan. A review report on the effectiveness of the proposed
mitigation measures on CWD will be provided to ACE summarising and analysing
the data gathered from the initial 6 months of SkyPier HSF Plan implementation.
During the construction phase, the ET is required to review the Plan regularly,
where necessary, the Plan shall be reviewed to reflect the marine travel routes
arrangement of the SkyPier HSF with an aim to minimise the impact on the CWD
hotspot;
● The ET shall conduct the pre-construction coral
dive survey at the artificial seawall at northern and northeastern airport
island, and the daylighting location at Sha Chau if there are any marine works
with potential to affect coral colonies is identified by the ET to check the
status of Balanophyllia sp. and other coral species and review the
feasibility of translocation. A pre-construction coral dive survey plan and
report will be prepared by the ET according to EP Condition 2.12 and verified
by the IEC for agreement with the Authority. A coral translocation plan shall
be submitted no later
than 3 months before the commencement of construction works (See Section 10.2.2);
● The ET is required to conduct the baseline,
construction and post-construction phase dolphin monitoring and the findings to
be verified by the IEC (see Section 10.2.4);
● The ET is required to audit the actual numbers of
HSFs operating from SkyPier after the HZMB and HKBCF commence operations during
construction phase by review of information obtained from the SkyPier
operators, including the AIS vessel tracking data; and
● The ET is required to conduct cumulative assessment
on CWD for construction phase in an annual basis by using the monitoring data
collected from the vessel based, land-based and underwater acoustic monitoring
(see Section 10.2.6).
10.6.2 Operational Phase
10.6.2.1 Specific mitigation
measures and precautionary measures for marine ecology during the operation
phase will be implemented by AAHK. The implementation schedule of the
recommended ecological mitigation measures is presented in Appendix
C. The key operation phase mitigation measures and precautionary
measures for the marine ecology are:
● Compensation of a Marine Park of size
around 2,400 ha to connect between the existing SCLKCMP and BMP for the loss of
marine habitats in northern Lantau waters. AAHK shall submit a Marine Park
Proposal, establishment of Marine Ecology Enhancement Fund and Submission of
Marine Ecology Conservation Plan according to EP Conditions 2.7 and 2.8
respectively no later than 3 months before the commencement of reclamation
related marine works of the project;
● Chemical/ Oil spill response plan;
and
● SkyPier high speed ferries’ speed
and routing restrictions.
10.6.2.2 During the
operational phase, the ET will be required to undertake the following
ecological audit measures of the recommended EIA mitigation measures for a
period of 12 months. The IEC will be required to verify the findings of the ET
audits.
● Audit the Spill Response Plan once
every 6 months for a period of one year; and
● Audit the SkyPier high speed
ferries’ speed and routing restrictions in accordance with the latest updated Marine Travel Routes and Management
Plan for High Speed Ferries of SkyPier for once every 3 months for a period of one year.
10.6.2.3 During the
operational phase, the ET will be required to conduct the operational phase CWD
monitoring, with the detailed monitoring plan (with reference to Section
10.2.4) submit to EPD in consultation with AFCD 3 months prior to the
completion of project construction.
11
Fisheries Impact
11.1
Introduction
11.1.1.1
The EIA Report conducted for the 3RS
indicated there will be temporary and permanent loss of fisheries habitats (and
resources) and fishing ground upon completion of construction of land formation
and associated marine works. The sites of fisheries importance including the
Brothers Marine Park (BMP), SCLKCMP and the spawning ground for commercial
fisheries resources in northern Lantau may also be affected indirectly during
the construction and operational phases, as a result of change in water quality
and hydrodynamics effect. A suite of mitigation measures for water quality has
been proposed in the EIA Report, which could also minimise the impact on
fisheries resources and fishing ground. Apart from this, a new marine protected
area is proposed which will be connected with the existing SCLKCMP to the
north, the BMP to the east, the marine mammals conservation area at the
Mainland waters to the west, with the extended HKIAAA as fisheries no-take
zone.
11.1.1.2
The EIA Report has concluded that,
with the implementation of the recommended water quality mitigation measures
and proposed establishment of new Marine Park to compensate the permanent loss
of fisheries habitats (and resources) and fishing ground, no adverse residual
impact on fisheries is anticipated. Apart from the above mitigation measures,
the consideration of alternative construction methods e.g. use of non-dredge
ground improvement methods by DCM would also reduce the potential release of
contaminant to the water column and reduce the indirect impact on fisheries
resources. Water quality monitoring and audit has been proposed at locations
covering sites of fisheries importance during construction and operation phases
to monitor the effectiveness of the proposed mitigation measures, thus fisheries
specific monitoring is considered not necessary.
11.1.1.3 The Fisheries Management Plan has been submitted no
later than 3 months before the commencement of reclamation related marine works
of the project in accordance to EP Condition 2.13.
11.2
Mitigation Measures
11.2.1.1
Recommended mitigation measures for
water quality that would minimise the impacts on fisheries habitats (and
resources), fishing ground and fisheries activities are proposed for the
construction phase in the EIA Report. The Project Design Team and
Contractor should be responsible for the design and implementation of these
measures under the supervision of the AAHK / PM and monitored by the ET.
The implementation schedule of the recommended water quality mitigation measures
is presented in Appendix
C. Key operation phase mitigation measure for the fisheries is the
establishment of a Marine Park of size around 2,400 ha for the loss of
fisheries habitats (and resources) and fishing ground in northern Lantau
waters.
12
Landscape and Visual Impact
12.1
Introduction
12.1.1.1
The EIA Report has recommended the
EM&A for landscape and visual resources is undertaken during both the
construction and operational phases of the project. The implementation and
maintenance of landscape compensatory planting measures is a key aspect of this
and shall be checked to ensure that they are fully realised and that potential
conflicts between the proposed landscape measures and any other project works
and operational requirements are resolved at the earliest possible date and
without compromise to the intention of the mitigation measures. In addition,
implementation of the mitigation measures recommended by the EIA Report shall
be monitored through the construction phase site audit programme.
12.2
Baseline Monitoring
12.2.1.1 Baseline monitoring for the landscape
and visual resources comprise a one-off survey was conducted within the project
site boundary prior to commencement of construction works. The commencement
date of baseline monitoring has been agreed between the ET / IEC / AAHK / PM to
ensure timely submission of the baseline monitoring report to EPD and relevant
authorities.
12.2.1.2 This includes a
vegetation survey of the entire site area and within compounds undertaken on an
“area” basis. Representative vegetation types were identified along with
typical species composition. An assessment of landscape character was made
against which future change can be monitored. The landscape resources and
elements of particular concern are noted.
12.2.1.3 A photographic
record of the site at the time of the contractor’s possession of the site shall
be prepared by the contractor and approved by the AAHK / PM. The approved
photographic record shall be submitted to the AAHK / PM, ET, IEC and EPD for record.
12.2.1.4 The landscape and
visual baseline has been determined with reference to the Landscape Resources
and Landscape Character Area maps included in the EIA Report.
12.3
Mitigation Measures
12.3.1.1 The following mitigation measures are
proposed to avoid and reduce the identified impacts during the construction
stage and are illustrated in Drawing
MCL/P132/EMA/12-001.1 to MCL/P132/EMA/12-001.6:
● The construction area and contractor’s
temporary works areas shall be minimised to avoid impacts on adjacent landscape
(CM1);
● Reduction of construction period to
practical minimum (CM2);
● Phasing of the construction stage to
reduce visual impacts during the construction phase (CM3);
● Construction traffic (land and sea)
including construction plants, construction vessels and barges shall be kept to
a practical minimum (CM4);
● Erection of decorative mesh screens
or construction hoardings around works areas in visually unobtrusive colours (CM5);
● Avoidance of excessive height and
bulk of site buildings and structures (CM6);
● Control of night-time lighting by
hooding all lights and through minimisation of night working periods (CM7);
● All existing trees shall be
carefully protected during construction. Detailed Tree Protection
Specification shall be provided in the Contract Specification. Under this
specification, the Contractor shall be required to submit, for approval, a
detailed working method statement for the protection of trees prior to
undertaking any works adjacent to all retained trees, including trees in
contractor’s works areas (CM8);
● Trees unavoidably affected by the
works shall be transplanted where practical. A detailed Tree
Transplanting Specification shall be provided in the Contract Specification, if
applicable. Sufficient time for necessary tree root and crown preparation
periods shall be allowed in the project programme (CM9); and
● Land formation works shall be
followed with advanced hydroseeding around taxiways and runways as soon as
practical (CM10).
12.3.1.2 The following mitigation measures are
proposed to remedy and compensate unavoidable impacts during the operation phase
(it should be noted that while the benefits of these mitigation measures will
be felt in the operation phase, many of the measures are implemented either
partially or entirely in the design phase):
● Sensitive landscape design of
reclamation edge by incorporating different angles of gradient and the use of a
range of armour rock sizes placed randomly in a riprap approach for an
irregular appearance. Planting of native coastal plants shall be incorporated (OM1);
● All above ground structures, including,
Vent Shafts, Emergency and Firemen’s’ Accesses etc. shall be, either fully
integrated with the planned buildings, or sensitively designed in a manner that
responds to the existing and planned urban context, and minimises potential
adverse landscape and visual impacts (OM2);
● Sensitive design of buildings and
structures in terms of scale, height and bulk (visual weight) (OM3);
● Use appropriate building materials
and colours in built structures to create cohesive visual mass (OM4);
● Lighting units to be directional and
minimise unnecessary light spill and glare (OM5);
● Greening measures, including
vertical greening, green roofs, road verge planting and peripheral screen
planting shall be implemented (OM6);
● Compensatory Tree Planting for all
felled trees shall be provided to the satisfaction of relevant Government
departments. Required numbers and locations of compensatory trees shall
be determined and agreed separately with Government during the Tree Felling
Application process under the relevant technical circulars (OM7);
● Streetscape (e.g. paving, signage,
street furniture, lighting etc.) shall be sensitively designed in a manner that
responds to the existing and planned urban context, and minimises potential
adverse landscape and visual impacts (OM8);
● All streetscape areas and hard and
soft landscape areas disturbed during construction shall be reinstated to equal
or better quality (due to implementation of screen planting, road verge
planting etc.), to the satisfaction of the relevant Government departments (OM9);
● Aesthetic improvement planting of
viaduct structure through greening of structure to mitigate visual impact of
viaduct form (OM10); and
● Sensitive design of footbridges,
noise barriers and enclosures with greening (screen planting / climbers /
planters) and chromatic measures (OM11).
12.3.1.3 The operation phase measures listed
above shall be adopted during the detailed design, and be built as part of the
construction works so that they are in place at the date of commissioning of
the 3RS (as stated in Section 12.3.1.2 above).
12.4
Environmental
Monitoring and Audit Requirements
12.4.1.1 An approved landscape contractor shall
be employed by the contractor for the implementation of landscape construction
works and subsequent maintenance operations during the 12-month establishment
period. The establishment works shall be undertaken throughout the contractor’s
one-year maintenance period which will be within the first operation year of
the project.
12.4.1.2 All measures
undertaken by both the contractor and the landscape contractor during the
construction phase and first year of the operation phase shall be audited by a
landscape architect, as a member of the ET, on a regular basis to ensure
compliance with the intended aims of the measures. Site inspections shall be
undertaken at least once every two months during the operation phase.
12.4.1.3 The broad scope of
the audit is detailed below. Operation phase auditing will be restricted to the
12-months establishment works of the landscaping proposals, with the AAHK / PM
taking over the maintenance and monitoring after this period, and thus only the
items below concerning this period are relevant to the operation phase:
● The extent of the agreed works areas
shall be regularly checked during the construction phase. Any trespass by the
contractor outside the limit of works, including and damage to existing trees
and woodland all noted and remedial action determined;
● The progress of the engineering
works all be regularly reviewed on site to identify the earliest practical
opportunities for the landscape works to be undertaken;
● All existing trees and vegetation within
the study area which are not directly affected by the works shall be retained
and protected;
● The methods of protecting existing vegetation
proposed by the contractors shall be acceptable and enforced;
● All landscaping works shall be
carried out in accordance with the specifications;
● The planting of trees and shrubs
shall be carried out properly and within the right season as far as practical;
● The species and mix of the new trees
and shrubs to be planted shall suitable; and
● The newly planted trees and grasses
areas shall be maintained throughout the establishment period, particularly in
respect of the following:
– Regular watering, weeding and
fertilising of all trees and shrub planting and areas of grass reinstatement;
– Regular grass cutting for reinstated
areas;
– Firming up of trees after periods of
strong winds;
– Regular checks for eradication of
pests, fungal infection, etc.;
– Pruning of dead or broken branches;
and
– Prompt replacement of dead plants
and regressing of failed areas of grass.
12.4.1.4 The Landscape and Visual Plan shall be submitted no
later than 3 months before the commencement of construction works on the formed
land of the project in accordance to EP Condition 2.18.
12.5
Monitoring Programs
12.5.1.1 The design, implementation and maintenance
of landscape and visual mitigation measures shall be checked to ensure that any
potential conflicts between the proposed landscape measures and any other works
for the project would be resolved as early as practical without affecting the
implementation of the mitigation measures.
12.5.1.2 Site inspection and
audit shall be undertaken as necessary in the construction and operation
phases.
Table 12‑1: Monitoring Programme for Landscape
and Visual
Stage
|
Monitoring Task
|
Monitoring Report
|
Form of Approval
|
Frequency
|
Detailed Design
|
Checking of design works against the recommendations
of the landscape and visual impact assessments within the EIA shall be
undertaken during detailed design and tender stage, to ensure that they
fulfil the intention of the mitigation measures. Any changes to the design,
including design changes on site shall also be checked.
|
Report by AAHK / PM confirming that the design
conforms to requirements of EP.
|
Approved by Client
|
At the end of the Detailed Design Phase
|
Construction
|
Checking of the contractor’s operations during the
construction period.
|
Report on Contractor's compliance, by ET
|
Counter signature of report by IEC
|
Weekly
|
Establishment Works
|
Checking of the planting works during the twelve-month
Establishment Period after completion of the construction works.
|
Report on Contractor's compliance, by ET
|
Counter signature of report by IEC
|
Every two months
|
Long Term Management (10 year)
|
Monitoring of the long-term management of the planting
works in the period up to 10 years after completion of the construction
works.
|
Report on
Compliance by ET or Maintenance Agency as appropriate
|
Counter signature of report by Management Agency
|
Annually
|
12.6
Construction Phase & Establishment Period
12.6.1.1 An implementation
programme will be prepared as required by EIAO-TM. Reference will be made to
the ETWB TC(W) No. 2/2004 on Maintenance of Vegetation and Hard Landscape
Features which defines the management and maintenance responsibilities for
natural vegetation and landscape works, including both soft works and hard
works, and authorities for tree preservation and felling. The format of the
preliminary arrangement of implementation programme is listed in Table 12‑2 below.
Table 12‑2:
Preliminary Funding, Implementation, Management and Maintenance Proposal
Landscape and Visual Mitigation Measure ID No.
|
Funding Agency
|
Implementation Agency
|
Management
Agency
|
Maintenance
Agency
|
Construction Phase
|
CM1 – CM10
|
AAHK
|
Contractor
|
-
|
-
|
Operation Phase
|
OM1, OM5, OM8, OM10, OM11
|
AAHK
|
Design Engineer
|
AAHK
|
AAHK
|
OM2 – OM4
|
AAHK
|
Design Engineer
|
Building Operator
|
Building Operator
|
OM6, OM7, OM9
|
AAHK
|
Contractor
|
AAHK
|
AAHK
|
12.6.1.2 The implementation
of landscape construction works and subsequent maintenance operations during
the 12-month establishment period must be supervised by a qualified Landscape
Resident Site Staff (Registered Landscape Architect or Professional Member of
the Hong Kong Institute of Landscape Architects).
12.6.1.3 Measures to
mitigate landscape and visual impacts during construction shall be checked and
monitored by a Registered Landscape Architect to ensure compliance with the
intended aims of the measures.
12.6.1.4 The progress of the
engineering works shall be regularly reviewed on site to identify the earliest
practical opportunities for the landscape works to be undertaken.
12.6.1.5 The planting works
shall be monitored during the first 10 years of the operation phase of the
project. Any areas of vegetation which fails to establish, shall be corrected
by the relevant management and maintenance parties at the earliest opportunity.
The maintenance requirement of the planting works stated under the Ten-Year
Management Programme is included in the monitoring requirement.
12.7
Event
and Action Plan
12.7.1.1
Should non-compliance of the landscape and visual impacts occur, actions
in accordance with the Event and Action Plan stated in Table 12‑3 below shall be carried out.
Table 12‑3:
Event and Action Plan for Landscape and Visual
Event Action Level
|
Action
|
ET
|
IEC
|
AAHK / PM
|
Contractor
|
Design Check
|
Check final design conforms to the requirements of EP
and prepare report.
|
Check report.
Recommend remedial design if necessary.
|
Undertake remedial if design necessary.
|
|
Non-conformity on one occasion
|
Identify source.
Inform AAHK / PM and IEC.
Discuss remedial actions with AAHK / PM, IEC and
Contractor.
Monitor remedial actions until rectification has been
completed.
|
Check report.
Check Contractor’s working method.
Discuss with ET and Contractor on possible remedial
measures.
Advise AAHK / PM on effectiveness of proposed remedial
measures.
Check implementation of remedial measures.
|
Notify Contractor.
Ensure remedial measures are properly implemented.
|
Amend working methods to prevent recurrence of
non-conformity.
Rectify damage and undertake additional action
necessary.
|
Repeated Non-conformity
|
Identify source.
Inform AAHK / PM and IEC.
Increase monitoring frequency.
Discuss remedial actions with AAHK / PM, IEC and
Contractor.
Monitor remedial actions until rectification has been
completed.
If non-conformity stops, cease additional monitoring.
|
Check monitoring report.
Check Contractor’s working method.
Discuss with ET and Contractor on possible remedial
measures.
Advise AAHK / PM on effectiveness of proposed remedial
measures.
Supervise implementation of remedial measures.
|
Notify Contractor.
Ensure remedial measures area properly implemented.
|
Amend working methods to prevent recurrence of
non-conformity.
Rectify damage and undertake additional action
necessary.
|
|
13
Cultural Heritage
13.1.1.1
No environmental monitoring and audit
is required for marine archaeology or terrestrial cultural heritage.
14
Environmental Auditing
14.1
Site
Inspection
14.1.1.1
Site inspections provide a direct
means to trigger and enforce the specified environmental protection and
pollution control measures. They should be undertaken routinely by the ET to
inspect the construction activities in order to ensure that appropriate
environmental protection and pollution control mitigation measures are properly
implemented. With well-defined pollution control and mitigation specifications
and a well-established site inspection, deficiency and action reporting system,
the site inspection is one of the most effective tools to enforce the
environmental protection requirements on the construction site.
14.1.1.2
The ETL is responsible for
formulating the environmental site inspection and auditing, deficiency and
action reporting system, and for carrying out the site inspection works. He
should prepare a proposal for site inspection and deficiency and action
reporting procedures to the IEC for agreement, and to AAHK / PM for approval.
The Contractor’s proposal for rectification would be made known to the AAHK /
PM and IEC.
14.1.1.3
Regular site inspections led by the
ETL should be carried out at least once per week. The areas of inspection
should not be limited to the environmental situation, status of implementation
of pollution control and mitigation measures within the construction works
areas; it should also review the environmental situation outside the project
sites which is likely to be affected, directly or indirectly, by the site
activities. The ET should make reference to the following information in
conducting the inspection:
● The EIA and EM&A recommendations
/ assumptions on environmental protection and pollution control mitigation
measures;
● The EP conditions and any approval
plans / submissions under the EP, any subsequent VEP FEP;
● On-going results of the EM&A
programme;
● Works progress and programme;
● Individual works methodology
proposals (which should include proposal on associated pollution control
measures);
● Contract specifications on
environmental protection;
● Relevant environmental protection
and pollution control laws; and
● Previous site inspection results.
The ET should evaluate
the overall performance of the implementation of the recommendations in the EIA
Report and ensure the appropriate control measures are properly implemented. A
summary of recommendations on environmental protection and pollution control
mitigation measures of the EIA Report is provided in Appendix
C.
14.1.1.4
The ET and IEC shall monitor and
check the Contractors’ / Operators for SkyPier HSF implementation of the
relevant measures, actions, programmes and/or recommendations as given in
approved EP submissions, including but not limited to the following:
● Marine Park Proposal;
● Marine Travel Routes and Management
Plan for Construction and Associated Vessels;
● Marine Travel Routes and Management
Plan for High Speed Ferries of SkyPier;
● Marine Mammal Watching Plan;
● Coral Translocation Plan;
● Egretry Survey Plan;
● Silt Curtain Deployment Plan;
● Spill Response Plan;
● Detailed Plan of DCM;
● Landscape and Visual Plan;
● Waste Management Plan;
● Plans related to land contamination
and remediation of contaminated land, if any; and
● Relics and Antiques Rescue Plan if
any.
14.1.1.5
The ET should monitor and check the
Contractors’ implementation of the DEZ, marine mammal watching and the vessel
skippers’ implementation of safe vessel operations in the presence of CWDs.
14.1.1.6
The Contractor should keep the ETL
updated with all relevant information on the construction contract necessary
for him to carry out the site inspections. Inspection results and associated
recommendations for improvements to the environmental protection and pollution
control works should be submitted to the IEC and the Contractor within 24-hours
for reference and for taking immediate action. The Contractor should follow the
procedures and time-frame stipulated in the environmental site inspection, and
the deficiency and action reporting system formulated by the ETL, to report on
any remedial measures subsequent to the site inspections.
14.1.1.7
The ET should also provide advice to
the Contractors on environmental improvement, awareness and on-site enhancement
measures and review of latest site inspection and audit results against the
previous results and flag up any persistent non-conformities or poor performing
areas to the AAHK / PM and IEC.
14.1.1.8
The ET and IEC should also carry out ad
hoc site inspections if significant environmental problems are identified.
Inspections may also be required subsequent to receipt of an environmental
complaint, or as part of the investigation work.
14.2
Compliance
with Legal and Contractual Requirements
14.2.1.1
There are contractual environmental
protection and pollution control requirements as well as environmental
protection and pollution control laws in Hong Kong with which construction
activities must comply.
14.2.1.2
In order that the works are in
compliance with the contractual requirements, relevant sections (e.g. sections
related to environmental measures) of works method statements submitted by the
Contractor to AAHK / PM for approval should be sent to the ETL for vetting to
see whether sufficient environmental protection and pollution control measures
have been included.
14.2.1.3
The ETL should also keep himself
informed of the progress and programme of the works to check that relevant
environmental laws have not been violated, and that any foreseeable potential
for violation can be prevented.
14.2.1.4
The Contractor should regularly copy
relevant documents to the ETL so that works checking can be carried out. The
document should at least include the updated Works Progress Reports, updated
Works Programme, any application letters for different licences / permits under
the environmental protection laws, and copies of all valid licences / permits.
The site diary should also be made available for the ETL’s inspection upon his
request.
14.2.1.5
After reviewing the documentation,
the ETL should advise the Contractor of any noncompliance with contractual and
legislative requirements on environmental protection and pollution control for
them to take follow-up actions, including any potential violation of
requirements.
14.2.1.6
Upon receipt of the advice, the
Contractor should undertake immediate action to correct the situation. AAHK / PM
should follow up to ensure that appropriate action has been taken in order to
satisfy contractual and legal requirements.
14.3
Checklist
of Key EIA Assumptions
14.3.1.1
A checklist of key assumptions
adopted in the EIA Report, including those that have become part of the EP
conditions, is provided in Appendix
E.
14.3.1.2
During the construction phase, the ET
should perform monthly review of the relevant key EIA assumptions in the
checklist to determine whether the assumptions remain valid. If any significant
changes in the key EIA assumptions that would affect the EIA findings are
identified, the ET should inform the AAHK/ PM and IEC, and propose suitable
follow-up actions/ further investigation within 24 hours or next working day
for approval by the AAHK/ PM and IEC. The findings of monthly review of the
relevant key EIA assumptions should be summarised in the monthly EM&A reports.
14.3.1.3
During the operation phase, it is
proposed that AAHK should carry out the first review of the relevant key EIA
assumptions after the first year of operation of the 3RS and then the
subsequent reviews at least every five years during the first 20 years of
operation of the project. If any significant changes in the key EIA assumptions
that would affect the EIA findings are identified, AAHK will study the
implications of the identified changes to the EIA findings and where necessary
propose follow-up actions/ further investigation accordingly.
14.4 Environmental Complaints
14.4.1.1
In accordance with EP Condition 2.1,
a Complaint Management Plan has been submitted to EPD no later than 3 months
before the commencement of construction of the project. The Complaint
Management Plan specifies a dedicated complaint hotline and an email channel
for timely response to complaints, and describes the complaint management
process.
14.4.1.2
The Complaint Management Plan also
specifies the handling of environmental complaints received from other
communication channels such as via the Community and Professional Liaison
Groups (CLG and PLG). All written complaints received from such other channels
will be passed directly to the ET for handling in accordance with the Complaint
Management Plan. For any questions or comments received from CLG / PLG members
during CLG / PLG meetings, these will be responded directly in the meetings or
in subsequent CLG / PLG meetings. For any other non-written complaints, the
complainant will be referred to the dedicated complaint hotline and/or email
channel for registering their complaint.
14.4.1.3
The ET has set up and managed the
dedicated complaint hotline and email channel in accordance with EP Condition
2.1 and the Complaint Management Plan.
14.4.2 Dedicated Complaint Hotline and
Email Channel for the Project
14.4.2.1
The ET established both the dedicated
complaint hotline and email channel for receiving any public comments. The ET
has set up and managed both the mailing address and fax number in order to
receive written environmental comments raised up by the public. These channels
are publicised on the dedicated project website. Table 14-1
shows the information of all the aforesaid channels.
Table 14-1:
Environmental Complaint Channels
Environmental Complaint Channels
|
Details
|
Dedicated Hotline Number
|
+852 3908 0354
|
Fax Number
|
+852 3747 6050
|
Dedicated Email Address
|
env@3rsproject.com
|
Mailing Address
|
Airport Authority Hong Kong
HKIA Tower, 1 Sky Plaza Road
Hong Kong International Airport
Lantau, Hong Kong
(Attn: Environmental Team Leader Mr Terence Kong
c/o Mr Lawrence Tsui (Third Runway Division)
|
Dedicated Project Website Address
|
http://env.threerunwaysystem.com
|
14.4.3 Environmental Complaint Procedures
14.4.3.1
All complaints should be referred to
the ET for actions. The ET should follow the procedures specified in the Complaint
Management Plan to record, investigate and report on the findings of the
complaint investigation. Details of the complaint procedures include the
following:
● The ET shall record the details of
the environmental complaint and the details of the complainant (if provided by
the complainant);
● The ET shall log the details of
environmental complaint in the complaint log-book;
● The ET shall inform the AAHK / PM
and IEC immediately and refer the environmental complaint to relevant Contractors
and other parties where applicable;
● The ET shall issue an interim reply
within 3 working days to acknowledge receipt and notify the complainant of the
referral of their complaint to the relevant parties where appropriate;
● The Contractor shall provide
information related to the construction activities and site conditions
surrounding the date, time and location of the complaint to the ET for
investigation;
● The ET shall investigate the
complaint to determine its validity, and assess whether the source of the
problem is due to the construction activities of the project;
● The ET shall review the
environmental monitoring data and conduct additional environmental monitoring
if necessary;
● If the complaint is confirmed to be
valid and due to the construction works of the projects, the ET shall review
the effectiveness of the existing mitigation measures and identify any
additional mitigation measures needed in consultation with the IEC and AAHK /
PM;
● The Contractor shall check their
implementation of the mitigation measures as specified and required in the EIA
Report, the EM&A Manual, the EP and their works contracts, as well as any
other mitigation measures previously requested by, and agreed with, the AAHK /
PM, and agree with the ET and IEC on any additional mitigation measures /
corrective actions / preventive actions where necessary, for ensuring
environmental compliance and preventing similar environmental complaints in
future;
● The ET / IEC shall undertake
additional monitoring and audit to verify the updated situation and the
effectiveness of the additional mitigation measures / corrective actions, if
required;
● The ET shall compile the
environmental complaint investigation report containing all the relevant information
and responses from other parties and follow up actions taken (i.e. mitigation
measures and additional monitoring) for submission to the AAHK / PM and IEC;
● The ETL shall certify the
environmental complaint investigation report, and obtain the IEC’s verification
and AAHK / PM’s approval before submission of the report;
● Where comments on the environmental
complaint investigation report are received, the ET shall re-submit the
investigation report;
● Upon final acceptance of the
environmental complaint investigation report, the ET shall provide a written
response to the complainant. (except in cases where the complaint is referred
from EPD). The time that would take to investigate a complaint depends on the
circumstances involved and would be different for each individual case, but the
complainant will be contacted within 4 weeks from the receipt of the complaint
and provided with an update of the investigation, and will also be given the
investigation results when available. For cases where the complaint is referred
from EPD, the ET shall provide the final complaint investigation report
(certified by the ET and verified by the IEC) to EPD for their reply to the
complainant;
● The ET shall update the record of
the complaint investigation, follow up actions and other relevant information
of the complaint in the complaint log-book;
● The ET / IEC shall update their
records of environmental monitoring, mitigation measures and site inspection
and audit checklists to reflect any updates to the EM&A requirements
associated with follow up actions / additional measures resulting from the
environmental complaint investigation which needs to be implemented as part of
future works to prevent re-occurrence and ensure continued environmental compliance;
and
● The ET shall record the complaint,
investigation findings, follow up actions and the results in the monthly
EM&A reports.
14.4.3.2
The environmental complaint process
flow diagram is presented in Drawing No. MCL/P132/EMA/14-001.
14.4.3.3
During the complaint investigation
work, the Contractor and AAHK / PM should cooperate with the ET in providing all
necessary information and assistance for completion of the investigation. If
mitigation measures are identified as required during in the investigation by
the ET, the Contractor should promptly carry out the mitigation works. AAHK /
PM should ensure that the measures have been carried out by the Contractor.
14.4.4 Environmental Complaint Reporting
14.4.4.1
For every environmental complaint
that is confirmed to be valid and due to the project’s activities, the ET shall
compile an environmental complaint investigation report containing all the
relevant information and responses from other parties and the follow up actions
taken.
14.4.4.2
The key areas to be covered in the
environmental complaint investigation report include, but are not limited to the
following:
● Details of the complaint received
such as received channel, date, time etc.;
● Details of the complainant such as
name, contact number, email etc. (if known);
● Description of the complaint such as
date, time, location, complaint circumstances etc.;
● Details of the information from the
relevant Contractors and the investigation findings;
● Details of the mitigation measures,
additional monitoring and follow up actions where applicable; and
●
Recommendations to
prevent recurrence of similar complaint.
14.5 Environmental Log-book
14.5.1.1
The ETL keeps a contemporaneous
log-book of each and every instance or circumstance or change of circumstances,
which may affect the compliance with the recommendations of the EIA Report and
the EP. The ETL will notify the IEC within one working day of the occurrence of
any such instance or circumstance or change of circumstance. The ETL’s
log-book is kept readily available for inspection by all persons assisting in
supervision of the implementation of the recommendations of the EIA Report
(such as AAHK / PM, IEC and Contractor) and the EP or by EPD or his authorised
officers in accordance to EP condition 2.2. An environmental log-book sample is
shown in Appendix
D.
14.5.1.2
The IEC will verify the environmental
log-book. In accordance to EP condition 2.3, the IEC will notify the EPD by
fax, within one working day of receipt of notification from the ETL of each and
every change of circumstances or non-compliance with the recommendations of the
EIA Report and the EP, which might affect the monitoring or control of adverse
environmental impacts from the project.
15
Reporting
15.1
Introduction
15.1.1.1
The reporting requirements of
EM&A are based upon a paper-documented approach. However, the same information
can be provided in an electronic medium upon agreeing the format with the AAHK
/ PM, IEC and EPD (for construction phase), and with AAHK / PM and EPD (for
operation phase). This would enable a transition from a paper / historic and
reactive approach to an electronic / real time proactive approach.
15.1.1.2
The types of reports that the ETL
should prepare and submit include baseline monitoring report, monthly EM&A
report, quarterly EM&A report, annual EM&A report and final EM&A
review report. In accordance with Annex 21 of the EIAO-TM, a copy of the
monthly, quarterly summary and final review EM&A reports should be
submitted to the EPD. The exact details of the frequency, distribution and time
frame for submission should be agreed with the AAHK / PM, IEC and EPD prior to
commencement of works.
15.1.1.3
The monthly EM&A Reports shall
include a summary of all non-compliance (exceedances) of the environmental
quality performance limits i.e., Action and Limit Levels. The monthly
EM&A Reports shall also present a summary of the implementation status of
the environmental protection, pollution control, mitigation measures and
associated EM&A requirements, as recommended in the EIA Report and/or the
relevant submissions made under the EP.
15.1.1.4
All environmental monitoring and
audit data and results should be provided to the public through a dedicated
website no later than two weeks after such information is available.
15.2
Baseline
Monitoring Reports
15.2.1.1
The ETL should prepare and submit 4
hard copies and 1 electronic copy of relevant Baseline Monitoring Reports to
EPD at least two weeks prior to commencement of construction works, except for
the Baseline Monitoring Report on Water Quality and Chinese White Dolphin which
shall be submitted at least two weeks prior to commencement of marine works.
The Baseline Monitoring Reports should be certified by the ETL and verified by
the IEC prior to submission. Copies of the Baseline Monitoring Reports should
be made available to the Contractor, the AAHK / PM and IEC. The ETL should
liaise with the relevant parties on the exact number of copies they require.
The report format and baseline monitoring data format should be agreed with the
AAHK / PM, IEC and EPD prior to submission.
15.2.1.2
The Baseline Monitoring Reports
should include at least the following:
i.
Up to half a page of
executive summary
ii.
Brief project
background information
iii. Drawings showing locations of the baseline
monitoring stations
iv. An updated construction programme
with milestones of environmental protection / mitigation activities annotated
v.
Monitoring results (in
both hard and diskette copies) together with the following information:
– Monitoring methodology
– Name of laboratory and types of
equipment used and calibration details
– Parameters monitored
– Monitoring locations (and depth,
where relevant)
– Monitoring date, time, frequency and
duration
– QA / QC results and detection limits
vi. Details of influencing factors,
including:
– Major activities, if any, being
carried out on the site during the period / monitoring
– Weather conditions during the period
/ monitoring
– Other factors which might affect
results
vii. Determination of the Action and
Limit Levels for each monitoring parameter and statistical analysis of the
baseline data, the analysis should conclude if there is any significant
difference between control and impact stations for the parameters monitored
viii. Revisions for inclusion in the
EM&A Manual
ix. Comments and conclusions
15.3
Monthly EM&A Reports
15.3.1.1
The results and findings of all
EM&A work carried out during the month should be recorded in the monthly
EM&A reports prepared by the ETL. 4 hard copies and 1 electronic copy of
EM&A report should be prepared and submitted to EPD within two weeks after
the end of each reporting month. The report should be certified by the ETL and
verified by the IEC prior to submission. Copies of monthly EM&A report
should be submitted to the following parties: AAHK / PM, IEC and the
Contractor. Before submission of the first EM&A report, the ETL should
liaise with the parties on the required number of copies and format of the
monthly reports in both hard copy and electronic medium.
15.3.1.2
The ETL should review the number and
location of monitoring stations and parameters every six months, or on as
needed basis, in order to cater for any changes in the surrounding environment
and the nature of works in progress.
15.3.2
First
Monthly EM&A Report
15.3.2.1
The first monthly EM&A report should
include at least but not be limited to the following:
i.
Executive summary (one
to two pages):
– Breaches of Action and Limit Levels
○
Summary of Action and Limit Levels exceedance, if any, at each
monitoring location
during the reporting period
– Complaint log
○
Summary of complaints
received in relation to the environmental impact during the reporting period
– Notifications of any summons and
status of prosecutions
○
Summary of notifications
of summons or prosecutions received during the reporting period.
– Changes made that affect the
EM&A
○
Summary of changes made
during the reporting period.
– Future key issues
○
List of the major site works
scheduled to be commissioned in the coming month after the reporting period.
ii.
Basic project
information:
– Project organisation including key
personnel contact names and telephone numbers
– Scope of works of the project
– Construction programme
– Works undertaken during the month
with illustrations (such as location of works etc.)
– Drawings showing the project area,
any environmental sensitive receivers and the locations of the monitoring and
control stations (with coordinates of the monitoring locations).
iii. A brief summary of EM&A
requirements including:
– All monitoring parameters
– Environmental quality performance
limits (Action and Limit Levels)
– Event-Action Plans
– Environmental mitigation measures,
as recommended in the EIA Report
– Review of the key assumptions
adopted in the EIA Report
– Environmental requirements in
contract documents
iv. Environmental status
– Advice on status of compliance with
environmental permit including the status of submissions under the
environmental permit
v.
Implementation status
– Implementation status of
environmental protection and pollution control / mitigation measures, as
recommended in the EIA Report
vi. Monitoring results (in both hard and
diskette copies) together with the following information:
– Monitoring methodology
– Name of laboratory and types of
equipment used and calibration details
– Parameters monitored
– Monitoring locations
– Monitoring date, time frequency, and
duration
– Weather conditions during the period
/ monitoring
– Graphical plots of the monitored parameters
in the month annotated against
–
The major activities
being carried out on site during the period
–
Weather conditions that
may affect the monitoring results
–
Any other factors which
might affect the monitoring results
–
QA / QC results and
detection limits
vii. Analysis of monitoring results,
non-compliance, complaints, and notifications of summons and status of
prosecutions:
– Analysis and interpretation of monitoring
results in the month
– Any non-compliance (exceedances) of
the environmental quality performance limits (Action and Limit Levels)
– Changes made that affect the
EM&A during the month
– Summary of environmental complaints
received including locations and nature of complaints, findings of the
investigation, actions and follow-up measures taken and final status
– Notification of summons and status
of prosecutions for breaches of current environmental protection / pollution
control legislation, including locations and nature of the breaches,
investigation, follow-up actions taken, results and summary
– Reasons for and the implications of
non-compliance, complaints, summons and prosecutions including review of
pollution sources and working procedures
– Actions taken in the event of
non-compliance and deficiency, and follow-up actions related to earlier
non-compliance
viii. Others
– An account of the future key issues
as reviewed from the works programme and work method statements
– Comment on the solid and liquid
waste management status during the month including waste generation and
disposal records
– Outstanding issues and deficiencies
– Comments on effectiveness of the
environmental management systems, practices, procedures and mitigation
measures, recommendations (for example, any improvement in the EM&A
programme) and conclusions
– Review of the relevant key EIA
assumptions
ix. Appendix
– Monitoring schedule for the present
and next reporting period
– Cumulative statistics on complaints,
notifications of summons and successful prosecutions
– Outstanding issues and deficiencies
15.3.3
Subsequent
Monthly EM&A Reports
15.3.3.1
The subsequent monthly EM&A
reports should include the following:
i.
Executive summary (one
to two pages):
– Breaches of Action and Limit Levels
○
Summary of Action and Limit Levels exceedance, if any, at each
monitoring location
during the reporting period
– Complaint log
○
Summary of complaints
received in relation to the environmental impact during the reporting period
– Notifications of any summons and
status of prosecutions
○
Summary of notifications
of summons or prosecutions received during the reporting period.
– Changes made that affect the
EM&A
○
Summary of changes made
during the reporting period.
– Future key issues
○
List of the major site
works scheduled to be commissioned in the coming month after the reporting
period.
ii.
Environmental status:
– Advice on status of compliance with
environmental permit including the status of submissions under the
environmental permit
– Review of the key assumptions
adopted in the EIA Report
iii. Implementation status:
– Implementation status of
environmental protection and pollution control / mitigation measures, as
recommended in the EIA Report
iv. Monitoring results (in both hard and
diskette copies) together with the following information:
– Monitoring methodology
– Name of laboratory and types of equipment
used and calibration details
– Parameters monitored
– Monitoring locations
– Monitoring date, time frequency, and
duration
– Weather conditions during the period
/ monitoring
– Graphical plots of the monitored
parameters in the month annotated against:
○
The major activities
being carried out on site during the period
○
Weather conditions that
may affect the monitoring results
○
Any other factors which
might affect the monitoring results
○
QA / QC results and
detection limits
v.
Analysis of monitoring
results, non-compliance, complaints, and notifications of summons and status of
prosecutions:
– Analysis and interpretation of
monitoring results in the month
– Any non-compliance (exceedances) of
the environmental quality performance limits (Action and Limit Levels)
– Changes made that affect the
EM&A during the month
– Summary of environmental complaints
received including locations and nature of complaints, findings of the
investigation, actions and follow-up measures taken, and final status
– Notification of summons and status
of prosecutions for breaches of current environmental protection / pollution
control legislation, including locations and nature of the breaches,
investigation, follow-up actions taken, results and summary
– Reasons for and the implications of
non-compliance, complaints, summons and prosecutions including review of
pollution sources and working procedures
– Actions taken in the event of
non-compliance and deficiency, and follow-up actions related to earlier
non-compliance
vi. Others
– An account of the future key issues as
reviewed from the works programme and work method statements
– Comment on the solid and liquid
waste management status during the month including waste generation and
disposal records
– Outstanding issues and deficiencies
– Comments on effectiveness of the
environmental management systems, practices, procedures and mitigation
measures, recommendations (for example, any improvement in the EM&A
programme) and conclusions
– Review of the relevant key EIA
assumptions
vii. Appendix
– Monitoring schedule for the present
and next reporting period
– Cumulative statistics on complaints,
notifications of summons and successful prosecutions
– Outstanding issues and deficiencies
15.3.3.2
Some information concerning the
EM&A works, such as the EM&A requirements would remain unchanged
throughout the EM&A programme. In the subsequent monthly EM&A Reports,
the first monthly EM&A Report can be referred instead of repeating the
description of the unchanged information.
15.4
Quarterly
EM&A Report
15.4.1.1
A quarterly EM&A report should be
produced and should contain at least the following information. In addition,
the first quarterly summary report should also confirm if the monitoring work
is proving effective and that it is generating data with the necessary
statistical power to categorically identify or confirm the absence of impact
attributable to the works.
i.
Up to half a page
executive summary
ii.
Basic project
information including a synopsis of the project organization and programme, and
a synopsis of works undertaken during the quarter
iii. A brief summary of EM&A
requirements including:
– Monitoring parameters
– Environmental quality performance
limits (Action and Limit Levels)
– Environmental mitigation measures,
as recommended in the EIA Report
– Review of the key assumptions
adopted in the EIA Report
iv. Drawings showing the project area,
environmental sensitive receivers and the locations of the monitoring and
control stations
v.
Implementation status
of environmental protection and pollution control / mitigation measures, as
recommended in the EIA Report
vi. Graphical plots of the monitored
parameters over the past four months (the last month of the previous quarter
and the present quarter) for representative monitoring stations annotated
against:
– The major activities being carried
out on site during the period
– Weather conditions during the period
– Any other factors which might affect
the monitoring results
vii. Advice on the solid and liquid waste
management during the quarter including waste generation and disposal records
viii. A summary of non-compliance
(exceedances) of the environmental quality performance limits (Action and Limit
Levels)
ix. A brief review of the reasons for
and the implications of any non-compliance, including a review of pollution
sources and working procedures
x.
A summary description
of actions taken in the event of non-compliance and any follow-up procedures
related to any earlier non-compliance
xi. A summary of all environmental
complaints received including locations and nature of complaints, findings of
the investigation, actions and follow-up measures taken, and final status
xii. Comments on the effectiveness and
efficiency of the mitigation measures; recommendations on any improvements in
the EM&A programme and conclusions for the quarter
xiii. Proponents’ contacts and any hotline
telephone number for the public to make enquiries.
15.5
Annual
EM&A Report
15.5.1.1
An annual EM&A report should be
produced and should contain at least the following information.
i.
One to two pages of
executive summary
ii.
Basic project
information including a synopsis of the project organization and programme and
a synopsis of works undertaken during the past 12 months
iii. A brief summary of EM&A requirements
including:
– Monitoring parameters
– Environmental quality performance
limits (Action and Limit Levels)
– Environmental mitigation measures,
as recommended in the EIA Report
– Review of the key assumptions
adopted in the EIA Report
iv. Drawings showing the project area,
environmental sensitive receivers and the locations of the monitoring and
control stations
v.
Implementation status
of environmental protection and pollution control / mitigation measures, as
recommended in the EIA Report
vi. Graphical plots of the monitored
parameters over the past 12 months for representative monitoring stations
annotated against:
– The major activities being carried
out on site during the period
– Weather conditions during the period
– Any other factors which might affect
the monitoring results
vii. Advice on the solid and liquid waste
management during the past 12 months including waste generation and disposal
records
viii. A summary of non-compliance
(exceedances) of the environmental quality performance limits (Action and Limit
Levels)
ix. A brief review of the reasons for
and the implications of any non-compliance, including a review of pollution
sources and working procedures
x.
A summary description
of actions taken in the event of non-compliance and any follow-up procedures
related to any earlier non-compliance
xi. A summary of all environmental
complaints received including locations and nature of complaints, findings of
the investigation, actions and follow-up measures taken, and final status
xii. Comments on the effectiveness and
efficiency of the mitigation measures; recommendations on any improvements in
the EM&A programme and conclusions for the quarter
xiii. Proponents’ contacts and any hotline
telephone number for the public to make enquiries.
15.6
Final EM&A Review Report
15.6.1.1
The EM&A program could be
terminated upon completion of those construction activities that have the
potential to cause significant environmental impacts, and / or the completion
of post-construction monitoring requirements.
15.6.1.2
The proposed termination by the
Contractor should only be implemented after the proposal has been endorsed by
the AAHK / PM and IEC followed by final approval from the EPD.
15.6.1.3
The final EM&A report should
include, inter alia, the following information:
i. An executive summary
ii.
Basic project information
including a synopsis of the project organization and programme, contacts of key
management, and a synopsis of work undertaken during the entire construction
period
iii. A brief summary of EM&A
requirements including:
– Monitoring parameters
– Environmental quality performance
limits (Action and Limit Levels)
– Environmental mitigation measures,
as recommended in the EIA Report
– Review of the key assumptions
adopted in the EIA Report
iv. Drawings showing the project area,
any environmental sensitive receivers and the locations of the monitoring and
control stations
v.
Advice on the
implementation status of environmental and pollution control / mitigation
measures, as recommended in the EIA Report, summarised in the updated
implementation status pro forma
vi. Graphical plots of the monitoring
parameters over the construction period for representative monitoring stations,
including the post-project monitoring annotated against:
– The major activities being carried
out on site during the period
– Weather conditions during the period
– Any other factors which might affect
the monitoring results
– The baseline condition
vii. Compare the EM&A data with the
EIA predictions
viii. Effectiveness of the solid and
liquid waste management
ix. A summary of non-compliance
(exceedances) of the environmental quality performance limits (Action and Limit
Levels)
x.
A brief account of the
reasons the non-compliance including a review of pollution sources and working
procedures
xi. A summary of the actions taken
against the non-compliance
xii. A summary of all environmental complaints
received the investigation, actions and follow-up measures taken to address the
complaints
xiii. A review of the monitoring
methodology adopted and with the benefit of hindsight, comment on its
effectiveness (including cost effectiveness)
xiv. A summary of notifications of
summons and successful prosecutions for breaches of the current environmental
protection / pollution control legislations, locations and nature of the
breaches, investigation, follow-up actions taken and results
xv. A review of the practicality and
effectiveness of the EM&A programme (e.g. effectiveness and efficiency of
the mitigation measures), and recommendation on any improvement in the EM&A
programme
xvi. A conclusion to state the return of
ambient and / or the predicted scenario as per EIA findings
15.7
Data Keeping
15.7.1.1 No site-based
documents (such as monitoring field records, laboratory analysis records, site
inspection forms, etc.) are required to be included in the EM&A reporting
documents. However, any such document should be retained by the ETL /
Monitoring Team and be ready for inspection upon request. All relevant
information should be clearly and systematically recorded in the document.
Monitoring data should also be recorded in digital format, and the software
copy must be available upon request. Data format should be agreed with the AAHK
/ PM, IEC and EPD. All documents and data should be kept for at least one year
following completion of the construction contract and one year after the completion
of operation phase monitoring for construction phase EM&A and operational
phase EM&A respectively.
15.8
Interim
Notifications of Environmental Quality Limit Exceedances
15.8.1.1
For construction phase EM&A, with
reference to the Event and Action Plan, when the environmental quality
performance limits are exceeded, the ETL should immediately notify the AAHK /
PM, IEC and EPD, as appropriate and should keep them informed of the results of
the investigation, proposed remedial measures, actions taken, updated situation
on site, need for further follow-up proposals, etc. A sample template for the
interim notifications is shown in Appendix
F. The ETL may modify the interim notification form for this EM&A
programme, the format of which should be approved by AAHK / PM and agreed by
the IEC.
16
Reference
Bejder, L. (2005). Linking short and long-term effects of nature-based
tourism on cetaceans (Master’s thesis). Dalhousie University, Halifax, Nova
Scotia, Canada.
Chen, T., Hung, S. K., Qiu, Y., Jia, X. &
Jefferson, T. A. (2010). Distribution, abundance, and individual movements
of Indo-Pacific humpback dolphins (Sousa chinensis) in the Pearl River Estuary,
China. Mammalia, 74, 117-125.
Dierauf, L. and F. M. D. Gulland. (eds) (2001).
Handbook of Marine Mammal Medicine, second edition, CRC Press, Boca Raton,
Florida. 1063 pp.
Gailey, G. A. & Ortega-Ortiz, J. (2002). A note on a computer-based
system for theodolite tracking of cetaceans. Journal of Cetacean
Research & Management, 4(2), 213-218.
Gailey, G., Würsig, B. & McDonald,
T.L.(2007). Abundance, behavior, and movement patterns of western gray whales
in relation to a 3-D seismic survey, Northeast Sakhalin Island, Russia.
Environmental Monitoring and Assessment 134:75–91.
Gulland, F., H. Pérez-Cortés M., J. Urbán R.,
L. Rojas-Bracho, G. Ylitalo, J. Weir, S. A. Norman, M. M. Muto, D.., J. Rugh,
C. Kreuder and T. Rowles. (2005). Eastern North Pacific Gray Whale (Eschrichtius
robustus) Unusual Mortality Event, 1999-2000: A Compilation. U.S. Dep.
Commer. NOAA Tech Memo NMFS-AFSC-150. 33p.
Kuehl, D. W. and R. Haebler. (1995).
Organochlorine, organobromine, metal, and selenium residues in bottlenose
dolphins (Tursiops truncatus) collected during an unusual mortality
event in the Gulf of Mexico, 1990. Archives of Environmental Contaminants and
Toxicology 28: 494-499.
Lammers, M. O., Brainard, R. E., Au, W. W. L., Mooney, T. A. & Wong,
K. B. (2008). An ecological acoustic recorder (EAR) for long-term monitoring of
biological and anthropogenic sounds on coral reefs and other marine habitats. Journal
of the Acoustical Society of America 123:
1720-1728.
Lundquist, D., Gemmell, N., & Würsig, B. (2012). Behavioural
responses of dusky dolphin (Lagenorhynchus obscurus) groups to
tour vessels off Kaikoura, New Zealand. PLoS One:
7:1-9, e41969.
Martinez, E. (2010). Responses of South Island
Hector’s dolphin (Cephalorhynchus hectori hectori) to vessel activity
(including tourism operations) in Akaroa Harbour, Banks Peninsula, New Zealand
(Doctoral dis- sertation). Massey University, Auckland, New Zealand.
NOAA Fisheries. (2004). Interim Report on the
Bottlenose Dolphin (Tursiops truncatus) Unusual Mortality Event Along
the Panhandle of Florida
Sims, P. Q., Hung, S. K. & Würsig, B.
(2012). High-speed vessel noises in West Hong Kong waters and their
contributions relative to Indo-Pacific humpback dolphins (Sousa chinensis).
Journal of Marine Biology, 2012, pp. 11.
Turchin, P. (1998) Quantitative Analysis of
Movement: Measuring and modelling population redistribution in animals and
plants. Sinauer Associates, Inc., U.S.A.
Wilkinson, D. M. (1996). National Contingency
Plan for Response to Unusual Marine Mammal Mortality Events, NOAA
Technical Memorandum NMFS-OPR-9, 9/96, Silver Spring, MD.
Wilkin, S. M., J. Cordaro and F. Gulland. 2012.
An unusual mortality event of harbour porpoises (Phocoena phocoena) off
central California: Increase in blunt force trauma rather than an epizootic.
Aquatic Mammals 38:301–310.
Würsig, B., Cipriano, F. & Würsig, M.
(1991). Dolphin movement patterns: information from radio and theodolite
tracking studies. Pages 79-111 in K. Pryor and K. S. Norris eds. Dolphin
societies: Discoveries and puzzles. University of California Press.
[1] As
defined by the United States Army Corporation of Engineers (USACE)
classification system for silt curtains.
[2] Note,
exceedances refer to those that are attributable to DCM works as determined by
the findings of exceedance investigation reports.